SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2009 Supreme(Pat) 1452

PATNA HIGH COURT
Navaniti Prasad Singh, J.
M/s Zee Saheb Cosmetic Zone Null Through Its Proprietor Mr.Rajiv Ranjan Gupta
Versus
Bihar State Electricity Board
CWJC No. 15996 of 2009
Decided On : NOVEMBER 21, 2009

Assessment in cases of unauthorized use of electricity, including theft, must be made under Section 126 of the Electricity Act, 2003, and is appealable under Section 127, with the final determination subject to the Special Criminal Court's decision.

Headnote:

Electricity Theft - Assessment under Sections 126 and 135 of the Electricity Act, 2003 - Section 126, Section 127, Section 135, Section 154 - The court discussed the provisions of Section 126, Section 127, and Section 135 of the Electricity Act, 2003, and highlighted the appeal process and final determination by the Special Criminal Court in cases of unauthorized use of electricity, including theft. The court emphasized the need for assessment under Section 126, appealability under Section 127, and the final determination by the Special Criminal Court under Section 154.

Fact of the Case:

The petitioner's shop was inspected for alleged excess load and meter tampering, leading to provisional and final assessment bills. The petitioner challenged the final assessment, arguing deprivation of remedies and arbitrary assessment.

Finding of the Court:

The court found that assessment in cases of unauthorized use of electricity, including theft, must be made under Section 126 of the Act and is appealable under Section 127. The final determination is subject to the Special Criminal Court's decision.

Issues: The issues included the deprivation of remedies due to punitive assessment under Section 135, the delay in final assessment, inclusion of provisional assessment figures as dues, and misconceptions in the calculation and appeal process.

Ratio Decidendi: The court emphasized that assessment in cases of unauthorized use of electricity, including theft, must be made under Section 126, appealable under Section 127, and subject to the Special Criminal Court's determination. It also highlighted the impermissibility of including provisional assessment figures as dues and the misconceptions in the calculation and appeal process.

Final Decision: The court directed the petitioner to raise objections before the appellate authority in accordance with Section 127 of the Act and to file an appeal, considering the observations and directions provided by the court.

JUDGEMENT

1. Petitioner No. 1 is the firm name and style of the shop of petitioner No. 2 at Boring Road in the district of Patna. For the purposes of the said shop, in April 2006, an electric connection was taken from Patna Electric Supply Undertaking (PESU), an undertaking of the Bihar State Electricity Board under consumer category NDS-II which was a three phase low tension connection for a sanctioned load of 14 KW under Account No. 41801150/346162. Oh 28.4.2008, the Special Task Force (STF) of the Board conducted an inspection of the petitioners premises and, taking into account all load connected, they came to the conclusion that petitioners had an installed load of 14.836 KW which was rounded off to 15 KW and, thus, allegedly had an excess load of 1 KW. Accordingly, petitioners were served with a bill for additional load of Rs. 6,044/- and asked to pay additional amount for load enhancement both of which petitioners paid. It may be noticed here that the said inspection import has been annexed as Annexure-7 to the supplementary affidavit filed on behalf of petitioners after copy of it was served on the counsel for the Board immediately after arguments were concluded on the next day. The inspection report shows that there were 5 air conditioners of 1.5 tonnes, the total load of which was taken to be 10 KW (at the rate of 2,000 Watts each).

2. On 9.2.2009,. again an STF inspection was carried out in the petitioners premises. This time, it was alleged that there was meter tampering. A report was drawn up which is part of Annexure-C/1 to the counter affidavit of the Board. In the report, it would be seen that the total load was shown to be 14.240 and taken to be 15 KW. In the report, the inspecting authorities are alleged to have tested the meter which showed substantial reduction in meter recording. It was, accordingly, alleged that meter, being tampered, it was a case of theft of electricity in terms of Section 135 of the Electricity Act, 2003 .

3. At this juncture itself, one may note one important aspect of the said report dated 9.2.2009. Here again, it is clearly noted that there were 5 air conditioners of one and a half tonne each (as found in the earlier inspection dated 28.4.2008). But this time its load was assessed at the rate of 2500 Watts each but as per report, the total load was shown as 10,000 Watts as in the past. This I am taking note of because subsequently, while raising bills, authorities have corrected the figure 10,000 to 12.500. Thus, an enhancement of 2500 Watts was done for the same machines which were found in the earlier report and billed accordingly. As later would be seen, petitioners contention would be that because of this enhancement, they have been wrongly assessed at 17 KW instead of 15 KW load found. That makes a substantial difference.

4. Consequent to the said inspection, on 9.2.2009, the meter was removed and Buddha Colony Police Station Case No. 27 of 2009 instituted for an offence punishable under Section 135 of the Act. While lodging the first information report, which is part of Annexure-C/1 to the counter affidavit, it is alleged that because of theft, Board has suffered a loss of about Rs. 6,47,666/-. On 10.2.2009, a provisional assessment bill totalling to Rs 7,08,145/- is served. Alongwith this, a chart of calculation was also served. The two are Annexures-3A and 3B. This provisional bill is as a matter of punitive assessment as allegedly provided under Section 135 of the Act and includes fixed charge of Rs.8,160/- and cost of new meter, Rs. 5,000/- alongwith punitive assessment after adjustment of Rs. 6,94,985.18P. Petitioner filed a writ petition before this Court being CWJC No. 3309 of 2009. While the writ petition was pending, on 8.4.2009, petitioners were again served a similar bill with calculation chart being Annexures-3A and 3B respectively based on assessment of load found at 17 KW. The writ petition was finally disposed of by order dated 30.4.2009 (Annexure-4/A) where in t















Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top