1997 Supreme(Del) 389

High Court Of Delhi
RAM CHAND VERMA - Appellant
Versus
DELHI DEVELOPMENT AUTHORITY - Respondent
Contempt Civil Petition 10 of 1989
Decided On : 04/28/1997

Advocates Appeared:
ABHILESH VERMA, N.S.Safaya, Ravinder Sethi

Before finding contempt of court, it is essential to establish the service of the court order upon the alleged contemner.

Headnote:

Contempt of Court - Arbitrary Allotment - The court found that the respondents were not aware of the stay order and therefore did not act in breach of it. The contempt proceedings were dropped and notices issued against the respondents were discharged.

Fact of the Case:

The petitioner was allotted a plot in a residential scheme, but the allotment was cancelled arbitrarily. The petitioner obtained a stay order against the cancellation, but the respondents allegedly disobeyed the stay order by allotting the plot to another party.

Finding of the Court:

The court found that the respondents were not aware of the stay order and therefore did not act in breach of it. The contempt proceedings were dropped, and notices issued against the respondents were discharged.

Issues: Violation of stay order, contempt of court

Ratio Decidendi: Before a proceeding for contempt can succeed, it is important to establish the service of the court order upon the person alleged to have committed contempt. In this case, the court found that the stay order was not communicated to the respondents, and therefore they did not act in breach of it.

Final Decision: The contempt proceedings were dropped, and notices issued against the respondents were discharged. Contempt proceedings were quashed.

M. S. A. Siddiqui, J.

( 1 ) THE petitioner was allotted plot No. 111, Block E, in Malviya Nagar Extension Residential Scheme, New Delhi. Thereafter the respondent No. 1 cancelled the allotment arbitrarily. Aggrieved by the said action the petitioner filed a writ petition under Article 226. On 27. 5. 1981 the petitioner obtained a stay order from this Court against cancellation and dispossession. It is alleged that inspite of the stay order the respondent Nos. 1 to 3 allotted the said plot to the respondent No. 5 who had in turn transferred the same to the respondent No. 4. It is further alleged that the respondents have contumaciously disobeyed the stay order dated 27th May, 1981 by allotting the plot to the respondent 5 and thus they are liable to be punished under Section 12 of the Contempt of Courts Act.

( 2 ) ON this petition a Rule was issued by this Court on 8. 2. 1989 calling upon the respondents to show cause why they should not be dealt with for contempt for the alleged violation of the Court s Order dated 27. 5. 1981 in CWP 1273/81. In response to the Rule issued on the respondents, the respondents 1 to 3 have shown cause and have taken up the plea that the Court s order dated 27. 5. 1981 was not communicated to them. It is further alleged that the allotment of the plot in question had already been cancelled vide letter No. F 27 (64)79/lsb (R) dated 6. 5. 1981 and thus by the time the stay order was passed on 27. 5. 81 the petitioner s allotment had already been cancelled and in such a situation no question of staying of the cancellation of the allotment arose. It is further alleged that after cancellation of the allotment, possession of the plot in question was also taken over by the respondent-DDA. It is, therefore, alleged that the respondent had not violated the order dated 27th May, 1991.

( 3 ) BEFORE a proceeding for contempt can succeed, it is of paramount importance to establish first, the service of the order of the Court said to have been disobeyed upon the person alleged to have committed contempt thereof. In view of the plea taken by the respondents that the alleged act of contempt was anterior to the date of the communication of the order, this Court on 24. 1. 1991 directed the respondent-DDA to inform about the name of the person incharge on whom the responsibility can be fixed. Pursuant to the said direction Shri O. P. Sharma, Deputy CLA (Lands), Delhi Development Authority filed his affidavit fixing the responsibility on the Peshi Clerk Shri N. S. Gautam. Consequently, Shri Gautam was summoned and his statement was recorded on 1. 8. 95. He testified that the stay order in question was not received by him. Shri O. P. Sharma and Shri Rakesh Behari, Commissioner (Lands) DDA have stated in their affidavit s that the said stay order was not communicated to the DDA. There is no reason to disbelieve their affidavit s. Relying upon the affidavit of Shri Rakesh Behari and Shri O. P. Sharma, I find and hold that the stay order dated 27th May, 1981 was not communicated to the respondents and on account of non communication of the stay order the plot No. 111, Block E, Malviya Nagar, Extension was transferred to respondent No. 4 in 1985.

( 4 ) IN this connection 1. may usefully excerpt the following observations of the Supreme Court in the case of Debabrata Bandopadhyaya and Others v. The State of West Bengal, AIR 1969 SC 189 :

"a question whether there is Contempt of Court or not is n serious one. The Court is both the accuser a well as the judge of the accusation. It behoves the Court to act with as great circumspection as possible leaking all allowance for errors of judgment and difficulties arising from inveterate practices in Courts and Tribunals. It is only when a clear case of contumacious conduct, not explainable otherwise, arises that the contemner must be punished. "

( 5 ) IN this case there is nothing from which I can inter that the respondents were ever aware of the stay order dated 27. 5. 81 passed in C