High Court Of Delhi
DLF INDUSTRIES LIMITED - Appellant
Versus
HONG KONG AND SHANGHAI BANKING CORPORATION LIMITED - Respondent
Interim Application 1022 of 1998
Decided On : 02/01/1999
BANK GUARANTEE - ENCASHMENT - INJUNCTION - JURISDICTION - NOVATION OF CONTRACTS - VARIATION CLAUSE - LIABILITY OF SURETY - TERMS OF CONTRACT - FRAUD AND IRRETRIEVABLE INJURY - ARBITRATION - EQUITABLE OBLIGATIONS - PERFORMANCE GUARANTEE - ADVANCE PAYMENT GUARANTEE - IRRETRIEVABLE INJURY - LIQUIDATED DAMAGES.
Fact of the Case:
Petitioner, DLF Industries Ltd. (DLF), entered into a contract with respondent No. 3, M/s Atul Limited (Atul), for the expansion of a power project. The contract was split into three separate agreements for the purpose of performance guarantee and other guarantees. The project was to be commissioned by 15/3/1996, but the time was extended till 15/5/1997. The contract was not completed. Bank guarantees were given by Hongkong and Shanghai Banking Corporation Limited, Central Bank of India, and ABN Amro Bank for advance payment and performance guarantee clauses. DLF claimed that Atul could not make the payments in time, and meetings were held for novation of contracts in favor of State Bank of India (SBI). Atul approached DLF to accept the novation of the three contracts in favor of SBI. DLF accepted the novation and agreed to give fresh bank guarantees in favor of SBI. However, Atul ceased to be the contracting party as the purchaser of the equipment TG set, its design, and engineering services, etc. After the novation, there was no privity of contract between DLF and Atul. DLF claimed that the original contract could not be enforced anymore, and the bank guarantees furnished by Atul had become non-operational. Atul contended that the bank guarantees were irrevocable and unconditional and were payable on demand without any demur. SBI claimed that it was entitled to invoke the bank guarantee as Atul had ceased to be the purchaser in view of the novation of the contract.
Finding of the Court:
1. The Delhi courts had jurisdiction to hear the case as the bank guarantees were executed in Delhi, and none of the banks were bound by the agreement between DLF and Atul to have exclusive jurisdiction in Valsad, Gujarat. 2. There was no novation of the contracts in favor of SBI as the novation was not fully implemented by both parties, and the bank guarantees were never executed by DLF in favor of SBI. 3. The variance clauses in the bank guarantees allowed the purchaser to vary the terms and conditions of the contracts without the consent of the banks, and such variation did not discharge the principal debtor or the banks giving bank guarantees. 4. Atul could invoke the bank guarantees as the term "purchaser" covered both Atul and SBI, and the Memo of Understanding between the parties allowed Atul to invoke the bank guarantees. 5. The bank guarantees were not invoked strictly in terms of the bank guarantee as they did not specify the amount claimed and the reason for the claim, but this technicality would not defeat the claim of Atul in the absence of any allegation of fraud or irretrievable injury to DLF. 6. The encashment of the bank guarantee for Rs. 115 lakhs could not be stopped as there was no fraud or irretrievable injury alleged by DLF, and the delay in the installation of the T.G. set caused loss to Atul. 7. The encashment of the bank guarantee for Rs. 1.88 lakhs could be allowed as the rest of the amount had been adjusted by deductions from the bills.
Issues: 1. Whether the Delhi courts had jurisdiction to hear the case? 2. Whether there was a novation of the contracts in favor of SBI? 3. Whether the variance clauses in the bank guarantees discharged the principal debtor or the banks giving bank guarantees? 4. Whether Atul could invoke the bank guarantees? 5. Whether the bank guarantees were invoked strictly in terms of the bank guarantee? 6. Whether the encashment of the bank guarantee for Rs. 115 lakhs could be stopped? 7. Whether the encashment of the bank guarantee for Rs. 1.88 lakhs could be allowed?
Ratio Decidendi: 1. The territorial jurisdiction of a court is determined by the place where the cause of action arose and the agreement of the parties to confer exclusive jurisdiction on a particular court. 2. Novation of a contract requires the consent of all parties involved, and the original contract is discharged only when the new contract is fully implemented. 3. A variance clause in a bank guarantee allows the purchaser to vary the terms and conditions of the contract without the consent of the bank, and such variation does not discharge the principal debtor or the banks giving bank guarantees. 4. The term "purchaser" in a bank guarantee covers both the original purchaser and any subsequent purchaser who acquires the rights and obligations of the original purchaser. 5. A bank guarantee must be invoked in accordance with the terms of the guarantee, but technical deviations from the prescribed form may be overlooked in the absence of fraud or irretrievable injury to the party against whom the guarantee is invoked. 6. The encashment of a bank guarantee can be stopped only on the grounds of fraud or irretrievable injury to the party against whom the guarantee is invoked. 7. The encashment of a bank guarantee for a specific amount can be allowed if the beneficiary of the guarantee has suffered a loss to that extent, and there is no evidence of fraud or irretrievable injury to the party against whom the guarantee is invoked.
Final Decision: OMP 20/98 and IA 1022/98 were allowed, and the respondents were restrained from encashing the bank guarantee. OMP 21/98 and IA 1023/98 were decided accordingly, allowing the respondents to encash the bank guarantee only to the extent of Rs. 1.88 lakhs. OMP 22/98 and IA 1024/98 were dismissed.
( 1 ) THIS judgment shall dispose of three OMP No. 20/98, 21/98 and 22/98 and above-mentioned IAs therein for all the three OMPs and IAs relate to one original tender/contract, requiring different bank guarantees and seek injunction against encashment of bank guarantees and as such based on similar questions of facts and law.
( 2 ) RELEVANT facts relating to these OMPs are as under:
2. 2 M/s Atul Products Limited (now known as Atul Limited since 22/7/1998) invited tender for expansion of power project by setting up an 18 MW steam turbine generating set at their factory situated at Valsad on a turn-key basis. The tender of the petitioner was accepted. Respondent No. 3 issued a Letter of Intent dated 1/2. 2. 95 for a lumpsum price of Rs. 10 crores. However, the parties agreed to split the said Letter of Intent into three separate agreements for the purpose of performance guarantee and other guarantee. Respondent No. 3 claims to be entitled to enforce their rights in respect of all the three aeements equally and for that purpose the three agreements were to be treated as one agreement only. The project was to be successfully commissioned by 15/3/1996. Hower, time was extended till 15/5/1997. The contract was not completed.
( 3 ) IN OMP No. 20 of 1998, Hongkong and Shanghai Banking Corporation Limited gave Bank Guarantee for a sum of Rs. 7. 1 lakhs for advance payment in respect of a part of the same agreement, i. e. contract No. APL/p-131/5 BC/e1 dated 3/5/1995 - equivalent to 10% of the total value for erection and commissioning services. 3. 2. In respect of OMP No. 21 of 1998 contract No. APL/p/31/5bc/d1 dated 27/2/1995 dated 27/2/1995 the Central Bank of India gave two bank guarantees. One is for advance payment and agreed to pay Rs. 653. 01 lakhs being equivalent to 10% of the supply value for the said order. Second is also for advance payment in respect of other part of the same agreement equivalent to 10% of design and engineering value of contract No. APL/p-131/5bc/d1 dated 27/2/1995 for a sum of Rs. 13. 5 lakhs. 3. 3 Similarly in OMP No. 22 of 1998 ABN Amro Bank gave performance bank guarantee for a sum of Rs. 115 lakhs in respect of another part of the same agreement being contract No. APL/p-131/5bc/d1 dated 1/3/1995. 3. 4 It is claimed by the petitioner DLF Industries Ltd. ("dlf" for short) that respondent No. 3, M/s Atul Limited could not make the payments in time. Meetings took place between Atul Ltd. ("atul" for short) on 17/5/1995, 17/9/1995 and 27/3/1996 for novation of contracts in favour of State Bank of India ("sbi" for short ). Ultimately Atul approached the petitioner vide letter dated 29/3/1996 forwarding letter of respondent No. 2 SBI dated 29/3/1996 to accept the novation of the three contracts between the petitioner and the respondent No. 3 as the contract between petitioner and State Bank of India respondent No. 2. Both the respondents had requested petitioner vide letter dated 29/3/1996 to accept the novation of the actual amount in favour of respondent No. 2. The petitioner accepted the novation by letter dated 29/3/1996 and agreed to give fresh bank guarantees in favour of SBI and asked for return of bank guarantees given to Atul for amending bank guarantees in favour of SBI. Thus, respondent No. 3 ceased to be the contracting party as "purchaser" of the equipment TG set, its design and engineering services etc. After the novation there is no privity of contract between the petitioner and respondent No. 3. Since the novation of contracts between State Bank of India and M/s. Atul Limited is without there being any consent of concerned Banks giving bank guarantees, Hongkong and Shenghai Bank, the Central Bank of India and of ABN Amro Bank stand discharged from making the payment under the bank guarantees in dispute. According to the petitioner, firstly, in terms of Section 62 of the Contract Act, the original contract could not be enforced any more and in terms of Section 133 of the India
REFERRED TO : Globe Transport Corporation V. Triveni Engineering Works and Anr.
Aligarh Muslim University and Anr. V. Vinay Engineering Enterprises (P) Ltd.
Cholamandlam Investments and Finance Co. V. Radhika Synthetics and Anr.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.