I.P.MUKERJI
Swadesh Ghosh – Appellant
Versus
CESC Limited – Respondent
The writ petitioner is in partnership business with one Shambu Ghosh. In partnership, they run a factory at premises No. 9/H/1, Abanish Chowdhury Lane, Kolkata-700 046. The business carried on by this partnership firm is manufacturing of rubber goods. The factory has two electricity meters, one of them, 2350145K of the writ petitioner. His partner also has another meter with which this case has no real connection.
2. On or about 28th August, 2003 (the date appearing in the order of provisional assessment) the electricity connection of the writ petitioner was disconnected by representatives of the respondent/licensee. Their ground was theft of electricity.
3. A provisional assessment was made on 28th August, 2003 itself where the provisional assessed sum was Rs.2,27,0340/-. This was followed by a final assessment on 2nd October, 2003.
4. The writ petitioner filed an appeal from that assessment order before the appellate authority. Thereafter, he filed a writ application in this Court in W. P. No. 1580 of 2005 alleging that the appellate authority was slow to dispose of that appeal.
5. That writ application was disposed of on 3rd August, 2005 by Jayanta Kumar Biswas, J. by the
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.