SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1985 Supreme(Del) 21

High Court Of Delhi
EM AND EM ASSOCIATES - Appellant
Versus
DELHI DEVELOPMENT AUTHORITY - Respondent
Suit 1391 of 1984
Decided On : 01/11/1985

Advocates Appeared:
D.K.Syal, M.L.Jain

The liability under a bank guarantee ultimately remains with the party specified in the original main contract, and the demand letter must conform to the terms of the bank guarantee for encashment.

Headnote:

Bank Guarantee - Stay Application - The court granted a stay against the encashment of a bank guarantee by the respondent DDA, as the letter of demand did not conform to the terms of the bank guarantee, rendering it defective. The bank guarantee arose from the original main contract between the petitioner and the respondent, and the liability ultimately remained with the petitioner-contractor.

Fact of the Case:

The petitioner sought a stay against the respondent DDA from encashing a bank guarantee. The respondent resisted the application.

Finding of the Court:

The court found that the letter of demand by the DDA did not conform to the terms of the bank guarantee, rendering it defective. The court also held that the bank guarantee arose from the original main contract between the petitioner and the respondent, and the liability ultimately remained with the petitioner-contractor.

Issues: Interpretation of the bank guarantee terms, competence of the petitioner to move the stay application, and the liability under the bank guarantee.

Ratio Decidendi: The bank guarantee can be restrained from encashment if the demand letter does not conform to its terms, and the liability under the bank guarantee ultimately remains with the petitioner-contractor.

Final Decision: The DDA was restrained from encashing the bank guarantee due to the defective nature of the demand letter. The court ordered the copy of the order to be sent to the Bank.

Jagdish Chandra

( 1 ) BY means of this application brought under Section 41 read with Second -chedule of the Arbitration Act, 1940 and Order 39 Rules 1 and 2 of the Code of Civil Procedure the petitioner EM and EM Associates seeks a stay against the respondent Delhi Development Authority (to be referred to as DDA), their officers, agents and servants from encashing the bank guarantee/guarantee bond No. 44/82 for Rs. 46,300. 00.

( 2 ) THIS application is resisted by the respondent/dpa.

( 3 ) THE perusal of the bank guarantee shows that the Syndicate Bank (hereinafter to be referred to as the Bank) undertook to pay the amount due and payable under this guarantee without any demur on demand from the DDA staling that the amount claimed is due by way of loss or damages caused to or would be caused to or suffered by the DDA by reason of any breach on the part of the petitioner-contrator of any of the terms and conditions contained in the original contract between the parties on the basis of which this bank guarantee was given by the Bank. Copy of the letter of demand by the DDA upon the Bank is Annexure P-2 dated 15-10-1984 in which the following relevant lines appear :

". . . . IN this connection I am to state that the three agreements in question have been closed. We propose to encash the aforesaid bank guarantees. You are, therefore requested to send a demand draft for Rs. 1,73,637. 60 in favour of the E. E. /cpd-Vlll per messenger of this letter

( 4 ) THIS letter nowhere alleges or mentions that this amount has become due to the DDA on account of any loss or damages caused to or to be caused to or suffered by the DDA by reason of any breach of the original contract on the part of the petitioner-contractor. Not staling these averments in the aforesaid letter renders the letter not in consonance with the terms of the bank guarantee and under the circumstances this letter of the DDA is defective and consequently the bank guarantee cannot be invoked by the DDA. In this view of the matter the petitioner is entitled to the stay as prayed for.

( 5 ) THE contention of the learned counsel for the respondent/dda that this bank guarantee was contract only between the bank on the one hand and the DDA on the other for which reason the petitioner-contractor was not competent to move this stay application in respect of the invoking of the bank guarantee, does not appear to be tenable because the bank guarantee has arisen out of the original main contract between the petitioner on the one hand and respondent/dda on the other and the money covered under the bank guarantee, even though payable by the Bank, shall ultimately remained the liability of the petitioner-contractor.

( 6 ) IN view of the above discussion, DDA is restrained from encashing the bank guarantee on the basis of the aforesaid letter dated 15-10-1984 on account of its defective nature as pointed out above. Copy of this order may be sent to the Bank.

Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top