1959 Supreme(Cal) 41

HIGH COURT OF CALCUTTA
K. C. Das Gupta, R. S. Bachawat
ARYAN MINING AND TRADING CORPORATION LTD. - Appellant
Versus
B. N. ELIAS AND CO. LTD. - Respondent
A. F. O. D 100  Of  1955
Decided On : FEBRUARY 18, 1959

Important Points

An agreement to extend the time for performance of a contract is binding on both parties and the seller is bound to deliver on the extended date.

Subject

Contract Law - Sale of Goods

Headnote

CONTRACT - SALE OF GOODS - EXTENSION OF TIME FOR PERFORMANCE - EFFECT - DAMAGES - ASSESSMENT.

Fact of the Case:

The subject matter of the suit was a contract for the sale of manganese ore. The contract was entered into on 26-12-1950, whereby Aryan Mining and Trading Corporation Limited agreed to sell to B. N. Elias and Co. Ltd. , 4000 tons of manganese ore with 46/48 per cent. , manganese contents at Rs. 82 per ton F. O. R. Barabil, delivery--500 tons monthly beginning from February, 1951 to be completed by December, 1951 latest. Under this contract the buyer deposited with the seller a sum of Rs. 1,20,000/- as advance. After giving credit for certain sums due to the seller for price of goods sold and delivered. B. N. Elias and Co. Ltd. claimed a sum of Rs. 56,919-4-9 by way of refund of the advance. At the trial it was conceded that the seller was entitled to a credit for a further sum of Rs. 13,624-4-9 on account of price of goods sold and delivered. Bose J. , has given a decree for refund of the balance sum of Rs. 43,294-15-9 on account of advance and a further sum of Rs. 244-12-9 for underloading and analysis charges. The correctness of this part of the decree is not challenged. It appears that under this contract 2,302 tons and 10 Cwt. of goods remained undelivered. There is now no dispute that all deliveries made by Aryan Mining and Trading Corporation Limited are to be appropriated towards the contract dated 26-12-1950 which is the subject-matter of this suit and that 2,302 tons and 10 cwt. of goods remained undelivered under this contract. The buyer alleges that the seller committed breach of the contract by not delivering the balance goods and it claims damages on the footing that the due date of delivery was extended up to 31-3-1952. Bose J. , has accepted the buyer's contention that the due date was extended as alleged by the buyer and has awarded damages on that footing. The correctness of his findings on this point is challenged.

Finding of the Court:

The court found that the due dates of delivery were extended as alleged by the buyers in the two suits. The court also found that the seller had committed breaches of both contracts. The court further found that the agreements as to the extension of the time for performance were binding on both parties and that the seller was bound to deliver on the extended dates. The court also found that the damages in respect of the B. N. Elias and Co. Ltd. , contract should be assessed on the basis of the market rates prevailing on the 31st March, 1952 and that damages in respect of the other contract should be assessed on the basis of the market rate prevailing on the 29th February, 1952.

Issues: 1. Whether the due dates of delivery were extended as alleged by the buyers? 2. Whether the seller had committed breaches of both contracts? 3. Whether the agreements as to the extension of the time for performance were binding on both parties? 4. Whether the seller was bound to deliver on the extended dates? 5. Whether the damages in respect of the B. N. Elias and Co. Ltd. , contract should be assessed on the basis of the market rates prevailing on the 31st March, 1952? 6. Whether damages in respect of the other contract should be assessed on the basis of the market rate prevailing on the 29th February, 1952?

Ratio Decidendi: 1. The court relied on the decision of the Privy Council in Muhammad Habidullah v. Bird and Company, 48 Ind App 175 : (AIR 1922 PC 178) to hold that the appellant being in breach, damages have to be calculated in the ordinary way on the basis of the substituted date, namely the 31st March, 1952 and the 29th February, 1952. 2. The court also relied on Sections 55 and 63 of the Indian Contract Act to hold that the agreements as to the extension of the time for performance were binding on both parties and that the seller was bound to deliver on the extended dates.

Final Decision: The court dismissed Appeal No. 45 of 1955 with costs. The court allowed Appeal No. 100 of 1955 to the extent that a decree for Rs. 114000/- be substituted in lieu of the decree for Rs. 1,30,000/-passed by the learned trial Judge. The decree of the learned trial Judge will stand modified to that extent. The rest of the decree including the decree for interest and costs is hereby affirmed. The cross-objection is dismissed.

R. S. BACHAWAT, J.

( 1 ) APPEALS Nos. 45 of 1955 and 100 of 1955 from original decrees have been heard together.

( 2 ) APPEAL No. 45 of 1955 is against a decree passed by Bose J. , in suit No. 3434 of 1952 instituted by B. N. Ellas and Co. Ltd. , against Aryan Mining and Trading Corporation Limited. Appeal No. 100 of 1955 is against a decree passed by Bose J. , in suit No. 3433 of 1952 instituted by the Agarpara Co. Ltd. , against Aryan Mining and Trading Corporation Limited. B. N. Elias and Co. Ltd. , is the Managing Agent of the Agarpara Co. Ltd.

( 3 ) BOTH the suits were heard together by Bose J, He delivered his main judgment an suit No. 3434 of 1952 and a subsidiary judgment in the other suit. Both the appeals have been heard together; This judgment is intended to cover both appeals.

( 4 ) THE subject-matter of suit No. 3434 of 1952 is a contract dated 26-12-1950, whereby Aryan Mining and Trading Corporation Limited agreed to sell to B. N. Elias and Co. Ltd. , 4000 tons of manganese ore with 46/48 per cent. , manganese contents at Rs. 82 per ton F. O. R. Barabil, delivery--500 tons monthly beginning from February, 1951 to be completed by December, 1951 latest. Under this contract the buyer deposited with the seller a sum of Rs. 1,20,000/- as advance. After giving credit for certain sums due to the seller for price of goods sold and delivered. B. N. Elias and Co. Ltd. claimed a sum of Rs. 56,919-4-9 by way of refund of the advance. At the trial it was conceded that the seller was entitled to a credit for a further sum of Rs. 13,624-4-9 on account of price of goods sold and delivered. Bose J. , has given a decree for refund of the balance sum of Rs. 43,294-15-9 on account of advance and a further sum of Rs. 244-12-9 for underloading and analysis charges. The correctness of this part of the decree is not challenged. It appears that under this contract 2,302 tons and 10 Cwt. of goods remained undelivered. There is now no dispute that all deliveries made by Aryan Mining and Trading Corporation Limited are to be appropriated towards the contract dated 26-12-1950 which is the subject-matter of this suit and that 2,302 tons and 10 cwt. of goods remained undelivered under this contract. The buyer alleges that the seller committed breach of the contract by not delivering the balance goods and it claims damages on the footing that the due date

of delivery was extended up to 31-3-1952. Bose J. , has accepted the buyer's contention that the due date was extended as alleged by the buyer and has awarded damages on that footing. The correctness of his findings on this point is challenged.

( 5 ) THE subject-matter of suit No. 3433 of 1952 is a contract dated 8-2-1951, whereby Aryan Mining and Trading Corporation Limited agreed to sell to Agarpara Co. Ltd. , 2000 tons of manganese ore at Rs. 90/- per ton F. O. R. Barabil--delivery 500 tons monthly beginning from October 1951 to be completed by December, 1951. Under this contract the buyer deposited a sum of Rs. 1,00,000/-with the seller as advance. Bose J. , has decreed refund of the advance with interest at 6 per cent. , per annum. The correctness of this part of the decree is not challenged. It is now common case that no part of the goods deliverable under this contract was delivered by the defendant. The buyer claims damages on the footing that the due date of delivery was extended up to 29-2-1952. Bose J. , has accepted the buyer's contention and has awarded damages on that footing. The correctness of his decree on this point is challenged.

( 6 ) ON a proper construction of both the contracts Bose J. , held that the contracts were entire and indivisible contracts and not instalment delivery contracts as contemplated by Section 38 of the Indian Sale of Goods Act. The correctness of this ruling is not challenged before us.

( 7 ) IN both suits the seller contended that time was not of the essence of the contract and that the seller had not committed any breach of the contract. Bose