2011 Supreme(Pat) 1939
PATNA HIGH COURT
Mungeshwar Sahoo, J.
Modi Brothers
Versus
State Of Bihar
First Appeal No. 835 of 1979
Decided On : SEPTEMBER 13, 2011
Important Points
Subject
Civil Law - Contract Law
Act Referred
Headnote
Money Suit - Bolder Pitching Work - Section 80 C.P.C. - Arbitration Act - [Section 80 C.P.C.] - [Summary of Acts and Sections: The court discussed the validity of the notice served under Section 80 C.P.C. and the applicability of the Arbitration Act. The court also referred to the clauses of the agreement and the relevant documents to determine the entitlement of the plaintiffs for the claimed amount.]
Fact of the Case:
The plaintiffs filed a money suit for the realization of money amounting to Rs.1,61,463.23 for bolder pitching work. The defendant contested the suit, claiming that the plaintiffs failed to complete the work within the stipulated period and that the remaining work was done by another agency due to the plaintiffs' negligence.
Finding of the Court:
The court found that the plaintiffs failed to prove that the government officials were responsible for the slow progress of the work. It also held that the suit was not maintainable due to improper service of notice under Section 80 C.P.C. The court dismissed the suit.
Issues: The issues included the maintainability of the suit, the validity of the notice under Section 80 C.P.C., and the entitlement of the plaintiff to the relief claimed.
Ratio Decidendi: The court held that the plaintiffs were not entitled to the claimed amount as they failed to complete the work within the stipulated period and the remaining work was done by another agency. It also found that the notice under Section 80 C.P.C. was validly served.
Final Decision: The First Appeal was dismissed, and no costs were awarded.
Mungeshwar Sahoo, J.
1. This First Appeal has been filed by the plaintiffs-appellants against the judgment and decree dated 28.07.1979 passed by Sri Budhdeo Narayan Sinha, the learned 3rd Additional Subordinate Judge at Sasaram in Money Suit No.173 of 1966/1 of 1979 dismissing the plaintiffs-appellants suit for realization of money amounting to Rs.1,61,463.23.
2. The plaintiffs-appellants filed the aforesaid money suit no.173 of 1966/1 of 1979 alleging that in September, 1962, tender 2 was invited by the respondent for the work of bolder pitching in apron and slop on Western Guide Bank Barrage Project, Indrapuri, Dehri-on- sone, Sahabad, Bihar. The plaintiffs tender was accepted by the respondent on 12.09.1962 and a contract was signed and work order was issued on 18.10.1962. Both parties entered into agreement dated 10.11.1962. Pursuant to the said contract, the plaintiffs went to the site with his staffs on 06.12.1962 but plaintiffs were allowed to commence the work only on 26.12.1962. The plaintiffs completed the work on 24.07.1963. The defendant did not take the progress work measured and paid only Rs.5,49,086 from time to time against the value of work of Rs.6,93,681.23. There were some short measurement and in some cases no measurement at all and in some cases, there were less measurement i.e. relating to item nos.2 and 3 and there were no measurement relating to item nos.4 and 5 of the contract. The plaintiffs were put to loss due to the fault and negligence of the defendant employees and the plaintiffs were not responsible for the loss suffered by the defendant for which compensation was claimed in the bill. Deductions were made from the security amount and still Rs.22,000 security deposit is with the defendant. The plaintiffs are entitled to get back the same also.
3. The plaintiffs served notice under Section 80 C.P.C. on 24.05.1966 and thereafter, receiving the notice, Executive Engineer sent a cheque for Rs.5100.32 with respect to the security deposit. Accordingly, the plaintiffs filed the suit for realizing the aforesaid amount.
4. The defendant on being noticed appeared and filed contesting written statement. The defendant admitted the agreement dated 10.11.1962 and the issuance of work order on 18.10.1962. It is stated that in fact, the site was made available to the plaintiffs on 06.12.1962 but the plaintiffs started working on 25.12.1962. The plaintiffs were required to complete the work within 31.05.1963 but failed to complete the work within the stipulated period which was essence of the contract. The plaintiffs were given repeated reminders to complete the work and it was stipulated that the time is the essence of contract but failed to complete the work and requested for extension of time. However, the time was extended till 25.07.1963. Since the plaintiffs were negligent and were not able to complete the work within the time, the department engaged another agency to complete the work before the monsoon break according to the clause nos.2 and 3 of the agreement. The plaintiffs completed the work till 25.07.1963 only upto 10,93720 Cubic feet bolder pitching out of the stipulated 15.95 lacs Cubic feet and the remaining work was done by the other agency on higher rate at the risk of the plaintiffs and, therefore, the said excess amount paid to the other agency has been deducted from the security deposit of the plaintiffs amounting to Rs.17,931.68. All other allegations made by the plaintiffs were denied. The defendant further alleged that the notice under Section 80 was not served according to the provision on the proper authority; therefore, in the eye of law, there was no service of notice under Section 80 C.P.C.
5. On the basis of the aforesaid pleadings of the parties, the learned Court below framed the following issues:
I. Is the suit as framed maintainable?
II. Has the plaintiff got valid cause of action for the suit? III. Is the service of notice under Section 80 C.P.C. illegal being not in pr