2016 Supreme(Cal) 246

IN THE HIGH COURT OF JUDICATURE AT CALCUTTA
MANJULA CHELLUR, ARIJIT BANERJEE, JJ.
Vinod Kumar Tewari - Appellant
Vs.
C.E.S.C. Ltd. & ors. - Respondents
M.A.T. 406 of 2015 with CAN No. 3368 of 2015
Decided On : 29-02-2016

Important Points

A consumer is liable to pay the charges for all electricity supplies provided to him, irrespective of the nature of the supply or the premises to which the connection is given.

Subject

Electricity Law - Disconnection of Supply

Act Referred

ELECTRICITY ACT : S.56

Headnote

ELECTRICITY ACT, 2003 - DISCONNECTION OF SUPPLY - SECTION 56 - CONSUMER'S LIABILITY TO PAY CHARGES - DISTINCTION BETWEEN COMMERCIAL AND DOMESTIC SUPPLY IRRELEVANT - NO RIGHT TO CLAIM TWO CONTRACTS - SECTION 56 APPLIES.

Fact of the Case:

The appellant had two lines of electricity supply, one for commercial consumption and the other for residential consumption. The respondent company disconnected the domestic supply due to non-payment of demand charges for the commercial supply. The appellant challenged the disconnection, arguing that the two supplies were different connections and should be treated separately.

Finding of the Court:

The court held that Section 56 of the Electricity Act, 2003 applies to the case and that the appellant, as the consumer, is liable to pay the charges for both the commercial and domestic supplies. The court further held that the appellant had not challenged the demand notices and that there was no provision in the Act which gives the appellant the right to claim that there are two separate contracts for the two supplies.

Issues: Whether the appellant, as the consumer, is liable to pay the charges for both the commercial and domestic supplies.

Ratio Decidendi: Section 56 of the Electricity Act, 2003 applies to the case and that the appellant, as the consumer, is liable to pay the charges for both the commercial and domestic supplies. The appellant had not challenged the demand notices and that there was no provision in the Act which gives the appellant the right to claim that there are two separate contracts for the two supplies.

Final Decision: The appeal was dismissed along with the application.

Advocates:
Advocate Appeared:
For the Appellant : Mr. Sandip Ghosh
For C.E.S.C. Ltd. : Mr. Subir Sanyal

JUDGMENT :

1. It is necessary to indicate certain facts relating to the present appeal in order to appreciate the stand of the appellant and the respondent company in the right perspective.

2. It is not in dispute that the appellant has two lines of supply as indicated in Annexure “P-6” at page 48 of the stay application, one for commercial consumption and the other for residential consumption. Both the commercial supply and the domestic supply of electricity is to the consumer name of Vinod Kumar Tewari, the appellant herein. The challenge before us can be ascertained reading the prayers at page 83 of the stay application papers wherein the appellant has asked the respondent company to restore the line of the appellant/petitioner in respect of Meter No. 4158440 domestic connection with reference to premises situated in holding no. 139/C/4, Ananda Palit Road, C.I.T. Road, Kolkata-700014. He has also sought consequential reliefs. The main contention of the petitioner before the Trial Court was to the effect that in view of different nature so far as the electricity supply, domestic and commercial, irrespective of the consumer being the same it has to be treated as different connections. Therefore, the disconnection notice under challenge ought to have been quashed by the learned Trial Judge by restoring the electric supply to the domestic line of the writ petitioner.

3. The main challenge on behalf of the respondent company was that there was no proper relief sought with regard to the facts and the demand notice remains unchallenged except challenging the disconnection. Learned counsel for the respondent company submits that the Court could not travel beyond considering whether restoration could be done in the absence of challenge to demand notice.

4. Learned Judge on consideration of the matter proceeded to hold that since there is no challenge with regard to the demand, therefore there has to be conditional order directing the respondent company to restore electricity supply subject to deposit of 50% of the demand within a given time and balance amount to be paid by two instalments as indicated in the order impugned.

5. Aggrieved by the same, the appellant is before us contending that Section 56 of the Electricity Act alone is the provision which could be relied upon by both the parties before the Court and he contends that irrespective of the character of the supply since the consumer is the same, there cannot be any uniformity in course of action taken by the supplying company since both the supplies have different consumer numbers, different lines, different purpose and different consumption charges, i.e. rate at which consumption is charged.

6. As against this learned counsel representing the company contends that even to substantiate the present stand of the appellant no pleadings are forthcoming, therefore question of considering the submission would not arise at this stage since Section 56 does not distinguish between the nature of consumption and there is no reference to premises to which the connection is given. Section 56 of the Electricity Act of 2003 reads as under:

“56. Disconnection of supply in default of payment.- (1) Where any person neglects to pay any charge for electricity or any sum other than a charge for electricity due from him to a licensee or the generating company in respect of supply, transmission or distribution or wheeling of electricity to him, the licensee or the generating company may, after giving not less than fifteen clear days' notice in writing, to such person and without prejudice to his rights to recover such charge or other sum by suit, cut off the supply of electricity and for that purpose cut or disconnect any electric supply line or other works being the property of such licensee or the generating company through which electricity may have been supplied, transmitted, distributed or wheeled and may discontinue the supply until such charge or other sum, together with any expenses incurred by