High Court Of Delhi
MOHINDER SINGH AND COMPANY - Appellant
Versus
UNION OF INDIA - Respondent
Suit 434A of 1988
Decided On : 03/08/1989
Arbitration Act - Construction Contract - The court directed the respondents to file the arbitration agreement in court and appoint an arbitrator to resolve the disputes arising from the construction contract.
Fact of the Case:
The petitioner sought direction for the respondents to file the arbitration agreement in court and refer the disputes for arbitration, arising from a construction contract for a Library Block in New Delhi. The respondents had made recoveries from the bill and certain payments for the work done were not made, leading to disputes.
Finding of the Court:
The court found that the disputes were covered under the arbitration clause of the agreement and directed the respondents to file the arbitration agreement in court. The Chief Engineer, C. P. W. D. was directed to appoint an arbitrator and refer the disputes for arbitration.
Issues: The issues involved the refusal of the respondents to appoint an arbitrator despite the existence of an arbitration clause, and the disputes arising from recoveries made from the bill and non-payment for work done.
Ratio Decidendi: The court relied on the arbitration clause in the agreement and the refusal of the respondents to appoint an arbitrator, leading to the direction for filing the arbitration agreement and appointing an arbitrator.
Final Decision: The petition was allowed, and the respondents were directed to file the arbitration agreement in court. The Chief Engineer, C. P. W. D. was directed to appoint an arbitrator and refer the disputes for arbitration. The petition was disposed of with parties bearing their own costs.
( 1 ) BY this petition under Section 8 and 20 of the Arbitration Act the petitioner seeks direction to the respondents to file the arbitration agreement in court and for reference of the disputes for arbitration.
( 2 ) THE petitioner was awarded the work for the construction of Library Block at M. A. M. C. , New Delhi (balance work) by agreement No. 31/ee/public Witness D-2/82-83. The work was completed on 18-9-1985. The respondent prepared the final bill on 30-7-1986 in respect of the work done by the petitioner which was accepted by the petitioner under protest. The case of the petitioner is that the respondents made certain recoveries from the bill and besides that certain payments had not been made for the work done. The claims for the payments was repudiated by the respondents. According to the petitioner certain disputes have arisen between the parties which are enumerated in para 7 of the petition. It is further stated that the agreement contain an arbitration clause which provides that all questions and disputes relating to claim or right arising out of the contract shall be referred to the sole arbitration of the person appointed by the Chief Engineer C. P. W. D. It is further stated that the disputes are covered under the arbitration clause and the respondents by letter dated 25. 7. 1986 were called upon to appoint an arbitrator which they have not done. The respondents acknowledged the receipt of the letter but informed the petitioner that the matter regarding appointment of an Arbitrator was under consideration. The respondents further informed the petitioner that all the claims were general in nature and were vague. Under these premises it is claimed that the respondents be directed to file the arbitration agreement in court and reference of the disputes for arbitration.
( 3 ) REPLY has been filed on behalf of Union of India. It is stated that no dispute was raised by the petitioner and he did not submit any list of claims to the department. The petitioner submitted various ambiguous and vague claims and he was informed by the department to elaborate certain claims before those claims could be referred to the arbitrator for adjudication. It is further stated that the respondents are willing to refer the matter to arbitration if the claims are clarified.
( 4 ) IN the rejoinder filed on behalf of the petitioner it has been denied that the claims were general in nature and were vague. However, the petitioner was directed by this court to give the details of the disputes mentioned in para 7 of the petition. The petitioner has filed the details of the claims. No other plea was taken by the respondents.
( 5 ) IN the result the petition is allowed. The respondents are directed to file the arbitration agreement in court. The Chief Engineer, C. P. W. D. is directed to appoint an arbitrator within 2 months from the date of communication of this order and refer the disputes mentioned in para 7 of the petition for arbitration. The Arbitrator shall make his award within 4 months from the date of entering upon reference. The petition is disposed of leaving the parties to bear their own costs.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.