2017 Supreme(Cal) 867
IN THE HIGH COURT OF CALCUTTA
JYOTIRMAY BHATTACHARYA, SHIVAKANT PRASAD, JJ.
Pioneer Publicity Corporation Pvt. Ltd. - Appellant
Vs.
Hooghly River Bridge Commissioners & Anr. - Respondents
F.M.A. No. 732 of 2017 & (CAN 2901 of 2017)
Decided On : 14-07-2017
Important Points
Subject
Civil Law - Contract Law
Act Referred
SPECIFIC RELIEF ACT : S.6, S.14(1)(c), S.41(c), S.9, S.14
Headnote
Injunction - Contractual Dispute - Code of Civil Procedure - Specific Relief Act - [Advertisement Contract] - [Order XXXIX Rules 1 and 2, Section 151 of the Code of Civil Procedure, Section 6 of the Specific Relief Act] - The court discussed the legality of the defendant's right to terminate the contract and take back possession of the sites from the plaintiff. The court referred to Clause 15 of the contract and the principles under Section 6 of the Specific Relief Act to determine that the plaintiff's possession could not be disturbed without due process of law. The court held that injunction was the appropriate remedy to protect the plaintiff's possession, setting aside the trial judge's order and granting an interim injunction in favor of the plaintiff.
Fact of the Case:
The plaintiff entered into a contract with the defendant to display hoardings and kiosks at various locations. The defendant later sought to terminate the contract and take back possession of the sites, leading the plaintiff to file a suit seeking declaration of the termination notice as invalid and a permanent injunction against the defendants.
Finding of the Court:
The court found that the plaintiff's possession could not be disturbed without due process of law and that injunction was the appropriate remedy to protect the plaintiff's possession.
Issues: The main issue was the legality of the defendant's right to terminate the contract and take back possession of the sites from the plaintiff.
Ratio Decidendi: The court relied on Clause 15 of the contract and the principles under Section 6 of the Specific Relief Act to hold that the plaintiff's possession could not be disturbed without due process of law, and that injunction was the appropriate remedy.
Final Decision: The court set aside the trial judge's order and granted an interim injunction restraining the defendants from disturbing the plaintiff's possession of the sites until the disposal of the suit.
For the Appellant : Mr. Saktinath Mukherjee, Mr. Saptansu Basu, Mr. Nilanjan Bhattacharjee, Mr. Dipanjan Sinha Roy, Mr. Arpan Guha
For the Respondent: Mr. Biswajit Basu, Mr. Manali Biswas
Jyotirmay Bhattacharya, J.
1. This First Appeal is directed against an order being no. 7 dated 23rd March, 2017 passed by the learned Judge, 5th Bench, City Civil Court at Calcutta in Title Suit no. 236 of 2017 at the instance of the plaintiff/appellant.
2. By the impugned order, the plaintiff’s application for temporary injunction under Order XXXIX Rules 1 and 2 read with Section 151 of the Code of Civil Procedure was rejected.
3. Let us now consider as to how far the learned Trial Judge was justified in rejecting the plaintiff’s application for temporary injunction in the facts of the present case.
4. After being successful in the tender, a contract was entered into between the plaintiff and the defendant no.1, allotting different sites permitting the plaintiff to display hoardings and kiosks on Vidyasagar Setu (2nd Hooghly Bridge), Gariahat flyover, A.J.C Bose Road flyover, Beck Bagan flyover, Park Street flyover, Lock Gate flyover, Nager Bazar flyover (Dum Dum), Khidderpore flyover and bridge for the period of three years (36 months) on the terms and conditions as mentioned in the notice inviting tender.
5. Admittedly, there was no problem between the parties during the said contract period. There was no complain against the plaintiff for non-compliance of any of the obligations which the plaintiff was required to fulfill in terms of the said contract. Admittedly, the said contract was extended for a further period of one year w.e.f. the date next to the date of expiry of the original contract with the same terms and conditions as laid down earlier except the locations as mentioned in the office letter dated 17th December, 2013 wherein already a further period of one year two months has been extended due to removal of hoardings from the other locations because of declaration of green zone. The extended period of the contract is due to expire sometime in August, 2017. There was no complaint from the side of the defendant that the plaintiff has not fulfilled any of the conditions which it is required to perform in terms of the subsequent contract for the extended period. Problems started when the defendant by its letter dated 27th December, 2016 intimated the plaintiff that the defendant will take back the area of operation as mentioned in the contract w.e.f. 1st April, 2017 in terms of Clause 15 of the terms and conditions of contract and instruction to the bidder. Service of such notice upon the plaintiff gave rise to the cause of action for filing the present suit by the plaintiff against the defendants as the advertisement right of the plaintiff was sought to be disturbed by the defendant during the extended period of contract causing loss of reputation and also loss of business. In the said suit the plaintiff prayed for a decree of declaration that the termination notice dated 27th December, 2016 is bad in law and also for a further declaration that the contract between the plaintiff and the defendant no.1 and the extension pursuant to the letter dated 18th August, 2016 are valid and still in force. A decree for permanent injunction was sought for restraining the defendants from creating any obstruction and/or hindrance to the plaintiff towards exercising its user right over and at advertisement sites hoardings/bill boards and kiosks allotted by the defendant no.1 at A.J.C Bose Road flyover, Gariahat flyover, Park Street flyover, Khidderpore flyover and bridge without due process of law. After filing the said suit the plaintiff filed an application for temporary injunction for restraining the opposite party/defendant from creating any third party interest at the allotted sites and also restraining them from acting in terms and/or from giving any effect and the further effect to the impugned termination notice dated 27th December, 2016 at the suit property which is mentioned in the schedule of the said petition and allowing the plaintiff/petitioner to exercise its contractual rights thereat in terms of the Memos dat