PATNA HIGH COURT
Ramesh Kumar Datta, J.
M/s S.K.Food Product
Versus
Bihar State Electricity Board Having Its Office Situated At Vidhyut Bhawan
Civil Writ Jurisdiction Case No. 16396 of 2008
Decided On : MARCH 3, 2009
1. The interlocutory application has been filed for amendment in the relief claimed in the writ application by addition of the prayer so as to challenge the letter dated 31.10.2008 and the punitive bill dated 29.10.2008 forwarded with the said letter which have been annexed as Annexures-4 and 4/A respectively.
2. The said actions of the respondent- Board being in continuance of the action challenged in the writ petition, the prayer for amendment is allowed.
3. LA No. 6688 of 2008 is accordingly, disposed of.
4. Heard iearned counsel for the petitioner and learned counsel for the Bihar State Electricity Board.
5. The writ petition has been filed for a direction to the respondent-Board to install a new meter in the business premises of the petitioner and also to restore the electrical connection and further quash the letter dated 31.10.2008 as also the enclosed punitive bill dated 29.10.2008 alongwith the said letter (Annexures-4 and 4/A).
6. The petitioner has a H.T.I.S. electrical connection with a contract demand of 80 K.V.A. from the respondent-Bihar State Electricity Board. An electronic meter was installed in the year 2007 in the business premises of the petitioner and the petitioner claims to have been regularly paying its bill for energy consumption. On 29.1.2008, after mid-night the electricity went off and after some time around 1 A.M. in the night it was realized that there was some smell of burning and thereafter on further investigation the staff saw fumes in the Meter Room and the meter was burning. Since the Meter was burning, the fire was extinguished by using fire extinguishing equipment and Mangal Talab Power Sub-Station was informed regarding the same. The petitioner claims to have informed the authorities of the Board in writing on 22.9.2008 itself in the morning. However, according to the officials of the Board, the 11 K.V. Feeder had tripped at 00.30 hours on 22.9.2008 showing earth fault at Mangal Talab Power Station and during the patrolling it was said by staff of the petitioner that a sound of blast was observed in metering unit during the trial of 11 KVA line; in the said circumstances, the supply of line of the petitioner was disconnected and the general line of the Feeder was restored at 2 A.M. in the early hours of the day. It is stated that no information was sent about the fire by the staff of the petitioner at night or even to the Board personnel who were on patrolling duty. Thereafter the admitted position is that an inspection was made on 22.9.2008 itself and a report was prepared. In the said report the details found during the inspection are mentioned but no conclusion has been drawn regarding any tampering with the meter although the report is merely on the factual aspect of the matter without drawing any conclusions. Subsequently on 26 9.2008 another inspection was made and after the said inspection, an F.I.R. was lodged against the petitioner under Sections 135 and 138(d) of the Electricity Act and under Sections 379, 415, 420, 467 and 472 of the Indian Penal Code.
7. Thereafter by letter dated 31.10.2008, a provisional punitive bill for Rs. 75,37,455.27/- was sent to the petitioner. It is pointed out by learned counsel for the petitioner that in the F.I.R. it was stated that a loss of approximately Rupees Thirty One Lacs was caused to the Board by the said theft of electricity.
8. Learned counsel for the petitioner submits that the action of the authorities of the Board is contrary to the provisions of paragraphs 8.19 and 8.20 of the Bihar Electricity Supply Code, 2007, which lays down the detailed procedure in case of burning of meter as also for testing of such a meter before any conclusion can be drawn regarding tampering or any other deliberate act by the consumer to interfere with the meter. It is contended that only after such a finding is recorded after testing of the meter that the consumption can be assessed under Section 126 of the Electricity Act and punished under the
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.