2004 Supreme(Del) 194

High Court Of Delhi
BASANT PROJECTS LTD - Appellant
Versus
BSES RAJDHANI POWER LTD - Respondent
W.P.(C.) 1275 of 2003
Decided On : 03/12/2004

Advocates Appeared:
AJAY KUMAR, JAYANT NATH, Sachin Chopra

Headnote:Constitution of India, 1950 - Article 226 — Disconnection of temporary electric connection — Plot auctioned by DDA — Instead of Permanent electric connection, temporary electric connection was provided which was sought to be disconnected — Electrification not yet complete even after a period of two years lapsed — Directions given to complete electrification and until then the same tariff should be charged as charged for permanent connection.

Manmohan Sarin, J.

( 1 )

( 2 ) PETITIONER has filed this writ petition, seeking restraint on the respondent/bses from dis-connecting the temporary electric connection, installed at premises bearing Plot No. 6, M. L. U. Pocket, Sector 12, Dwarka, Delhi.

( 3 ) THE facts leading to the filing of the present writ petition may be briefly noted:-

( 4 ) PETITIONER had purchased the plot in question in a DDA auction and after the sanction of plot, it raised construction. However, petitioner had only been sanctioned and provided a temporary electric connection, which apart from not catering to the needs of the consumers, is cost prohibitive.

( 5 ) COUNTER affidavit has been filed on behalf of the respondent/bses as also DDA. Mr. Jayant Nath on behalf of respondent/bses submits that DDA was to give BSES the 4th plot for setting up the sub-station, which had not been provided. Besides, he submits that DDA was sharing the cost of electrification with DVB (now BSES ). However, after the privatisation of DVB as BSES, DDA has been dragging its feet and hedging the issue.

( 6 ) LEARNED counsel further submits that the Regulatory Authority in one of the proceedings, initiated by DDA, has passed an order, directing that the earlier system, wherein the cost of electrification was shared between DVB and DDA, shall continue. Let DDA notify the respondent/bses of the terms and conditions for licensing of the 4th plot, requirement of which was indicated by BSES belatedly, as per DDA. Both DDA and BSES shall within a period of two months from today finalize the licence terms for the 4th plot, as also sharing of cost etc. , as required for electrification. Thereafter, BSES shall ensure that within eight months from today, the electrification work is completed.

( 7 ) LEARNED counsel for the petitioner makes an oral prayer that the plot that was auctioned by DDA was auctioned with the assurance that the infrastructure and amenities would be available. The electrification has not even been undertaken except for temporary connection provided. In these circumstances, as a period of two years has already elapsed without any default on the part of petitioner, I think this is a fit case that direction ought to issue to BSES that at least for a period of eight months, during which the electrification is to be completed by it, petitioner would be charged the tariff, as if it was a permanent connection. Ordered accordingly. The writ petition is disposed of with the above direction.

Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top