2010 Supreme(Cal) 175

High Court of Calcutta
Sanjib Banerjee, J.
Bharat Heavy Electricals Limited – Appellant
Versus
Tata Projects Limited – Respondent
A.P. No. 213 of 2006
Decided On: Feb 19, 2010

Important Points

An arbitral tribunal's award will be set aside if it acts in manifest disregard of the contract from which it derives its authority.

Subject

Arbitration Law - Award - Setting Aside

Act Referred

ARBITRATION AND CONCILIATION ACT : S.34

Headnote

ARBITRATION - INTERFERENCE WITH CONTRACTUAL TERMS - OVERRUN CHARGES, CRANE-HIRE CHARGES, INTEREST, AND PAINTING WORK DEDUCTION - ARBITRAL TRIBUNAL'S AWARD SET ASIDE IN PART - ARBITRATION AND CONCILIATION ACT, 1996, SECTION 34.

Fact of the Case:

In an arbitration proceeding arising from a contract for the erection, testing, and commissioning of two 120 MW boilers, the petitioner challenged four heads of claim awarded by the arbitral tribunal: overrun charges, crane-hire charges, interest, and a reduction in the deduction allowed for incomplete painting work.

Finding of the Court:

The court set aside the arbitral tribunal's award on the grounds of manifest disregard for the contract, which prohibited overrun charges, crane-hire charges, and interest. The tribunal's award on the painting work deduction was upheld as it was within the tribunal's authority to adjudicate on the dispute.

Issues: 1. Whether the arbitral tribunal exceeded its authority by awarding overrun charges, crane-hire charges, and interest in contravention of the specific terms of the contract? 2. Whether the arbitral tribunal erred in disallowing the deduction made by the petitioner for incomplete painting work?

Ratio Decidendi: 1. An arbitral tribunal cannot act in derogation of the specific terms of the agreement that prohibited certain claims. 2. A deliberate departure from the contract amounts to manifest disregard of authority or misconduct on the part of the tribunal. 3. A conscious disregard of the law or the provisions of the contract from which the arbitral tribunal has derived its authority vitiates the award to the extent of the award deviating from the contract.

Final Decision: The court allowed the petition in part, setting aside the arbitral tribunal's award on the grounds of overrun charges, crane-hire charges, and interest. The challenge on the painting work deduction was dismissed.

Advocates:
Advocate Appeared:
Sarathi Dasgupta, Dhuruba Ghosh, P.S.Biswas, Bijan Majumdar, Jayanta Dutta.

JUDGMENT

Sanjib Banerjee, J.

1. THE petitioner challenges four several heads of claim that have been entertained and allowed in the impugned arbitral award. THE petitioner says that the sums awarded on account of overrun charges, crane-hire charges and interest are in derogation of the agreement between the parties. THE petitioner assails the reduction in 'the quantum of deduction allowed by the arbitral tribunal on account of the respondent-claimant failing to complete the painting work.

2. THE petitioner obtained an order for setting up some plant of boiler units and was desirous of engaging a sub-contractor for discharging a part of the work. Pursuant to a notice inviting tender issued by the petitioner, the respondent offered to erect, test and commission two 120 MW boilers (Unit II and Unit III) on behalf of the petitioner. THE value of the contract awarded in favour of the respondent was Rs.6,99,40,000/-. Following disputes and differences having arisen between the parties, either party, nominated its arbitrator and the two arbitrators chose the third. THE arbitral tribunal awarded Rs.69.22 lakh on various heads and a sum of Rs.25.39 lakh on account of interest.

In the present proceedings under section 34 of the Arbitration and Conciliation Act, 1996, the petitioner says that the arbitral tribunal which derived its authority under the agreement between the parties could not have overridden the specific clauses in the contract to give relief to the respondent. The petitioner says that the arbitral tribunal had no power to consider the claims on account of overrun charges, crane-hire expenses and interest. On the fourth count of challenge, the petitioner suggests that the arbitral tribunal misdirected itself and disallowed the deduction made by the petitioner on irrelevant and extraneous considerations. In substance, it is the petitioner's case that the arbitral tribunal failed to decide the reference in accordance with the terms of the contract, in respect of the matters which have been challenged at the hearing.

3. THE matter was heard at length on February 17, 2010. Upon the petitioner's submission being concluded, substantial time was wasted by the respondent on account of the obvious unpreparedness. THE matter was adjourned and costs reserved. Even at the second call in a continuing part-heard matter, the respondent has not been represented at the hearing on February 18, 2010.

4. CLAUSE 9 of the agreement clearly stipulated that no overrun charge would be applicable for the contract. CLAUSE 10 provided for revision on accepted contract rate and envisaged rate revision at the rate of 10 per cent per annum in the event the contractual completion period was extended by the petitioner for reasons not attributable to the respondent. In addition, clause 11 of the agreement permitted payments to be made for extra work.

The petitioner demonstrates that in the written submission filed before the arbitral tribunal on behalf of the petitioner under cover of a letter dated October 8, 2004, the petitioner had categorically referred to clause 9 of the agreement and had submitted that overrun charges could neither be claimed nor awarded. Notwithstanding such objection, the tribunal addressed issue No.4, pertaining to the claim on account of overrun charges and did not consider the objection that a claim on such head was prohibited under the agreement. It is evident that there was an express bar on any claim being made on account of cost overrun charges and the arbitral tribunal's award of Rs.15 lakh under such head is in derogation of the agreement under which the tribunal derived its authority. The arbitral tribunal clearly erred in entertaining such head of claim and the award in respect of such claim cannot be sustained.

5. CLAUSE 12.2 of the agreement provided for the petitioner to arrange a 250 MT capacity crane and operator and consumables therefor for the second unit. The sub-contractor was, under such clause, obliged to provid