SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1964 Supreme(Cal) 73

HIGH COURT OF CALCUTTA
H. K. Bose, G. K. Mitter
B. K. DHAR (PRIVATE) LTD. - Appellant
Versus
UNION OF INDIA - Respondent
A. F. O. O.  246  Of  1962
Decided On : MARCH 20, 1964

Advocates Appeared:
Ajit Chaudhary, B.K.SEN, P.P.Ginwalla

A party who has knowledge of the circumstances on which he might have founded an objection to the Arbitrator proceeding to make his award, but who submits to the arbitration going on and allows the Arbitrator to deal with the case as it stands, taking its chance of the decision being more or less favorable to it, will be deemed to have waived his right to challenge the Award on the ground of irregularity.

Headnote:

ARBITRATION - Setting aside of Award - Error of law apparent on the face of the Award - Compensation for delay - Cancellation of contract - Waiver of right to challenge Award on ground of irregularity.

Fact of the Case:

Appellant, a construction company, entered into a contract with the President of India for the construction of a Canteen-cum-Rest Room. The contract contained a clause providing for compensation for delay in completion of the work. The work was delayed due to faulty designing and planning by the Military Engineering Service (M.E.S.), and the contract was subsequently cancelled by the respondent on the ground of appellant's default. The appellant filed a statement of case before the Arbitrator, who awarded in favor of the respondent, including compensation for delay. The appellant filed an application to set aside the Award on the grounds of error of law and misconduct of the Arbitrator.

Finding of the Court:

The Court held that there was no error of law apparent on the face of the Award. The Arbitrator was not required to give reasons for allowing the claim for compensation for delay, and there was no indication that he had decided any question of law relating to the interpretation of the relevant clauses of the contract. The Court also held that the appellant had waived its right to challenge the Award on the ground of irregularity by failing to make any protest or objection during the arbitration proceedings.

Issues: 1. Whether there was an error of law apparent on the face of the Award. 2. Whether the appellant had waived its right to challenge the Award on the ground of irregularity.

Ratio Decidendi: 1. An error of law apparent on the face of the Award is a ground for setting aside the Award, but only if the error is material to the decision. 2. A party who has knowledge of the circumstances on which he might have founded an objection to the Arbitrator proceeding to make his award, but who submits to the arbitration going on and allows the Arbitrator to deal with the case as it stands, taking its chance of the decision being more or less favorable to it, will be deemed to have waived his right to challenge the Award on the ground of irregularity.

Final Decision: The appeal was dismissed, and each party was ordered to bear its own costs.

H. K. BOSE, C. J.

( 1 ) THIS is an appeal from an order of A. N. Ray, J. dismissing an application for setting aside an award. The appellant is a company incorporated under the Indian Companies Act, 1913 and carries on inter alia the business of building and construction at 6 Hasting Street, Calcutta. The appellant entered into a contract in writing, dated the 30th December, 1954 with the President of India represented by the Acting Chief Engineer, Eastern Command, for construction of a Canteen-cum-Rest Room for the Gun and Shell Factory at Cossipore for a lump sum of Rs. 2,11,827 in accordance with the terms, conditions and specifications set out in the documents constituting the contract The work to he done under the contract consisted of dismantling or demolishing the existing structure and construction of Canteen-cum-Rest Room building complete with sanitary fittings, fixtures, etc. The time for completion of the entire work was twelve months from the date of handing over of the site and the contract also contained clauses for deviations or alterations in the work and also for suspension of execution of the work during its progress. There was also a clause providing for compensation for delay in completion of the work. This is numbered as Clause (50) of the contract and provides that if the contractor fails to complete the work and clear the site on or before the date of completion, he shall without prejudice to any other right or remedy of Government on account of such breach be liable to pay as compensation an amount equal to one per cent of the contract sum for every week that the whole of the work remains uncompleted but the total amount of compensation shall not exceed ten per cent of the contract sum and the amount found due on account of such compensation may be adjusted or set off against any sum payable to the contractor under the contract. There is also a clause in the contract providing for cancellation for contractor's default. This is clause 54. There is a clause for arbitration being Clause 69. Pursuant to this contract the appellant received a Works Order, dated 31st January, J935 and under it the date of completion of the work was stated to be 30th January, 1950. But it appears that it was discovered shortly after this Works Order was given, that the site chosen by the Military Engineering Service (described hereinafter as M. K. S.) for the Canteen-cum-Rest Room interfered with the drainage of other existing structures in the vicinity and/or with drains already constructed. As a result of this faulty designing and planning of the part of the M. K. S. the latter had to direct suspension of the work and such suspension was made on 30th April, 1955. On 29th February, 1956 the appellant ultimately received written instructions that the original site was to be shifted 6'--9" to the North and 5'--7 1/2" to the East and the actual site was thus made over to the appellant on the 29th February, 1956. Thereafter for certain other reasons the progress of the work under the contract had to be suspended from time to lime, with the. result that the completion of the work was considerably delayed and the appellant was constrained to ask for increase of the rates and negotiation of fresh rates for execution of the work, but on 9th May 1957 the M. E. S. cancelled the contract on the. ground that the appellant had been guilty of default. Thereafter certain joint measurement was made in respect of the work executed by the appellant and for the unexecuted portion of the work a contract was entered into with another company known as Prakash Chandra (Private) Ltd. Thereafter the appellant required the respondent to appoint an Arbitrator in accordance with the terms of the contract and to refer the disputes between the appellant and the respondent for arbitration and on the 4th June 1958 the Engineer-in-Chief, Army Head Quarters, New Delhi, appointed M. L. Rahaja, Superintending Engineer as sole Arbitrator. In the meantime the a















Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top