2000 Supreme(Del) 837

High Court Of Delhi
PARAS RAM SHARMA - Appellant
Versus
DELHI DEVELOPMENT AUTHORITY - Respondent
Suit 2596A of 1996
Decided On : 09/22/2000

Advocates Appeared:
S.K.Agarwal

Headnote:Arbitration Act, 1940 - Section 30 & 33 — Objections to award — Allegation that award regarding counter claim is totally arbitrary and capricious — Counter claim on account of recovery initiated in respect of works executed in or under water-works duly sanctioned by competent authority — Award made by the arbitrator is a possible view — Award made rule of the court.

S. K. Agarwal

( 1 ) THIS order will dispose of the objections filed by the respondent - Delhi Development Authority, against the Award of respondent No. 2 dated 25. 9. 1996 deciding some of the claims in favour of the petitioner and rejecting the counter claim of the respondent.

( 2 ) BRIEF facts are : that the petitioner (contractor) entered into an agreement with the respondent - (DDA) for execution of the work "development of Rohini Project Phase I upto Madhuban Chowk (2a to 2c) SH Outfall Storm water drain No. 2 alongwith outer Ring Road. " The work commenced with effect from 27. 11. 1988 and was required to be completed on 26. 11. 1989, but was actually completed on 26. 6. 1990. After completion of the work, the contractor claimed extra payment for the work executed in or under water and the same was sanctioned by the Competent Authority and conveyed to the petitioner vide letter dated 16th August, 1990. On 22. 3. 1995, under clause 25 of the Contract Agreement, the disputes between the petitioner and the respondent were referred to the sole arbitrator, the Super intendant Engineer, DDA. Both the parties filed their respective Claims/counter claims. On 25. 9. 96, the arbitrator published the award in favour of the petitioner, awarding Rs. 8,500. 00 on account of balance amount towards the final bill (Claim No. 1); Rs. 1. 00 lakh on account of security deposit lying with the department (claim No. 2) and Rs. 4,70,244. 00 for the work executed in or under sub soil water (claim No. 4 and counter claim No. 1 ). Interest at the rate of 12% per annum with effect from 28. 3. 1995 was also awarded. It is a reasoned award.

( 2 ) I have heard learned counsel for the. parties and have been taken through the award as well as relevant clauses of the contract.

( 3 ) LEARNED counsel for the Respondent - DDA challenged the award regarding claim No. 4 and counter claim No. 1, of Rs. 4,70,244. 00 on account of the recovery made by the department in respect of the work executed in or under water. It was argued that the same is totally arbitrary, capricious and without jurisdiction, as such payment is prohibited by clause 73 of the Additional Specification and Special Conditions for execution of the work. Learned counsel for the petitioner/claimant argued that Clause 73 could have applied if in the schedule of quantities some rates were provided for executing the work in/or under water, It is not so. The schedule of quantities did not provide for any payment for executing the work in/or under water conditions, therefore, Clause 73 does not apply. Alternatively, it was argued that even if the interpretation put on Clause 73 was a possible interpretation, the view taken by the arbitrator cannot be set aside, while considering objection under Section 30 of the Arbitration Act.

( 4 ) IN order to appreciate the rival contentions, it is necessary to refer to Clause 73 of the General Conditions of the Contract, which reads as under:

"nothing extra over and above the rates provided in the schedule of quantities, for executing in/or under water shall be paid for pumping and bailing out water by any method lowering of sub-soil water level during execution of work,"

( 5 ) MERE reading of Clause 73 shows that it prohibits any extra payment to the contractor for working in/or under water or for bailing out water by any method. This clause is clear and explicit. It does not admit any doubt. Law in this regard is well settled by several authoritative pronouncements of the Apex Court.

( 6 ) IN Steel Authority of India Ltd. v. J. C. Bidhraja, Government and Mining Contractor, (1999) 8 SCC 122 after taking into consideration several earlier decisions it was held:

"it is to be reiterated that to find out whether the arbitrator has travelled beyond his jurisdiction and acted beyond the terms of the agreement between the parties, the agreement is required to be looked into. It is true that interpretation of a particular condition in the agreement would be within the














Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top