2016 Supreme(Pat) 599

IN THE HIGH COURT OF JUDICATURE AT PATNA
Vikash Jain, J.
M/s. BCL Secure Premises (P) Ltd. & Ors. - Petitioners
Versus
The Union of India through General Manager, East Central Railway Hajipur & Ors. - Respondents
Civil Writ Jurisdiction Case Nos. 10537, 10590 of 2012 & 18991 of 2013
Decided On : 04-07-2016

Advocates:
Advocate Appeared:
For the Petitioner: Mr. Alok Tripathi, Mr. Rajeev Ranjan, Mrs. Bela Singh
For the Respondents: Mr. Anil Kumar Sinha

The definition of 'Tender documents or Tender papers' and the applicability of forfeiture of EMD in the context of changes made in the tender document.

Headnote:

Tender Forfeiture - Railway Tender - [General Conditions of Contract, Special Conditions of Contract, Instructions to Tenderers and conditions of tendering, Technical Supplement and Specifications, Preamble Schedule of Work & Supplies including all Annexure and forms etc.] - The court set aside the forfeiture of the petitioner's EMD as the tender in question had been discharged by the respondents themselves, and the definition of 'Tender documents or Tender papers' did not include documents of the financial bid under the Two Packet Open Tendering System.

Fact of the Case:

The petitioner filed a writ petition seeking to quash an impugned letter and to finalize a tender in their favor. The petitioner confined the relief sought to the forfeiture of the Earnest Money Deposit (EMD) and did not press the remaining prayers.

Finding of the Court:

The court found merit in the petitioner's submission that the tender in question had been discharged by the respondents themselves, and the definition of 'Tender documents or Tender papers' did not include documents of the financial bid under the Two Packet Open Tendering System.

Issues: Forfeiture of Earnest Money Deposit (EMD) and changes made in the tender document by the petitioner.

Ratio Decidendi: The court set aside the forfeiture of the petitioner's EMD as the tender in question had been discharged by the respondents themselves, and the definition of 'Tender documents or Tender papers' did not include documents of the financial bid under the Two Packet Open Tendering System.

Final Decision: The impugned order dated 04.06.2012 was set aside to the extent of forfeiture of the petitioner's EMD, and the respondents were directed to ensure the refund of the EMD to the petitioner.

JUDGMENT :

Vikash Jain, J.

Heard learned counsel for the petitioners and learned counsel for the respondent Railway.

2. The present writ petition has been filed with a prayer for quashing and setting aside the impugned letter No. ECR/S&T/OT/ 140/Pt-III dated 04.06.2012 (Annexure-P/15) issued from the office of respondent no. 2; directing the respondents to finalise the Tender No. ECR/S&T/OT/140 (Annexure-2) and issue Letter of Acceptance (LoA) in favour of the petitioner being the technically qualified lowest bidder; directing the respondents to decide the tender No. ECR/S&T/OT/140 in terms of the judgment dated 04.06.2012 (Annexure-P/11) passed by this Court in CWJC No. 10256 of 2012; and for connected reliefs.

3. When the matter is taken up for disposal, learned counsel Mr. Alok Tripathi appearing for the petitioner confines the relief sought in the present writ petition to the extent of forfeiture of the Earnest Money Deposit (EMD) of Rs. 12,56,160/- deposited by the petitioner and does not press the remaining prayers.

4. It is submitted on behalf of the petitioner that the impugned order dated 04.06.2012 (Annexure-P/15) is arbitrary and unsustainable. Learned counsel for the petitioner submits that if according to the impugned letter itself the tender in question was discharged, the question of the EMD being liable for forfeiture did not arise and the same was bound to be refunded to the petitioner. Learned counsel for the petitioner further invites attention to para 4.1.3 of the minutes of the tender committee meeting held on 12.01.2012 and 18.01.2012 (Annexure-R/2), according to which the petitioner is said to have made changes/additions/deletions in its financial bid, as incorporated in the table therein. It is submitted that the EMD might have been made liable for forfeiture in the event of the petitioner making changes in the 'tender documents' downloaded from website as provided in clause 2(b) of the Tender Notice. Reference to para 1.2 of the 'Instructions to Tenderers and Conditions of Tendering' discloses the nature of documents included within the meaning of the phrase 'Tender documents or Tender papers', which reads as follows :-

"1.2 The General Conditions of Contract applicable to Civil Engineering Works corrected up to date, Special Conditions of Contract, Instructions to Tenderers and conditions of tendering, Technical Supplement and Specifications, Preamble Schedule of Work & Supplies including all Annexure and forms etc. shall hereafter be collectively referred to as the "Tender documents or Tender papers" If there is any conflict between the conditions given in this tender document & GCC, the former shall prevail."

It is submitted that under the Two Packet Open Tendering System as in the present case, none of the documents contemplated in para 1.2 contemplates documents comprising the financial bid and as such the action taken by the respondents for changes/additions/deletions said to have been made with reference to the financial bid, is completely dehors the 'Instructions to Tenderers and Conditions of Tendering'.

5. Learned counsel for the respondents on the other hand reiterates that changes having been made in the tender document by the petitioner, the action by way of forfeiture of the EMD had rightly been taken against the petitioner. He invites attention to para 3 of the supplementary minutes of the tender committee meeting held on 26.04.2012 (Annexure-R/3) whereby the Tender Committee, differing with the view of the Tender Accepting Authority, had expressed its opinion that para 2 of the Tender Notice was applicable also in respect of financial bid.

6. Having heard the parties and on a careful consideration of the materials on record, this Court finds considerable merit in the submission of learned counsel for the petitioner. In view of the fact that the tender in question has been discharged by the respondents themselves being not in dispute, the petitioner cannot be held liable for default in order to i