2005 Supreme(Del) 625

High Court Of Delhi
NATIONAL INSTITUTE OF BANKING STUDIES AND CORPORATION MANAGEMENT - Appellant
Versus
VIJ CONSTRUCTION LTD. - Respondent
First Appeal Order : 81 of 2004
Decided On : 05/24/2005

Important Points

The power conferred on the arbitrator under Section 16 includes the power to rule on the question as to whether any claim/counter claim can be said to be a dispute within the meaning of the Arbitration Agreement and whether the arbitrator has or does not have the jurisdiction to adjudicate on the said claim/counter claim.

Subject

Arbitration Law - Jurisdiction of Arbitrator

Act Referred

ARBITRATION ACT : S.33
ARBITRATION AND CONCILIATION ACT : S.37(2)(a)

Headnote

Arbitration - Construction Agreement - Arbitration and Conciliation Act, 1996, Section 16, Section 37 - The court allowed the appeal against the order of the arbitrator and directed the arbitrator to entertain and adjudicate upon all the counter-claims made by the appellant before the arbitrator in accordance with the law.

Fact of the Case:

An agreement for construction was executed between the parties. Disputes arose, and an arbitrator was appointed. The respondent moved an application for deletion of certain counter claims, which was opposed by the appellant. The arbitrator allowed the application, concluding that certain counter claims were pre-mature and outside the ambit of the expression dispute.

Finding of the Court:

The court found that the arbitrator's order holding that the counter-claims other than those raised in the letter dated 5. 5. 2000 cannot be entertained and adjudicated upon because those are pre-mature claims and are outside the ambit of the expression dispute is legally unsustainable and therefore liable to be set aside.

Issues: The main issue was whether the arbitrator could make the impugned order on the application of the respondent under Section 16 of the Act, holding that certain counter-claims cannot be entertained and adjudicated upon because those are pre-mature and are outside the ambit of the expression dispute.

Ratio Decidendi: The power conferred on the arbitrator under Section 16 includes the power to rule on the question as to whether any claim/counter claim can be said to be a dispute within the meaning of the Arbitration Agreement and whether the arbitrator has or does not have the jurisdiction to adjudicate on the said claim/counter claim.

Final Decision: The appeal was allowed, and the impugned order of the arbitrator was set aside. The arbitrator was directed to entertain and adjudicate upon all the counter-claims made by the appellant before the arbitrator in accordance with the law.

Advocates Appeared:
M.K.CHAUDHARY, S.K.CHANDWANI, V.K.MAKHIJA, Valmiki Mehta

R. C. JAIN, J.

( 1 ) THIS appeal under Section 37 (2) (a) of the Arbitration and Conciliation act, 1996 (hereinafter called as the Act ) is directed against the Order of the Sole Arbitrator {mr. justice, C. L. Chaudhary (Retd)} dated 6. 2. 2004, whereby the learned Arbitrator has directed deletion of certain counter-claims of the appellant from the scope of the Arbitration Proceedings.

( 2 ) IN short the relevant facts giving rise to the present appeal are that an agreement for construction was executed between the parties on 20. 4. 1996 whereby the respondent was to construct a building-Northern India Bank Staff Training college at Campus Project at Plot No. A-30, Sector 62, Institutional Area, Noida for the appellant. Disputes/differences arose between the parties with regard to the said contract and the respondent appointed one Mr. L. R. Pahwa as the Arbitrator to adjudicate upon certain claims. However, a petition (AA No. 182/2001) under Section 11 of the Act was also moved for appointment of the Arbitrator and was disposed of by this Court on 17. 1. 2000 with the following order: I am satisfied that disputes have arisen between the parties, as stated in the petition. Counsel appearing for the respondent states that the respondent also has certain Counter Claims as against the petitioner. In that view of the matter and with the consent of the counsel appearing for the parties, I appoint Hon ble Mr. Justice C. L. Chaudhary, a Retired Judge of this Court, as an Arbitrator for adjudicating all the disputes between the parties i. e. Claims of the petitioner arising out of and in connection with the present contract as also the Counter Claims of the respondent.

( 3 ) THE learned Arbitrator entered upon the reference and the respondent- herein filed a statement of claim dated 11. 5. 2002 and thereafter additional statement of claim on 12. 7. 2002. In response to the same, the appellant filed reply to the said statement of claims/additional claims and also made counter claim against the respondent. The respondent, thereafter, moved an application under Sections 16 of the Act for deletion of certain counter claims which the appellant had preferred before the Arbitrator on the ground that as per the conditions of the contract, dispute had not arisen in respect of those counter claims as the person raising the dispute ought to have given a notice with regard to the disputes. The said application was opposed by the appellant by filing a reply inter-alia contending that the counter claims had arisen from the main contract dated 20. 4. 1996 between the parties and as per the order of this Court dated 17. 1. 2002 in AA No. 182/2001, all such counter- claims, once they arose from the contract were necessarily the subject matter of arbitration. It was also pointed out that the counter- claims by their very nature were those which arose after the filing of the claims by the respondent and as such were bound to be considered by the Arbitrator.

( 4 ) LEARNED Arbitrator vide the impugned order has allowed the application of the respondent under Section 16 of the Act concluding as under: In view of this, I hold that the counter claims raised in the letter dated 8. 5. 2000 will have to be adjudicated upon by this arbitral tribunal and the rest of the counter- claims cannot be entertained and adjudicated upon, because those are pre-mature claims and are outside the ambit of the expression dispute. The contention of mr. Mahesh K. Chaudhary that the claimant had increased the amount of claims, which were filed before the previous Arbitrator Mr. Pahwa and the claims fled before this arbitral Tribunal. It is within my domain and province to decide this question as to what is the effect of increasing the amount, if Mr. Makesh K. Chaudhary s contention is correct? This point shall be decided by me, if raised in the pleadings. In the result, the application is allowed to the extent indicated above. The application stands disposed of.