IN THE HIGH COURT OF JUDICATURE AT CALCUTTA
Soumen Sen, J.
Subash Projects & Marketing Limited - Appellant
Vs.
State Bank of Hyderabad & Ors. - Respondent
G.A No. 1085 of 2001 and C.S No. 70 of 2001
Decided On : 06-02-2018

Advocates Appeared:
For the Appellant : Mr. Kaushik Saha, Adv., Mr. Satyaki Chaudhury, Adv.
For the Respondent: Mr. Bodhisatta Biswas, Adv.

The main legal point established in the judgment is the exclusion of jurisdiction based on the forum selection clause in the agreement and the revocation of leave under Clause 12 of the Letters Patent.

Headnote:

Revocation of Leave - Arbitration Agreement - Clause 12 of the Letters Patent - [BANK GUARANTEES] - [CONTRACT DISPUTE] - [Clause 35 of the Agreement] - [Swastik Gases Pvt. Ltd. v. Indian Oil Corporation Ltd. (2013) 9 SCC 32] - The court discussed the jurisdictional clause in the agreement and the interpretation of similar clauses in previous cases. It concluded that the jurisdiction of the court was excluded based on the forum selection clause in the agreement, and the suit should be filed before the appropriate Court at Mumbai.

Fact of the Case:

The plaintiff filed a suit seeking delivery up and cancellation of bank guarantees issued by the defendant No. 2 in favor of the defendant No. 1. The plaintiff alleged that the bank guarantees had become null and void due to the defendant No. 3's failure to obtain permission from the defendant No. 4 to allow the plaintiff to act as a sub-contractor.

Finding of the Court:

The court found that the jurisdiction of the court was excluded based on the forum selection clause in the agreement, and a part of the cause of action had arisen at Mumbai. Therefore, the leave granted under Clause 12 of the Letters Patent was revoked, and the suit was directed to be filed before the appropriate Court at Mumbai.

Issues: The main issue was the jurisdiction of the court and the revocation of leave under Clause 12 of the Letters Patent.

Ratio Decidendi: The court's decision was based on the interpretation of the forum selection clause in the agreement and the exclusion of jurisdiction under Clause 12 of the Letters Patent.

Final Decision: The leave granted under Clause 12 of the Letters Patent was revoked, and the suit was directed to be filed before the appropriate Court at Mumbai. The application for revocation of leave and the suit were disposed of accordingly.

JUDGMENT :

SOUMEN SEN, J.

The defendant No. 3 has filed this application for revocation of leave under Clause 12 of the Letters Patent. In the alternative, a prayer is made for referring the dispute forming the subject matter of the suit to arbitration in accordance with the Arbitration Agreement between the parties.

2. The plaintiff has filed a suit in this Court after obtaining leave under Clause 12 of the Letters Patent. In the suit, the plaintiff has essentially prayed for delivery up and cancellation of four bank guarantees issued by the defendant No. 2 in favour of the defendant No. 1.

3. The plaintiff contends that the plaintiff and the defendant No. 2 entered into a Memorandum of Understanding (MOU) dated 15th October, 1999 to collaborate for preparation and submission of a tender in response to a notice issued by the National Highway Authorities of India, the defendant No. 4, for “Four Laning of KM.156.000 to KM 163.895 of Gauwahati Bypass section of N.H -37 in the State of Assam (contract Package No. SW/7-(AS)” on the basis of the distribution of work in 40:60 approximately. Pursuant to such MOU, the defendant No. 3 had submitted their tender to the defendant No. 4 and the work was ultimately allotted to the defendant No. 3. Subsequent to acceptance of the offer by the defendant No. 4, the plaintiff and the defendant No. 1 entered into a new agreement on 25th April, 2000 superseding the earlier MOU. The said agreement was executed outside the jurisdiction of this Court. Under the agreement dated 25th April, 2000, the plaintiff was to work as a sub-contractor under the defendant No. 3 subject to getting permission from the defendant No. 4. The plaintiff obtained a mobilization advance of Rs. 1.82 crores from the defendant No. 3 against the submission of four bank guarantees. Such four bank guarantees of Rs. 45.50 lakhs each were issued by the defendant No. 1 being the bankers of the plaintiff from the office of the defendant at Park Street within the jurisdiction of this Court to the defendant No. 2, the banker of the defendant No. 3 of such jurisdiction of this Court. The defendant No. 4 by letters dated 19th September, 2000 and October 3, 2000 directed the defendant No. 3 not to give any portion of the work awarded under any sub-contract. In respect of the specific request relating to the plaintiff it is alleged that the defendant No. 4 was of the opinion that the plaintiff does not have the requisite experience in the field of High Way engineering. In view of the failure on the part of the defendant No. 3 to obtain permission from the defendant No. 4 to allow the plaintiff to act as sub-contractor, the four bank guarantees had become null and void. The defendant Nos. 1 and 2 are aware of the terms of the agreement and the circumstances under which the said bank guarantees have now become unenforceable. Notwithstanding the same, the defendant No. 3 has not discharged the said bank guarantees and the said defendant Nos. 1, 2 and 3 and each of them are threatening to encash the said four bank guarantees. In view of the cancellation of the said agreement by the defendant No. 3 by its letter dated 30th November, 2000, the plaintiff is entitled to treat the said four bank guarantees issued at the instance of the plaintiff by the defendant No. 1 as void and unenforceable by the defendant Nos. 2 or defendant Nos. 3 against the plaintiff in any manner whatsoever. In Paragraph 32 of the plaint, the plaintiff has made the necessary averments to show that a part of the cause of action has arisen from within the jurisdiction of this Court and, accordingly, has prayed for revocation of leave under Clause 12 of the Letters Patent.

4. It is elementary that in deciding an application for revocation of leave under Clause 12 of the Letters Patent, the averments made in the plaint are required to be taken as true and correct. The plaintiff has admitted that in Paragraph 5 of the plaint that the agreement dated 25th April, 2000 was executed


























Click Here to Read the rest of this document