High Court Of Delhi
AARKEY ENGINNIERING COMPANY - Appellant
Versus
DELHI DEVELOPMENT AUTHORITY - Respondent
Suit 3771A of 1992
Decided On : 03/18/1999
ARBITRATION - AGREEMENT - CONSTRUCTION - COMPENSATION - LEVY - JUSTIFICATION - BREACH OF CONTRACT - AWARD - VALIDITY - INTEREST - ENTITLEMENT.
Fact of the Case:
The petitioner was awarded a contract for the construction of LIG houses by the respondent-DDA. The contract was rescinded by the respondent-DDA on 7.1.1989. The matter was referred to arbitration and the Arbitrator published his award on 28.8.1992. The respondent-DDA filed objections under sections 30 and 33 of the Arbitration Act against the award.
Finding of the Court:
The court held that the Arbitrator had valid reasons for awarding compensation to the petitioner and that the rejection of the respondent-DDA's counter-claim was justified. The court also held that the petitioner was entitled to interest @ 12% p.a. on the sum awarded by the Arbitrator from the date of decree till realization.
Issues: 1. Whether the Arbitrator had jurisdiction to deal with the question of compensation leviable under Clause (2) of the agreement. 2. Whether the Arbitrator was justified in awarding compensation to the petitioner. 3. Whether the Arbitrator was justified in rejecting the respondent-DDA's counter-claim.
Ratio Decidendi: 1. The court held that the Arbitrator had jurisdiction to deal with the question of compensation leviable under Clause (2) of the agreement as the same was not in the exclusive domain of the S.E. 2. The court held that the Arbitrator was justified in awarding compensation to the petitioner as the respondent-DDA had committed a breach of the contract by rescinding it without fulfilling their obligations in terms of the agreement. 3. The court held that the Arbitrator was justified in rejecting the respondent-DDA's counter-claim as the levy of compensation under Clause (2) of the agreement was wholly unjustified.
Final Decision: The court made the award dated 28.8.1992 a rule of the Court and directed the respondent-DDA to pay the petitioner the sum awarded by the Arbitrator along with interest @ 12% p.a. from the date of decree till realization.
( 1 ) IN response to the tender invited by the respondent-DDA, the work for construction of certain LIG houses at Hastal was awarded to the petitioner vide agreement No. 8/ee/wd-9/dda-88-89. The stipulated date of commencement of work was 9. 7. 1988 and the same was to be completed on 8. 10. 1989. On 7. 1. 1989, the respondent-DDA rescinded the contract. Consequent upon some disputes having arisen between the parties, the matter was referred to the arbitration in terms of the arbitration agreement. The Arbitrator published his award of 28. 8. 1992.
( 2 ) WHILE the petitioner filed an application for making the award a rule of the Court, the respondent-DDA has filed objections under section 30 and 33 of the Arbitration Act against the award. The respondent is mainly aggrieved by the rejection of counter-claim No. 2 and award on claim No. 3 preferred by the petitioner. Learned Counsel for the respondent contended that in view of Clause (2) of the agreement, the Arbitrator has no jurisdiction to deal with th,e question of compensation leviable under Clause (2), as the same was in the exclusive domain of the S. E. Strong reliance was placed on the decisions rendered in Sudhir Bros. v. DDA, 1995 (2) ALR 437 and P. C. Corporation v. Chief Administrator Dandkamaya Project, AIR 1991 SC 957. It needs to be high lighted that similar arguments were considered and rejected in the case of Vikas Engineering Co. v. DDA, 1995 (1) A. D. 1408. The decision in Sudhir Bros v. DDA, and P. C. Corporation v. Chief Administrator, Dandkarnaya Project (supra), are distinguishable on facts and their ratio decident does not govern a case like in hand. It is significant to mention that the Arbitrator had observed that the respondent-DDA has committed a breach of the contract by rescinding the same without fulfilling their obligation to hand over foundation drawing, etc. The petitioner preferred a claim of Rs. 10,43,557. 00 before the Arbitrator. The Arbitrator reduced the claim of Rs. l,13,000. 00. It would be useful to extract reasons assigned by the Arbitrator for partly allowing the claim No. 3 as under;
"this claim is for loss incurred by the claimants of anticipated profit at the rate of Rs. 10. 00 of the contract amount of Rs. 1,04,35,571. 00. After having arrived at the conclusion in claim No. I that the respondents had committed a breach of contract by rescinding the contract without fulfilling their fundamental obligation of. handing over the foundation drawing, the question of consideration is the admissibility of compensation to the claimants on account of loss of anticipated gain. Denial by the respondents was mainly on the ground that this claim is not covered under any clause/condition of the agreement and also from point of view of law of equity and natural justice. This was strongly contested by the claimants. I feel that the objection raised by the respondents are not sustainable in view of Section 73 of the Indian Contract Act which provides for compensation for loss of damage which naturally arose in the usual course of things from such breach or which the parties knew when they made the contract to be likely to result from the breach. Therefore, I hold that the claimants are entitled to receive compensation for loss of profit which they were expected to earn by executing the work under contract. However, there is no evidence on record to establish that the claimants have provided for an element of 10% profit in their tendered rates in the said agreement, but I accept the contention of the claimants that it is a general practice in this trade to allow 10% to cover overheads and profit when estimates are made for this type of work. In this case the preliminary arrangement such as C/o site office, cement godown, water tanks were made by the claimants. They also collected certain materials like bricks and stone aggregate. However, the claimants are not entitled for the profit on the stipulated material. Moreover the claiman
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.