SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1973 Supreme(Cal) 287

HIGH COURT OF CALCUTTA
S. A. Masud
BRIJLAL AND CO. - Appellant
Versus
MADHYA PRADESH ELECTRICITY BOARD - Respondent
Commercial Cause Suit 477  Of  1972
Decided On : NOVEMBER 27, 1973

The issues in two suits must be directly and substantially the same for a stay of one suit to be granted under Section 10 of the Code of Civil Procedure, 1908.

Headnote:

STAY OF SUIT - SECTION 10 OF THE CODE OF CIVIL PROCEDURE, 1908 - ISSUES IN CALCUTTA HIGH COURT SUIT NOT DIRECTLY AND SUBSTANTIALLY THE SAME AS IN JABALPUR SUIT - STAY OF CALCUTTA SUIT REFUSED.

Fact of the Case:

The plaintiff, a contractor, filed a suit in the Calcutta High Court against the defendant, Madhya Pradesh Electricity Board (Board), for damages arising out of an alleged breach of contract. The Board had earlier filed a suit in Jabalpur against the contractor for refund of the price paid for defective and short supplies of goods. The Board applied for a stay of the Calcutta suit under Section 10 of the Code of Civil Procedure, 1908, arguing that the issues in both suits were directly and substantially the same.

Finding of the Court:

The court held that the issues in the Calcutta suit were not directly and substantially the same as those in the Jabalpur suit. The contractor's claim in the Calcutta suit was much more comprehensive than the Board's claim in the Jabalpur suit, as it included claims for damages for breach of contract on various grounds, including the alleged cancellation of the contract and the failure to give despatch instructions for the balance of the contracted goods.

Issues: Whether the issues in the Calcutta High Court suit were directly and substantially the same as those in the Jabalpur suit, such that a stay of the Calcutta suit under Section 10 of the Code of Civil Procedure, 1908, was warranted.

Ratio Decidendi: The court held that the issues in the two suits were not directly and substantially the same, as the contractor's claim in the Calcutta suit was much more comprehensive than the Board's claim in the Jabalpur suit. The court also noted that the contractor had already filed a suit and paid court fees in Calcutta, and that allowing the counterclaim in the Jabalpur suit would require the contractor to pay court fees again.

Final Decision: The court dismissed the Board's application for a stay of the Calcutta suit.

S. A. MASUD, J.

( 1 ) THIS is an application on behalf of the defendant-respondent under Section 10 of the Code of Civil Procedure, 1908 for stay of the plaintiff's suit in this Hon'ble Court. The relevant facts are stated as follows.

( 2 ) IN 1970 Madhya Pradesh Electricity Board, a statutory body, hereinafter described as "the Board", had invited tenders for the supply of galvanised bolts and nuts for high tension and transmission lines. The terms and conditions of supply, specification of the bolts and nuts and quantity were contained in the Board's specification (1) "project TR-47". The plaintiff M/s. Brijlal and Company a registered partnership firm at 22, Burtolla Street, Calcutta, hereinafter described as "the Contractor" duly submitted its tender which was accepted by the Board. Free samples of bolts and nuts were submitted fay the Contractor to the Board. The said samples were approved and formal order was placed by the Board on 30th October. 1970. It was agreed between the parties that the petitioners would open a Letter of Credit in Calcutta after receipt of the security deposit from the Contractor. The contractor submitted the Bank guarantee in respect of security deposit which was accepted by the Board on November 30, 1970. The Board also issued instructions for opening the Letter of Credit on the Central Bank of India, Brabourne Road Branch, Calcutta. The said letter of Credit was opened for Rs. 5. 09. 422. 92 P. , being 95% of the value of 151 tonnes and 2200 Nos. of galvanised bolts and nuts including inter-State Sales Tax @ 3%. The Contractor's case, however, is that the Board should have opened the Letter of Credit for a sum of Rs. 16. 69,941. 90 P. which, according to the Contractor, was total contracted price for goods to be supplied, exclusive of sales tax and Rs. 50. 098. 26 P. which would be the sales tax @ 3% on the said full value. According to the petitioner, the Contractor commenced the despatch of bolts and nuts on or about 6th December, 1970. The parties subsequently agreed that the goods should be sent on the basis of "freight to pay" and not "freight paid". According to the Board, since February, 1971, the Contractor was supplying bolts and nuts not according to the specifications and that the goods were defective. The said defective supplies constituted gross breach of the terms and conditions of the contract. It has been alleged that the Contractor failed to replace the said defective goods. Further, the contractor also committed breach of contract on the ground of short supply of the goods. Under these circumstances the Board cancelled the order for the balance quantity of the goods on April 6, 1971.

( 3 ) THE contractor instituted a suit being Suit No. T. S. 330 of 1971 at the City Civil Court, Calcutta for a declaration that the contract between the parties was still subsisting, for injunction restraining the Board from claiming encashment of the security from the Rank of India, and for other reliefs. On August 21, 1971 a written statement was filed by the Board in the said City Civil Court suit. On March 12, 1972 the Board instituted a Civil Suit No. 1-B of 1972 (Madhya Pra-desh Electricity Board v. Brijlal and Company) praying for a decree for a sum of Rs. 1,45,940. 13 p. , Rs. 3,891. 68 p. and for other reliefs. In September, 1972 the contractor made an application before the City Civil Courts for withdrawal of their suit. By an order dated September 12, 1972 the contractor was. permitted to withdraw the suit with liberty to bring a fresh suit of a comprehensive nature on the same subject-matter. On September 15, 1972 a Writ of Summons of the Jabalpur Suit filed by the Board was served on the Contractor. On September 29. 1972 the present suit was instituted in Calcutta by the Contractor against the Board. In January, 1973 the contractor filed their written statement in the Jabalpur Suit. On February 12. 1973 the present application has been filed.

( 4 ) THE short point to be decided i











Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top