2017 Supreme(Cal) 314
IN THE HIGH COURT OF JUDICATURE AT CALCUTTA
ANIRUDDHA BOSE, J.
Union of India – Petitioner
Versus
M/s. Build Fab – Respondent
AP No. 231 of 2007
Decided On : 10-04-2017
For the Petitioners: O.P. Dubey, J.S. Dhatt.
For the Respondents: Bijon Majumdar, Prasanta Banerjee.
The main legal point established in the judgment is the authority of the arbitrator to adjudicate on various claims under the construction contract, and the absence of specific bar or prohibition in the contract on making claims under any of the heads on which award has been made in favour of the claimant.
Headnote:
Arbitration - Construction Contract - Arbitration and Conciliation Act 1996 - Clause 25, General Conditions of Contract (GCC) Clause 42 - Claims under six heads - Award challenged on diverse grounds - Arbitrator's authority to act in that capacity was questioned - Dispute resolution by arbitration - Claims under six heads - Award of principal, interest, and costs - Arbitrator's authority to adjudicate on dispute on any of these heads - Claimant's contention on escalation, penal recovery of cement, extra/substituted items, extra establishment, tools and plants, and loss of profit - Arbitrator's findings and reasoning - Court's analysis and conclusion - No specific denial of the claimant's contention relating to escalation - Arbitrator's examination of factual aspects - Award containing an overall factual analysis of the cases of the claimant and the respondent - Arbitrator's acceptance of the mode of calculation of the claimant and award of sums under various heads - No error on the part of the arbitrator in rejecting the counter-claim for costs - No specific bar or prohibition in the contract on making claims under any of the heads on which award has been made in favour of the claimant - No error on the part of the arbitrator in rejecting the counter-claim for costs - Award sustained
Fact of the Case:
The petitioner engaged the respondent for constructing a building for Regional Provident Commissioner at Kolkata. Dispute arose in relation to certain claims made by the contractor after payment of final bill. The arbitrator awarded a sum of Rs. 18,04,403/- as principal in relation to the first four claims, along with interest and costs. The award was challenged on diverse grounds.
Finding of the Court:
The Court found that the arbitrator's authority to act in that capacity was questioned, but the petitioner's plea on that count was rejected by the arbitrator. The Court also found that there was no specific denial of the claimant's contention relating to escalation, and the arbitrator had examined the factual aspects while deciding on various issues. The Court concluded that there was no error on the part of the arbitrator in rejecting the counter-claim for costs, and no specific bar or prohibition in the contract on making claims under any of the heads on which award has been made in favour of the claimant.
Issues: The issues included the arbitrator's authority to adjudicate on dispute on various heads, the claimant's contentions on escalation, penal recovery of cement, extra/substituted items, extra establishment, tools and plants, and loss of profit, and the petitioner's challenge to the arbitrator's findings and reasoning.
Ratio Decidendi: The Court's decision was influenced by the arbitrator's examination of factual aspects, the absence of specific denial of the claimant's contentions, and the lack of specific bar or prohibition in the contract on making claims under any of the heads on which award has been made in favour of the claimant.
Final Decision: The Court dismissed the application and sustained the award, finding no error on the part of the arbitrator in rejecting the counter-claim for costs, and no specific bar or prohibition in the contract on making claims under any of the heads on which award has been made in favour of the claimant.
1. The petitioner had engaged the respondent (claimant) for constructing a building for Regional Provident Commissioner at Kolkata. The agreement to that effect was executed on 21st August, 1994. It was initially agreed upon by and between the parties the starting date for execution of the work was to be 27th August, 1994, and the work was to be completed in twenty four months. The projected date of completion of the work, thus, was 26th August, 1996. The value of the contract was Rs. 90,34,898/- (Rupees ninety lacs thirty four thousand eight hundred and ninety eight only). The date of completion of work was extended by approximately twenty eight and the actual date of completion of work was 21st December, 1998. Clause 25 of the contract provided for resolution of disputes arising out of the contract by arbitration. In this clause, the Chief Engineer, Central Public Works Department in charge of the work at the material point of time was specified to be the arbitrator and the administrative head of the same organization was specified to be the arbitrator if there was no chief engineer.
2. Dispute had arisen in relation to certain claims made by the contractor after payment of final bill, in which no disbursal had been made in respect of certain items, or partial disbursal had been made. The arbitrator, whose award is under challenge in this petition was appointed in terms of an order passed under Section 11 (6) of the Arbitration and Conciliation Act 1996. I find from records that at the initial stage the arbitrator’s authority to act in that capacity was questioned, but the petitioner’s plea on that count was rejected by the arbitrator in an application taken out under Section 16 of the 1996 Act. In the statement of claim filed before the arbitrator, the claimant had raised claims under six heads. The first claim comprised of three parts, in respect of escalation, penal recovery of cement and extra/substituted items. A total sum of Rs. 5,11,655/- (Rupees five Lacs eleven thousand six hundred and fifty five only) was claimed under these three heads. The second claim related to cost of maintaining extra establishment both on-site and off-site for twenty eight months, being the extended time within which the contract was completed and the sum claimed was Rs. 5,27,000/- (Rupees five lacs twenty seven thousand only). Claim No. 3 related to extra cost on tools and plants for prolongation of the work and a sum of Rs. 2,63,000/- (Rupees two lacs sixty three thousand only) was claimed. The fourth claim was for Rs. 5,27,000/- (Rupees five lacs twenty seven thousand only) on account of loss of profit resulting from prolongation of the work beyond the stipulated period of twenty four months. The rest two claims were in respect of interest and costs. Upon hearing the learned counsel appearing for the parties after completion of pleadings and examination of evidence, the arbitrator awarded a sum of Rs. 18,04,403/- (Rupees eighteen lacs four thousand four hundred and three only) as principal in relation to the first four claims. 12% interest was awarded from 17th February, 2005 till the date of the award, which was computed to be Rs. 4,63,371/- (Rupees four Lacs sixty three thousand three hundred and seventy one only) and 18% interest with effect from 10th April, 2007, to be computed from the date of the award till the date of payment. Costs of Rs. 1,00,000/- was awarded in addition, against claim no. 6. The award was made and published on 9th April, 2007.
3. This award is assailed in this proceeding on diverse grounds. It appears from the award itself that in course of hearing before the arbitrator, the petitioner sought to exclude certain claims as excepted matters. The arbitrator on this point, inter-alia, held:-
“...........But claims which are incidental to and arise out of or flow from the contract but which do not form the subject matter of the contract cannot be termed as ‘excepted matters’ as for instance refund of security