High Court Of Delhi
HINDUSTAN CONSTRUCTION CORPORATION - Appellant
Versus
DELHI DEVELOPMENT AUTHORITY - Respondent
Decided On : 10/30/1998
ARBITRATION ACT, 1940 - SECTION 28 - AMENDMENT ACT 1 OF 1997 - CLAUSE (B) - AWARD SET ASIDE - ARBITRATOR DIRECTED TO DECIDE CLAIMS ON MERITS - CLAUSE 25 OF THE AGREEMENT HELD VOID.
Fact of the Case:
Petitioner filed objections against an arbitration award, arguing that the arbitrator erred in finding that the claim was barred by time and that the letter raising disputes within 90 days of payment of the final bill was irrelevant. The respondent contended that the arbitrator acted correctly and that the invocation for arbitration had to be within 90 days from the date of intimation of the final bill.
Finding of the Court:
The court found that the arbitrator did not decide the claims on merit and that the clause in the agreement limiting the time for invoking arbitration was void under Section 28(b) of the Contract Act, as amended by Amendment Act 1 of 1997.
Issues: Whether the arbitrator was justified in finding that the reference to arbitration was barred by time.
Ratio Decidendi: The court held that the clause in the agreement limiting the time for invoking arbitration was void under Section 28(b) of the Contract Act, as amended by Amendment Act 1 of 1997, and that the arbitrator erred in finding that the claim was barred by time.
Final Decision: The court allowed the objections, set aside the award, and directed the arbitrator to decide the claims on merit.
( 1 ) -AN award dated january 17,1994 rendered by Shri Dandage, sole arbitrator was filed before the Court.
( 2 ) ON the filing of the said award notices were issued to both the parties vide order dated august 12, 1996. The petitioner filed objections against the said award (vide I. A. No. 11143/96) under Sections 30 and 33 of the arbitration Act, The respondent did not prefer any objections against the said award despite service of notice on them. However, they filed a reply to the objections preferred by the petitioner.
( 3 ) IT has been urged for and on behalf of the objector that there is an error apparent on the face of the award inasmuch as the award has not been rendered on merits. The learned arbitrator fell into a grave error by coming to the conclusion that the claim of the petitioner was barred by time. The claimant failed to invoke the arbitration clause within a period of 90days of the preparation of the final bill as per the conditions of the contract. The learned arbitrator overlooked and ignored the letter dated May 7, 1984 written by the petitionet ex. C5 wherein the disputes Were raised by the petitioner giving rise to the present claim within 90 days of the payment of the final bill which even according to the award is April 16, 1984. Thus the learned arbitrator has mis-conducted himself and the proceedings and the impugned award referred to above is liable to be set aside.
( 4 ) LEARNED counsel for the respondent while countervailing the said argument has contended that the arbitrator has neither mis conducted himself nor the proceedings. There is no error apparent on the face of the award. Both the parties are bound by the terms of the contract. According to clause 25 of the agreement the invocation for arbitration has to be within 90 days from the date of intimation that the final bill is ready for payment. The period of 90 days would start running from the date of the intimation of the final bill. It would not run from the date of payment of the final bill. The letter dated May 7, 1984 was therefore, absolutely irrelevant. The objections are false and frivolous and are thus liable to be dismissed.
( 5 ) IT is manifest from above that the only issue which arises to be adjudicated upon in the present case is as to whether the learned arbitrator was justified in coming to the conclusion that the reference to the arbitration was barred by time. According to the learned arbitrator as per his finding (vide para 6. 4 of the award dated January 17,1994) the claimant demanded the arbitration much after the limit of 90 days not only from the date of payment of final bill but also from the date of release of the amount withheld therein. Hence the claims of the claimant were held to be barred by time.
( 6 ) SINCE we are concerned with the construction of C1. 25 of two agreement, the same can be adverted to with profit. It is in the following words:-
"it is also a term of the contract that if the contractor (s) does (do) not make demand of arbitration in respect of any claim (s) in writing within 90 days of the intimation from the Engineer-in-Charge that the Bill is ready for payment the claim (s) of the contractor (s) will be deemed to have been waived absolutely and the Delhi Development Authority shall be discharged and released of all liabilities under the contract in respect of those (these) claims. "
( 7 ) LEARNED counsel for the respondent on the basis of the above clause in the contract has contended that there is nothing wrong with the award. inasmuch as the claimant demanded arbitration much after the limit of 90 days.
( 8 ) LEARNED counsel for the petitioner on the other hand has argued that the said clause is hit by an amendment which has been made to Section 28 of the Contract Act (vide Amendment act 1 of 1997) whereby clause (b) has been incorporated therein. Section 28 of the contract Act deals with agreements in restraint of legal proceedings, void. It envisages as under:-
"every agreeme
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.