2015 Supreme(Pat) 303

IN THE HIGH COURT OF JUDICATURE AT PATNA
JYOTI SARAN, J.
Md. Masiha – Petitioner
Versus
State of Bihar & Others – Respondents
CWJC No. 360 of 2015 & I.A. No. 144 of 2015
Decided On : 13.2.2015

Advocates:
Advocate Appeared:
For the Petitioners: Mr. Farooq Ahmad Khan.
For the Respondent-State: Mr. Devendra Kumar Sinha, Mr. Alok Kr. Rahi.
For the Mines Department: Mr. Rajendra Prasad.

The main legal point established in the judgment is that once an exercise has been completed, the principles of promissory estoppel and legitimate expectation prevent a turning around of decisions, and whimsical actions by the department leading to loss of revenue are not justified.

Headnote:

TENDER - Settlement of Balughat - [Mines and Geology Department, Government of Bihar] - [Annexure-9, Annexure-10, Annexure-11] - The court discussed the completion of the exercise for settlement of Balughat, the technical bid of the petitioner, and the recommendations of the Collector and Tender Committee. The court highlighted the principles of promissory estoppel and legitimate expectation, emphasizing that the department's decision to order a fresh auction after the exercise was completed was whimsical and led to loss of revenue for the State.

Fact of the Case:

The petitioner challenged an order directing a fresh auction for settlement of Balughat, arguing that the exercise had been completed and the decision of the Tender Committee and the recommendation of the District Magistrate should be conclusive and binding.

Finding of the Court:

The court found that the department's decision to order a fresh auction after the completion of the exercise was vague, non-descriptive, and led to loss of revenue for the State without any accountability.

Issues: The main issue was whether the department's decision to order a fresh auction for settlement of Balughat after the completion of the exercise was justified.

Ratio Decidendi: The court emphasized the principles of promissory estoppel and legitimate expectation, stating that once the exercise had been completed, there could be no turning around, and the department's decision was whimsical and led to loss of revenue for the State.

Final Decision: The court set aside the order of the department and directed the department to proceed in the matter in the light of the decision of the Tender Committee and the recommendations of the Collector for completion of the formalities. The writ petition was allowed, and the interlocutory application was disposed of.

JUDGMENT

JYOTI SARAN, J.

1. Heard Mr. Farooq Ahmad Khan, learned counsel appearing on behalf of the petitioner, Mr. Devendra Kumar Sinha, learned Additional Advocate General No. 2 representing the Mining Department.

2. The petitioner is aggrieved by the order dated 30.12.2014 issued under the signature of Joint Secretary-cum-Director, Mines and Geology Department, Government of Bihar, a copy of which is placed at Annexure-1 to the writ petition whereby while responding to the recommendation dated 26.11.2014 of the District Magistrate-cum-Collector, Madhubani for settlement of Balughat at Madhubani with the petitioner, a direction has been issued to hold a fresh auction in the interest of Government revenue.

3. It is the argument of Mr. Khan, learned counsel appearing for the petitioner that it is after three round of exercise undertaken by the respondent-Department that finally the technical bid of the petitioner was found to be the most appropriate and since it was above the reserve Jama hence the Collector, Madhubani while discussing the matter in detail, has recommended for settlement in his favour vide letter dated 26.11.2014 (Annexure-10) and with a reminder on 27.12.2014 placed at Annexure-11 but it has been responded to by the impugned order.

4. He submits that in the first round there was no tenderer responding to the notice which resulted in second round tender in which it was the petitioner alone who applied and thus while maintaining the offer made by petitioner that the department went for a third tender in which one more person, namely, Tej Narain Yadav only applied, however since the technical bid of said Tej Narain Yadav was rejected, it left the petitioner alone in the contest.

5. It is submitted that since there remained only one contestant in the contest that the District Magistrate, Madhubani sought instruction from the headquarter and vide letter dated 17.11.2014 of the Headquarters, the District Magistrate was required to complete the formalities following which the Tender Committee held its meeting on 26.11.2014 when the financial bid of the petitioner was opened and was found at Rs. 78,70,000/- i.e. above the reserve Jama which was fixed at Rs. 78,67,200/-. The Tender Committee consisting of the Mining Officer, Madhubani, Commercial Tax Officer, Madhubani, Senior Deputy Collector (Revenue), Madhubani, the Additional Superintendent of Police, Madhubani and the Collector, Madhubani recommended for settlement of Balughat in favour of the petitioner, a copy of which is placed at Annexure-9 and it is following such recommendation that the Collector after discussing the entire matter has given his recommendation in favour of the petitioner on 26.11.2014 placed at Annexure-10 which recommendation was reiterated in his letter dated 27.12.2014 placed at Annexure-11. He submits that although such exercise was undertaken after approval by the headquarters, yet when the recommendation of the Collector reached the Joint Secretary –cum- Director for his approval that he has chosen to reject the same and directed for fresh order.

6. Mr. Khan learned counsel appearing for the petitioner has submitted that the exercise having been completed it is no more open for the respondents to set at naught the exercise and the decision of the Tender Committee and the recommendation of the District Magistrate would be conclusive and binding. Learned counsel has relied upon a decision of this Court reported in State of Bihar vs. P.E.C. Limited, 2004 (3) PLJR 741 paragraph 10 to submit that once the technical bid of the petitioner was opened and was found above the reserve Jama there was no turning around for the respondents.

7. Mr. Khan has also referred to a Bench decision of this Court reported in M/s. Vijay Raj Mewar Construction Co. Pvt. Ltd. vs. State of Bihar, 2006 (3) PLJR 503 paragraph 6 and Mandar Madhusudan Bahudhandhi Swablambi Sahkari Samitee Ltd. vs. State of Bihar, 2007 (2) PLJR 27 paragraph-10 to submit that once the ex









Click Here to Read the rest of this document