1997 Supreme(Del) 264

High Court Of Delhi
SHILPI MODES PRIVATE LIMITED - Appellant
Versus
SHILPI UNITECH - Respondent
Interim Application 8710 of 1995
Decided On : 03/11/1997

Important Points

An agreement to enter into an agreement by which some critical part of the contract matter was left to be determined is no contract at all.

Subject

Contract Law - FORMATION OF CONTRACT

Act Referred

CIVIL PROCEDURE CODE : O.39 R.4, O.39 R.1, O.38 R.5, O.39 R.2

Headnote

PARTNERSHIP - DISSOLUTION - MOU - VALIDITY - INJUNCTION - ORDER 39, RULES 1 AND 2 READ WITH ORDER 39, RULE 5 OF THE CODE OF CIVIL PROCEDURE - COURT HELD THAT THE MOU IS NOT A CONCLUDED CONTRACT AND THE OWNERSHIP OF THE PLAINTIFF OVER THE SUBJECT MATTER OF THE AGREEMENT WAS NOT ESTABLISHED ON THE DATE OF AGREEMENT AND THE SAME WAS LEFT TO BE VERIFIED ON A FUTURE DATE. THEREFORE, THE INJUNCTION GRANTED EARLIER IS VACATED.

Fact of the Case:

Plaintiff filed a suit against the defendants seeking dissolution of the partnership firm and rendition of accounts. The plaintiff claimed that a partnership agreement existed between the plaintiff and defendant No. 2, and that the defendants had failed to honor their commitment under the MOU. The plaintiff also filed an application for an injunction to restrain the defendants from transferring or alienating the properties in dispute.

Finding of the Court:

The court found that the MOU was not a concluded contract as the ownership of the plaintiff over the subject matter of the agreement was not established on the date of agreement and the same was left to be verified on a future date. The court also found that the plaintiff had failed to prove the existence of a partnership agreement between the plaintiff and defendant No. 2.

Issues: Whether the MOU is a concluded contract.

Ratio Decidendi: The court held that a contract, terms of which are not certain cannot be said to be a concluded contract and the same cannot be enforced. In order to be a binding contract an agreement must be definite and certain.

Final Decision: The court dismissed the plaintiff's application for injunction and allowed the defendants' application to vacate the ad interim injunction.

Advocates Appeared:
ARUN JAITLEY, Nidhesh Gupta, P.C.Khanna, Rajan Sarin, RUCHI SINDHVANI

M. K. Sharma

( 1 ) THIS order shall dispose of the application filed by the plaintiff under Order 39, Rules I and 2 read with Order 39, Rule 5 of the Code of Civil Procedure and also the application namely, I. A. 9309/1995 filed on behalf of defendants 2 to 4 under Order 39, Rule 4 of the Code of Civil Procedure.

( 2 ) THE plaintiff instituted the present suit against the defendants seeking for a decree for declaration for dissolution of defendant No. 1 and also for rendition of accounts by defendant No. 2 and after such rendition of account to pass a decree in favour of the plaintiff and against defendants 2 to 4 in respect of the amount found to be due to it.

( 3 ) THE case pleaded in the plaint is that the defendant No. 1 is a single venture partnership of the plaintiff and the defendant No. 2. It is alleged that a partnership agreement between the plaintiff and the defendant No. 2 had come into existence and acted upon and that although in respect of the said single venture partnership entered into between the plaintiff and the defendant No. 2 no name was given but the said name as the defendant No. 1 could be used as the description of the fact that a partnership agreement between the two had come into existence. It is alleged that the plaintiff purchased 67acresofland in Villagegawal Pahari and another 40acres of land was acquired by it in Hyderpur. Besides the plaintiff company also had agreement with land owners for purchase of approximately 180 acres of land in Village Hyderpur. In respect of the aforesaid land the plaintiff entered into a partnership business with defendant No. 2 to develop the said land by both the parties for the purpose of colonisation project. It is stated that the defendants in the course of negotiations made detailed enqui"ies and all negotiations in respect of the aforesaid land. On 7. 10. 1991 the terms were reduced into writing in an alleged partnership agreement described as Memorandum of Understanding. A copy of the said Memorandum of Understanding is on record. The parties agreed that the expenses for development of the land which was in the ownership of plaintiff company through sale deed was to be shared between the plaintiff and defendant No. 2 company in the ratio of 55% for the plaintiff and 45% for the defendant No. 2, and the expenses for development of the land which was in the agreement for the purchase was to be shared in the ratio of 65:35 between the plaintiff and defendant No. 2 respectively. The defendant company under re-structured agreement assured the payment of Rs. 10 lacs per week from middle of November, 1991 till January, 1992 to fulfil the minimum requirement and in terms thereof the defendant company No. 2 gave two cheques of Rs. 15 lacs each alongwith covering letters that the payment of the same was assured. However, when the aforesaid 2 cheques were presented to the Bank the same were dishonoured on the ground that the "drawer had stopped the payment". In view of the failure on the part of the defendant No. 2 to honour its commitment under the MOU the present suit has been instituted by the plaintiff for the aforesaid reliefs.

( 4 ) ALONGWITH the plaint the plaintiff also filed an application under Order 39, Rules 1 and 2 read with Order 39, Rule 5 of the Code of Civil Procedure which was registered as I. A. 8710/1995. On 14. 9. 1995 this Court by an ad interim ex parte injunction passed in the aforesaid suit restrained the defendant No. 2 from transferring, alienating or parting with possession of the properties set out in Schedule a except for the purpose of running the business of defendant No. 2 till the next date.

( 5 ) THE aforesaid order apparently was passed by this Court on the basis of the statement made by the Counsel for the plaintiff that on taking of accounts the plaintiff would be entitled to atleast Rs. 815 crores from the defendants and that the partnership between the plaintiff and defendantno. 2isadmittedbythedefendants and that in reply to no