High Court of Judicature at Calcutta
ASHIM KUMAR BANERJEE, SHUKLA KABIR SINHA, JJ.
State of West Bengal & Another
Versus
M/S. N. Bhakat & CO. & Another
A.P.O. No. 241 of 2012 & A.P. No. 435 of 2008
Decided On : 09-10-2012
ARBITRATION - AWARD - JUDICIAL REVIEW - ARBITRATOR'S REASONS - NON-INTERFERENCE - CONTRACT - ESCALATION AND IDLE LABOUR CHARGES - DELAY IN COMPLETION - LIABILITY OF STATE - NO CLAIM CERTIFICATE - EFFECT - INTEREST ON AWARDED SUM.
Fact of the Case:
Arbitration award challenged on grounds of delay in making protest, final payment duly received, claimants' request to treat seventh R.A. Bill as final bill and issuance of "No Claim Certificate", non-application of mind by Arbitrator, and unreasonable interest and cost awarded.
Finding of the Court:
1. Arbitrator's award is not subject to judicial review unless it is perverse, absurd, based on no evidence, or contrary to well-settled principles of law. 2. Clauses in the contract excluding claims for idle labour and escalation of rates do not absolve the State from liability for damages caused by their fault in delaying the work process. 3. "No Claim Certificate" does not bar a claim if the dispute is arbitrable and the claim is made within the limitation period. 4. Arbitrator's award is reasonable and justified, and does not fall under any exceptional category amenable to judicial review.
Issues: 1. Whether the Arbitrator's award is perverse, absurd, based on no evidence, or contrary to well-settled principles of law. 2. Whether the clauses in the contract excluding claims for idle labour and escalation of rates absolve the State from liability for damages caused by their fault in delaying the work process. 3. Whether the "No Claim Certificate" bars the claim if the dispute is arbitrable and the claim is made within the limitation period. 4. Whether the Arbitrator's award is reasonable and justified.
Ratio Decidendi: 1. The Arbitrator's award is not subject to judicial review unless it is perverse, absurd, based on no evidence, or contrary to well-settled principles of law. 2. Clauses in the contract excluding claims for idle labour and escalation of rates do not absolve the State from liability for damages caused by their fault in delaying the work process. 3. "No Claim Certificate" does not bar a claim if the dispute is arbitrable and the claim is made within the limitation period. 4. Arbitrator's award is reasonable and justified, and does not fall under any exceptional category amenable to judicial review.
Final Decision: Appeal succeeds in part and is allowed without any order as to costs. Claim No. 4 is reduced to Rs.1, 01,828/-. The entire awarded sum would carry interest at the rate of 9% per annum instead of 12% per annum as awarded by the Arbitrator.
Ashim Kumar Banerjee, J.
Backdrop
The subject matter of appeal would relate to an order passed by the learned Single Judge, declining to set aside and/or interfere with an award published under the old Arbitration Law being the Arbitration Act, 1940. His Lordship, by judgment and order dated March 28, 2012 appearing at page 299-307 of the paper book, upheld the award except the claim No. 2 that was found to be repeated in claim No. 4. In effect, the learned Judge affirmed the award to the extent of Rs.7,19,038/-covering claim Nos. 3 and 4 that was allowed by the Arbitrator.
Bringing the facts in a narrow campus, we would find, the appellant/State entrusted a partnership farm M/S. N. Bhakat & Company to execute a work on behalf of the State represented by Public Works Department, (hereinafter referred to as P.W.D.), Kharagpur Division for construction of residential quarters for non-gazetted staff for Eastern Frontier Rifles. The tender value was Rs.22,06,011/-. As per the contract, the work was scheduled to be completed within eighteen months from the date of the work-order. Since the work-order was issued on April 13, 1983, the work was supposed to be completed by October 30, 1984 whereas the work was completed on December 31, 1985 as stated by the claimants’ witness. However, records would depict, the work was completed on January 15, 1986. State accepted delayed handing over of possession. State from time to time extended the time-schedule as we find from the record. Contemporaneous correspondence would show, State duly paid seventh Running Account Bill (hereinafter referred to as R.A. Bill) that was paid on August 5, 1986. The claimants thereafter wrote to the authority to treat seventh R.A. Bill as the final bill and refund their security deposit that was withheld as per the contract. Claimants would contend, they were compelled to write such letter as State was unusually delaying the process in releasing the security. State would however, contend, such letter must be construed as an event of accord of satisfaction of the final payment that would give rise to the dispute. The claimants raised subsequent claims for escalation and idle labour charge because of delay in completing the construction. According to the claimants, delay was due to delayed handing over of site by the P.W.D. as also delay in supplying rawmaterials. Significant to note, supply of principal raw-materials being cement and steel was the responsibility of the State. There had been delay in supply as found out by the Arbitrator. According to the State, there could not have been any further claim either on escalation or idle labour charges or otherwise that would be apparent from the claimants’ letter dated November 11, 1986 wherein they had informed the P.W.D. that they had completed the work on January 15, 1986 and received final payment against seventh R.A. Bill that might be treated as final bill as there were no further work beyond the last measurement done on January 7, 1986. Once the claimants treated the seventh R.A. Bill as final and requested release of security deposit, there could not be any additional amount payable to them. Moreover, they did not reserve their right contemporaneously that would make the subsequent claim for the additional cost not sustainable. The claimants would contradict such stand of the State by referring to its letter dated February 27, 1987 appearing at page-242 of the paper book that would also rely upon communication made by the Assistant Engineer, P.W.D. appearing at page 240 and 241 wherein State admitted delay in delivery of the raw-materials. The claimants also relied upon their letters dated August 25, 1986 and February 15, 1987 appearing at page 51-52 of the paper book wherein they reserved their right to claim for damage because of delayed work.
AWARD :
The Arbitrator was a technical and non-legal person. Although the said Act of 1940 would not compel the Arbitrator to give a reasoned award unlike
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.