1999 Supreme(Del) 945
High Court Of Delhi
KISHAN CONSTRUCTION COMPANY - Appellant
Versus
DELHI DEVELOPMENT AUTHORITY - Respondent
First Appeal Order 225 of 1998
Decided On : 11/01/1999
A.SALVAN, G.D.GANDHI
Claims and counterclaims that are connected and arise out of the same contract are inseparable in nature and should be considered together by the arbitrator.
Headnote:
ARBITRATION - SETTING ASIDE AWARD - CLAIMS AND COUNTER CLAIMS - INSEPARABLE IN NATURE - AWARD SET ASIDE AND REMITTED BACK TO ARBITRATOR FOR CONSIDERATION OF CLAIMS AND COUNTER CLAIMS AFTER NOTICE TO PARTIES.
Fact of the Case:
The appellant and the respondent entered into a contract, disputes arose, and the disputes were referred to arbitration. The arbitrator made an award rejecting the claims of the respondent and disposing of the counterclaims of the appellant. The appellant filed objections before the Additional District Judge to remit the counterclaim to the arbitrator, and the respondent filed objections to set aside the award. The Additional District Judge set aside the entire award and remitted it back to the arbitrator to consider the claims and counterclaims of the parties after notice to them.
Finding of the Court:
The Additional District Judge was justified in holding that the claims and counterclaims of the parties were inseparable in nature and in setting aside the entire award and remitting it back to the arbitrator to consider the claims and counterclaims of the parties after notice to them.
Issues: Whether the claims and counterclaims of the parties were inseparable in nature.
Ratio Decidendi: The claims and counterclaims of the parties were connected and arose out of the same contract. The arbitrator did not give any reasons for rejecting the claims of the respondent for Rs. 36,008.00 and Rs. 9,063.00.
Final Decision: The appeal was dismissed.
( 2 ) PURSUANT to a contract entered into between the parties, disputes arose between the parties and the said disputes were referred to the sole arbitration of Sh. S. C Kaushal in terms of clause 25 of the agreement. Pursuant to the aforesaid reference the arbitrator entered into the reference and considered the claims and counterclaims of the parties and made his award on 4. 1. 94. By the aforesaid award the arbitrator held that all the three claims of DDA were not justified and accordingly rejected the said claims, ln respect of the counter-claims of the appellant he held that no counter-claim came up duly referred by the Chief Engineer and with the said observations he disposed of the counter-claims accordingly. As against the aforesaid award passed by the arbitrator the appellant herein filed objection before the Additional District Judge praying for remitting back the counter-claim to arbitrator for deciding the said counter-claims of the appellant. Objections were also filed by the respondent for setting aside the award given in respect of claims of the DDA. The Additional District Judge took up the aforesaid objections for consideration and disposed of the same by setting aside the entire award and remitted back the same to the arbitrator to consider the claim and counter-claims of the parties after notice to them. Being aggrieved by the said order, the present appeal has been filed by the appellant.
( 3 ) ACCORDING to the counsel for the appellant, the Additional District Judge was not justified in holding that the claims and counter claims of the parties were inseparable in nature, for according to him claims made by the DDA and counter-claims of the appellant herein are independent claims having no bearing and relevance with each other.
( 4 ) COUNSEL for the respondent, however, submits that no appeal has been preferred by the respondent herein taking in to consideration the fact that entire award was set aside by the trial court although the objection filed by respondent was required to be disposed of by the Additional District Judge by allowing the same.
( 5 ) I have considered the rival submissions of the counsel for the appellant as also the counsel for the respondent. The claims of the respondent, which were referred for arbitration were three-fold in nature. The first claim of Rs. 84,671. 00 was on account of rescission of contract, whereas the second claim was for an amount of Rs. 25,000. 00 towards cost of the proceedings and the third claim was for payment of interest. The aforesaid three claims were referred to the arbitrator for his decision by a specific order of the court. It also transpires from the records that by an order dated 15. 7. 93, the appellant herein was allowed to raise counterclaims before the arbitrator also. Pursuant thereto certain counter-claims were raised before the arbitrator, namely, Counter-Claim No. 1 which was on account of actual work done at site. Counter- Claim No. 2 which was a claim on account of loss of labour. Counter-Claim No. 3 was in respect of cost of construction of store and other accommodation at the site. Claim No. 4 was on account of loss of material. Claim No. 5 was towards interest and Claim No. 9 was for payment of cost ot arbitration proceedings. The Additional District Judge by setting aside the award remitted back to the arbitrator the entire award with directions to him to consider the claim of the DDA as also the counter-claims of the appellant here in.
( 6 ) I have gone through the findings recorded by the arbitrator in respect of Claim No. l which was a claim for payment of Rs. 84,671. 00 on acc