2006 Supreme(Del) 1801

High Court Of Delhi
ANIL KUMAR
LANDMARK INFRACON P.LTD - Appellant
Versus
U.O.I.THROUGH - Respondents
WPC 21269 Of 2005
Decided On : 10/09/2006

Subject

Land Acquisition - PETROLEUM AND MINERALS PIPELINES (ACQUISITION OF RIGHT OF USER IN LAND) ACT, 1962

Act Referred

CONSTITUTION OF INDIA : Art.226
PETROLEUM AND MINERALS PIPELINES ACQUISITION OF RIGHT OF USER IN LAND ACT : S.10, S.4(1), S.6, S.8, S.3

Headnote

Petroleum and Mineral Piplines (Acquisition of Land of User in Land) Act, 1962 Sections 3, 5 and 6 - Notification issued for acquisition of land - Challenged the action of the respondent to lay down the pipelines for carriage of petroleum products - No objection was filed by petitioner - At the time of notification, petitioner was not owner of the plot - Settled law that subsequent purchaser has no right to challenge the validity of notification and the court in exercise of jurisdiction, will not transgress into the field of policy decision Court was of view, the decision of the respondent to lay down the pipeline in a particular area cannot be termed malicious, arbitrary or whimsical and court in exercise of jurisdiction, will not transgress into the field of policy decision - No merit - Hence, writ petition dismissed. [Paras 36, 38 & 39]

Advocates Appeared:
A.D.N.RAO, RAJIV NAYAR, SIBA PRASAD DAS, SURESH KAIF, VIKAS DHAVAN


ANIL KUMAR, J.

( 1 ) THE petitioner has challenged the action of the respondent to lay down the pipelines for carriage of petroleum products through various plots of land of the petitioner and has sought a prohibition in laying down the pipelines in the manner as proposed by the respondents and to rationalize laying down the pipeline so as not to obstruct the petitioner from beneficial use and enjoyment of his land and to consider an alternative proposal as given by the petitioner for laying down the pipelines and quash the notification of right of user of certain areas of the land of the petitioner in plots bearing Khasra Nos. 753, 758, 759, 761, 763, 764, 765, 778/2, 793, 794 and 795 in Village Rajokri, New delhi.

( 2 ) AFTER the petition was filed by the petitioner, a Local Commissioner was appointed by the Order dated 16th November, 2005 to visit the site and submit report as to whether pipelines had been laid or only certain preparatory steps had been taken. The Local Commissioner appointed by the Court gave a report dated 18th November, 2005 observing inter alia that more or less work was done almost the entire length to different extent. While in some areas only trenches were dug whereas in other areas trenches were even covered after laying the pipes. There seems to be dispute with regard to laying of pipeline in khasra Nos. 758, 759/1, 759/2, 793 and portion of 794.

( 3 ) THE petition is contested by the respondents contending inter alia that as a result of the implementation of the Plans for the development of petroleum resources in the country, necessitating laying of petroleum pipelines in the country to serve as an efficient and cheap means of transport of distribution of petroleum and petroleum products has arisen. Though the land could be acquired under the Land Acquisition Act, 1894, however, it was considered appropriate to acquire the mere right of user of land for laying and maintaining the pipelines and accordingly the Petroleum and Mineral Pipelines (Acquisition of Land of User in Land) Act, 1962 was enacted empowering the central Government to acquire the right of user in any land if it appears to the government that it is necessary in the public interest to lay pipelines under said lands for transport of petroleum from one locality to another. The Act provides a detail procedure for acquisition of right of user for laying down the pipelines and use of the lands.

( 4 ) ACCORDING to the respondents in order to meet the expanding demand of the petroleum products within the NCR regions it was decided that in addition to the existing pipelines a second pipeline being an alternate and additional pipeline was decided to be laid from Indore to Delhi. The route was from Indore to Bijwasan to New Delhi via State of Madhya Pradesh, Rajasthan, Uttar Pradesh and Haryana.

( 5 ) TO lay down the last lap of the pipeline, Bharat Petroleum Corporation was appointed as an executing authority which carried out a detailed survey for selection of route from Piyala Village (Faridabad) to Bijwasan and the route was selected taking into consideration factors such as avoidance of any undulated areas to avoid exposure of pipelines in future, to avoid displacement of inhabitation, to avoid cutting of trees and ensure the shortest possible route with a minimum number of bends and, therefore, route was selected for acquiring the right of user passing through villages of Samalkha, Bijwasan, Nangaldeval, bharthal, Rajokri and Kapashera. The said route was selected because in the said area no development has taken place and the land was lying vacant and it was nearest available route to Delhi and the most of the area under 2001 Town and Country Planning Map', Delhi was comprised of area demarcated as recreational area as such would not have caused dislocation or prevented land use meant for construction activity.

( 6 ) CONSEQUENTLY, a notification No. 930 under Section 3 of the Petroleum and Mineral Pipelines (Acquisition of Land