2007 Supreme(Del) 1481

High Court Of Delhi
SANJAY KISHAN KAUL
GAIL (INDIA) LIMITED - Appellant
Versus
SURYA ROSHINI LIMITED - Respondents
OMP 405 Of 2007
Decided On : 07/24/2007

Advocates Appeared:
JAGJIT SINGH

The court emphasized the importance of upholding the Arbitrator's findings and the limited scope of interference with arbitration awards under the Arbitration and Conciliation Act, 1996.

Headnote:

Contract - Arbitration - Arbitration and Conciliation Act, 1996 - Article 30. 4. 1 - The Arbitrator found that the cap of an overall limit of 10% of the contract price was in respect of cost of replacement and installation of pipes and did not deal with reimbursement relating to consequential damages. The pipes failed during the Field Hydrostatic Test and the said failure caused defects in the pipes. The claim for differential in price between the two types of pipes was rejected as the gas could be supplied at the designed pressure of 25-30 kg/CM2 and the purpose of laying the pipeline for supply of gas to NTPC was achieved. The claim for serving other customers was rejected. The court dismissed the petition seeking interference with the Award.

Fact of the Case:

A contract was executed between the petitioner and National Thermal Power Corporation (NTPC) for the supply of gas. Disputes arose regarding the quality of line-pipes supplied by the respondent, leading to arbitration proceedings. The Arbitrator made an Award in favor of the petitioner, which was challenged in the present petition.

Finding of the Court:

The court found no grounds for interference with the Arbitrator's Award, as the claims and defenses were adequately examined, and the damages awarded were deemed sufficient. The court dismissed the petition seeking interference with the Award.

Issues: Quality of line-pipes supplied, reimbursement for consequential damages, and the interpretation of the contract terms were the key issues in dispute.

Ratio Decidendi: The court upheld the Arbitrator's findings on the cap of the overall limit of 10% of the contract price, the failure of the pipes during the Field Hydrostatic Test, and the rejection of the claim for differential in price between the two types of pipes. The court emphasized that the purpose of laying the pipeline for gas supply to NTPC was achieved, and the claim for serving other customers was rejected.

Final Decision: The court dismissed the petition seeking interference with the Arbitrator's Award.

SANJAY KISHAN KAUL, J.

( 1 ) A Contract was executed between the petitioner and National Thermal power Corporation ( for short, "ntpc" ) in terms whereof the petitioner agreed to supply gas to NTPC for its power plant at Village Mujheri, Tehsil ballabhgarh, District Faridabad, w. e. f. 01. 05. 1999. " In furtherance of the contract, the petitioner provided a tap off at Village Chainsa in its main gas pipe line running from Bijapur to Dadr. " A fourteen km. long Spur pipeline of 14 inches diameter from tap off point at Village Chainsa to the power plant of ntpc at Faridabad was also required to be laid. " The petitioner, thus, floated a global tender through its consultants on 11. 04. 1998 for procuring the line-pipes of two descriptions.

( 2 ) THE respondent is engaged in the business of production of electric welded pipes and tendered its bid document to the petitioner, which was accepted by the petitioner. " This resulted in a purchase order dated 12. 08. 1998 for supply of line-pipes, which was duly signed by the respondent in token of its acceptance on 20. 08. 1998. " The purchase order was subsequently modified in terms of the clarification sought by the respondent, such clarification being issued by the petitioner vide letter dated 26. 08. 1998.

( 3 ) IN furtherance of the contract, the line-pipes were supplied by the respondent to the petitioner and the same were laid and installed by the petitioner. " It is the case of the petitioner that the pipes failed the Field hydrostatic Test even before the requisite test pressure was reached and the petitioner resorted to alternative remedial measures for carrying out its operations under the contract with NTPC and incurred huge expenditure. " On 01. 03. 2000, the petitioner sent a notice of demand, which was rebutted by the respondent vide its letter dated 14. 03. 2000. " The respondent also claimed that, in any case, the liability to reimburse the petitioner for alleged failure of its pipes during the Field Hydrostatic Test was only to the extent of 10% of the contract value.

( 4 ) THE disputes between the parties not having been resolved, the petitioner initiated arbitration proceedings under Article 30. 4. 1 to the General terms and Conditions of the Contract as set out in the letter dated 01. 03. 2000 and also requested the respondent to select an Arbitrator from the panel of three persons mentioned in the letter. " The respondent in turn requested for negotiation in a subsequent letter dated 10. 05. 2001 and in a letter dated 27. 03. 2003, the respondent requested for condonation of its lapses on account of failure of the pipes supplied to the Field Hydrostatic Test but claimed its liability to reimburse the petitioner was to the maximum extent of 10% of the contract value. " The petitioner was not satisfied with the same and invoked performance bank guarantee furnished by the respondent to the extent of 10% of the contract value. "

( 5 ) THE petitioner also filed a civil suit before the Delhi High Court for damages. " The respondent filed an application under Section 8 of the arbitration and Conciliation Act, 1996 ( for short, "the said Act" ) seeking reference of disputes to arbitration in terms of Article 30. 4. 1 of the General conditions of Contract. " This application was allowed by this Court on 03. 11. 2004 and Justice Anil Dev Singh (Retd.) was appointed as the Sole arbitrator to adjudicate upon the disputes between the parties. "

( 6 ) THE petitioner filed Statement of Claims in which a total sum of rs. 90,68,035/- was claimed. " One of the components of damages is the price difference between the cost of line-pipes of specified quality as compared to the one actually supplied by the respondent, which was alleged to be of lower specification, lower quality, lower strength, lower weight. " This claim was to the tune of Rs. 61,72,728/ -. "

( 7 ) THE Arbitrator made and published an Award dated 19. 04. 2007 holding that the petitioner was entitled to a total su












Click Here to Read the rest of this document