2009 Supreme(Cal) 779
IN THE HIGH COURT AT CALCUTTA
Sanjib Banerjee, J.
CESC Ltd. & Anr.
Vs.
Appellate Side Authority & Anr.
W.P. No. 15081 (W) of 2009
Decided on : 20th October, 2009
Important Points
Subject
Electricity Law - Unauthorized Use of Electricity
Act Referred
Headnote
ELECTRICITY ACT, 2003 - SECTION 126(5) - UNAUTHORIZED USE OF ELECTRICITY - ASSESSMENT OF CHARGES - KEY LEGAL PROVISIONS, INTERPRETATIONS, AND THEIR INFLUENCE ON THE COURT'S DECISION.
Fact of the Case:
The licensee challenged an order passed by the appellate authority in proceedings under section 127 of the Electricity Act, 2003, related to unauthorized use of electricity by the consumer and assessment of charges.
Finding of the Court:
The court held that the appellate authority erred in disregarding the previous inspection on July 26, 2007, where unauthorized use of electricity was detected. However, the court also noted that the licensee failed to provide a plausible explanation for the delay in conducting the second inspection on February 25, 2009.
Issues: 1. Whether the appellate authority erred in refusing to acknowledge the licensee's right to charge the consumer from a year prior to the initial inspection of July 26, 2007, as per section 126(5) of the Act. 2. Whether the appellate authority erred in requiring the assessment to be made on the basis of 12 months rather than 365 days preceding the date of inspection.
Ratio Decidendi: 1. The court held that section 126(5) of the Act gives the licensee an option to claim payment on account of unauthorized use of electricity from a previous date if such date is ascertained or, if such previous date is not ascertainable, to charge for a period of 12 months preceding the date of detection of unauthorized use of electricity. 2. The court held that the appellate authority erred in disregarding the previous inspection of July 26, 2007, where unauthorized use of electricity was detected, but the licensee failed to provide a plausible explanation for the delay in conducting the second inspection on February 25, 2009. 3. The court held that there was no merit in the licensee's second ground that the appellate authority erred in directing the licensee to calculate for a period of 12 months preceding the date of the effective detection of pilferage rather than 365 days.
Final Decision: The court dismissed the licensee's writ petition.
Subir Sanyal, Ratul Biswas for the petitioners
Arabindo Chatterjee, P. Sarkar for the respondent No. 2
1. The licensee has challenged an order dated June 10, 2009 passed by the appellate authority in proceedings under section 127 of the Electricity Act, 2003.
2. Some of the undisputed facts may be first recorded. The licensee made an attempt to disconnect the supply to the respondent consumer on July 26, 2007 following an inspection. It is the licensee's contention that such inspection revealed that there was unauthorized use of electricity by the second respondent, but the licensee could not immediately disconnect the supply due to "aggressive resistance" from the consumer. The licensee contemporaneously reported the matter to the local police authorities and a First Information Report was lodged. It was the licensee's assertion before the appellate authority that the police failed to discharge their duties to provide support to the licensee to disconnect the supply. The licensee thereafter attempted a further inspection on February 25, 2009 presumably with police support, whereupon discovering pilferage of electricity the line was disconnected from outside the consumer's premises. A provisional order of assessment was made.
3. Following the consumer's objection to the provisional assessment, a hearing was afforded to the consumer. The final order of assessment followed. Such final assessment was carried by the consumer in appeal which culminated in the order impugned in the present proceedings.
4. There are two grounds which have been raised by the licensee. The first ground is that the appellate authority failed to appreciate the purport of section 126(5) of the Act in refusing to acknowledge the licensee's right to charge the consumer from a year prior to the initial inspection of July 26, 2007. The second grievance is that the appellate authority required the assessment to be made on the basis of 12 months rather than 365 days preceding the date of inspection.
5. As to the first ground urged by the licensee, there appears to be a legal basis to the petitioner's argument. Section 126(5), indeed gives the licensee an option to claim payment on account of un authorised use of electricity from a previous date if such date is ascertained or, if such previous date is not ascertainable, to charge for a period of 12 months preceding the date of detection of unauthorized use of electricity. It is the licensee's argument that since the previous inspection of July 26, 2007 revealed that the consumer had tampered with the meter seal and unauthorised use of electricity had been established, in accordance with the first limb of section 126(5) of the Act such previous date of July 26, 2007 should be reckoned to be the date ascertained for the purpose of calculating the loss occasioned to the licensee on account of the unacceptable conduct of the consumer.
6. The appellate authority altogether disregarded the previous inspection of July 26, 2007. Though the appellate authority did not notice such fact in its order, it appears from the final order of assessment that the licensee had charged the consumer for a period of one year prior to the date of initial inspection on July 26, 2007. This was clearly impermissible since sub-section (5) of section 126 gives the licensee either of two possible periods. A licensee cannot claim from the ascertained date and thereafter take advantage of the second limb of sub-section (5) of section 126 to seek payment for a period of 12 months prior to the ascertained date. It appears that the two limbs of sub-section (5) of section 126 are mutually exclusive. However the appellate authority should have considered that if an earlier ascertained date was available and there was no dispute regarding the same, it was open to the licensee to charge on account of unauthorized use of electricity with reference to such previous ascertained date.
7. The difficulty in this matter arose in the long hiatus between the original inspection and the subsequent. There was no explanation either in the final order of assessme