High Court Of Delhi
NATIONAL THERMAL POWER CORPORATION LTD - Appellant
Versus
SIEMENS ATIENGESELLSCHAFT - Respondent
O.M.P. : 462 of 2003
Decided On : 05/24/2005
( 1 ) THIS appeal under Section 37 (2) (a) of the Arbitration and Conciliation act 1996 (hereinafter referred to as the Act) read with Section 151 CPC is directed against the Partial Award dated 31st July, 2002 made by the International Chamber of commerce, Arbitration Tribunal. Facts and circumstances giving rise to the appeal may be noted as under.
( 2 ) ON 6th December 1989 the parties entered into a contract for setting up of 817 MW Gas Based Combined Cycle Power Project at Dadri in U. P. at a price of dem 324,405,000/- equivalent to Rs. 2,190,000,000/- (Rupees Two Thousand One hundred Ninety Million ). At the request of respondent-SAG, three separate contracts were entered into with cross-fall breach clause. One contract was with respondent- sag, known as the First Contract and the other with its associates, namely, bharat Heavy Electricals Limited (BHEL), New Delhi and the third with Siemens limited, Bombay. Considerable delay occurred in execution of the contract which was mostly attributable to the appellant-NTPC, due to delay in opening of LCs in favour of the respondent-SAG and in obtaining Import Licences for various equipments from Statutory Authorities. Respondent raised several claims against the appellant-NTPC for losses resulting from delay. On the other hand, the appellant was also facing acute difficulty in getting the critical components and spare parts and tools from the respondent. In order to sort out the said disputes, a high-powered meeting of the parties was held on 6th /7th April, 2000 in which several decisions were taken. One of the decisions taken in the meeting was that the respondent was to supply the critical components and spare parts etc. to the appellant-NTPC on its part and on the other hand appellant-NTPC had agreed to look into the claims raised by the respondent-SAG with more positive approach in view of the fact that there were delays in arranging import licences and opening of LC by NTPC. It would appear that pursuant to the said decisions, the respondent-SAG supplied critical components etc. but appellant-NTPC did not favourably consider the claims of the respondent- sag for damages on account of the aforesaid delay.
( 3 ) SUBSEQUENTLY, the respondent-SAG made a reference to ICC Court of arbitration, Paris for settlement of their disputes/claim to compensation on account of delays. In terms of Clause 27 of the Contract, the ICC International Court of arbitration registered the reference as Case No. 11728/acs and on 5th May, 2002 issued Terms of Reference. The Terms of Reference of the ICC International Court of Arbitration contained summary of parties respective claims and counter-claims. The ICC International Court of Arbitration was comprised of three Arbitrators, namely, Mr. Arthur Marriott QC, Chairman and Mr. Justice R. S. Pathak and mr. Justice A. M. Ahmadi, two former Chief Judges of the Supreme Court of India. It is pertinent to note that while the claim of respondent-SAG related largely to compensation on account of delay on the part of the NTPC in procuring the import licences and belated opening of the LC in favour of the respondent, the NTPC besides filing their defence to the said claims also filed several counter claims on various counts amounting to hundreds of crores of rupees against the respondent-SAG. The respondent-SAG resisted the said counter claims of the NTPC, inter alia, on the grounds that counter claims were not arbitrable because the claims had been waived and/or abandoned and/or discharged and/or satisfied or compromised and the respondent had failed to fulfill the conditions precedent to arbitration specified in clauses 26 and 27 of the General Conditions of Contract. The Terms of Reference dated 5th May, 2002 contain the following issues:- The list of issues formulated below is not definitive, and may require expansion or reformulation as the arbitration progresses subject to article 19 of the Rules. A. Jurisdiction and Formulation of Clai
Ram Sarup Gupta Vs. Bishun Narain Inter College and Ors
T.N.Electricity Board Vs. M/s Bridge Tunnel Constructions and Ors
Allahabad Vs. Heavy Engineering Corpn., Ranchi
NIRMA LTD Vs. LURGI ENERGIE UND ENTSORGUNG GMBH, GERMANY and ORS.
UOI Vs. M/s East Coast Boat Builders and Engineers Ltd.
Mahindra Supply Company vs. ABC
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.