SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1998 Supreme(Del) 494

High Court Of Delhi
SPECTRUM TECHNOLOGIES USA INC. - Appellant
Versus
SPECTRUM POWER GENERATION COMPANY LIMITED - Respondent
Interim Application 11435 of 1997
Decided On : 07/16/1998

Advocates Appeared:
A.K.SUDHARKAR RAO, AJAY ROY, ARPANA KAUL, BINA GUPTA, M.M.Rao, Manmohan, N.M.RAO, R.R.SINGH, RAMJEE SRINIVASAN, Ritu Bhalla, Ruchi Narula

Headnote:Civil Procedure Code, 1908 - Order 1 Rule 10 — Impleadment of parties — Necessary parties — Considerations for — Plaintiff cannot be permitted to expand the scope of suit unnecessarily to confuse the main issue for taking into consideration material relevant as evidence for side issues — A party not interested in denying the rights of the plaintiff is not required to be made a party.

       Held:

       ".....(1) If, for the adjudication of the "real controversy" between the parties on record, the presence of a third party is necessary, then he can be imp leaded; (2) It is imperative to note that by such impleading of the proposed party, all controversies arising in the suit and all issues arising there under may be finally determined and set at rest, thereby avoiding multiplicity of suits over a subject-matter which could still have been decided in the pending suit itself; (3) The proposed party must have a defined, subsisting, direct and substantive interest in the litigation which interest is either legal or equitable and which right is cognisable in law; (4) Meticulous care should be taken to avoid the adding of a party when the addition is intended merely as a ruse to ventilate certain other grievances of one or the other of the parties on record which is neither necessary nor expedient to be considered by the Court in the pending litigation; and (5) It should always be remembered that considerable prejudice would be caused to the opposite party when irrelevant matters are allowed to be considered by Courts by adding a new party whose interest has no nexus to the subject-matter of the suit."

       Applying all the five tests, if does not appear that in the present matter, IDBI has any substantive legal interest in questions arising and involved in the suit, which cannot be decided without IDBI making a party. Of course, their presence may be necessary to prove the alleged admission, presence of their Director on the Board of Directors of defendant No.1 through awareness.

       The IDBI does not appear to be interested in denying the rights of the plaintiff for the purpose of proving an admission on the part of defendant. As such, the IDBI is certainly not required to be made a parly.

       There cannot be any dispute in aforesaid such circumstances that IDBI is neither necessary nor proper party nor its presence as a party is likely to enable this court in effectually deciding the matter. In so far as the question of bringing on record admission etc. is concerned, it would be brought on record by summoning witness with the record of IDBI to prove the same without impleading them as a party.

S. N. Kapoor, J.

( 1 ) THE crux of the dispute in this matter depends on an answer to the question: "whether the IDBI is the necessary or proper party and whether its presence would help and enable this court to effectually and completely adjudicate upon and settle all the questions involved in this suit?"

( 2 ) THE plaintiff filed a suit seeking "a mandatory injunction directing defendant Nos. 2 and 3 to make necessary amendments in the Articles of Association in accordance with the requirement of promoters agreement dated 29th June 1993", "a declaration that the resolution at item No. 9 passed by the Board of Directors of defendant No. 1 in its 27th meeting held on 14th November 1995 is illegal and ultra vires the promoter agreement dated 29th June 1993 and parties were still bound by the promoters dated 29th June, 1993" and further seeking "a declaration that Dr. A. V. Mohan Rao and Mr. Brij Bhartelly are and continue to be members of the Board of Directors of defendant No. 1 on behalf of the plaintiff and also Mr. C. P. Jain, Director (Finance), NTPC to be inducted in the Board of Directors of defendant No. 1 as nominee of defendant No. 3. " There are other prayers also which are not relevant for the present purpose. Thus, the suit is intended to enforce the promoters agreement and rights arising therein.

2. 2 The plaintiff, defendant No. 2 and 3 entered into a joint venture for building, owning and operating a gas based power plant for the Government of Andhra Pradesh at Kakinada on the basis of promotors agreement dated 29th June 1993. Defendants No. 2 and 3 have violated the promotors agreement. A loan agreement was entered into between the joint venture company defendant No. 1 and IDBI on 11th August 1984. The plaintiff company gave undertaking to financial institution IDBI to the effect that if there was any shortfall in the resources for completing the project or working capital or any cost over runs then it would be met by them. On this basis IDBI is sought to be impleaded as a party. According to the case of defendant No. 1, the promoters agreement has outlived its utility and parties have started dealing it now as a dead letter. But on March 12, 1998, defendant No. 1 in its letter to IDBI enclosed a compliance chart of various pre-disbursement conditions indicating that the Promoters Agreement had been entered into and the plaintiff is one of the promoters. The plaintiff s grievance is that though the defendant No. 1 is in dire need of additional funds with huge cost over runs of Rs. 190 crores and debt equity ratio that has been turned topsy turvy by the defendants. The defendant No. 1 is not ready to issue further shares to the plaintiff. The impleadment of proposed defendants No. 4 and 5 namely IDBI head office as well as Hyderabad Branch office would enable this court to effectually and completely adjudicate upon and settle all the questions involved in this suit especially the question of safeguarding the public money invested by the financial institutions. No relief is being sought against IDBI by the plaintiff. The proposed defendants No. 4 and 5 are one and the same persons and they cannot be treated separately.

2. 3 It is contended by the learned counsel for the plaintiff that the plaintiff has a dominus litis, in this suit. The IDBI has no objection to its impleadment. Defendant No. 1 has no right to object to the present application. He relies on Razia Begum Vs. Sahebzadi Anwar Begum and Ors. AIR 1958 SC 886 (p. 896 para 13) and Gonsalo De Filomena Luis Vs. Inacio Piedade Hildeberte Fernandes and Ors. , AIR 1977 Goa 4.

( 3 ) THE stand of the IDBI is that the IDBI being a premiere financial institution, is charged with the responsibility of financing projects contributing towards industrial development of the nation. As a matter of policy and principle, it does not normally concern itself with the inter se disputes between the promotors in respect of the projects being financed by it. However, the IDBI h
























Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top