SupremeToday Landscape Ad
Back
Next
Headnote Court Copy Facts Arguments Court observation Judicial Analysis Case Map Category Hierarchy Table of Content
Listen Article Pause Article
judgment-img

2009 Supreme(Del) 917

HIGH COURT OF DELHI AT NEW DELHI
HONBLE MS. JUSTICE ARUNA SURESH, J.
VIJAY KUMAR GOEL – PLAINTIFF
Versus
DELHI DEVELOPMENT AUTHORITY & ANR. – DEFENDANTS
IA No.6254/2007 and IA No.6255/2007
in CS (OS) No.2537/2000
Decided on : August 21, 2009

Important Points

The main legal point established in the judgment is that the court may allow the filing of additional documents if they are deemed relevant for the fair adjudication of the case and if no prejudice is likely to be caused to the opposing party.

Subject

Civil Law - Evidence and Procedure

Act Referred

CIVIL PROCEDURE CODE : O.12 R.8, O.7 R.14
RIGHT TO INFORMATION ACT : .

Headnote

Additional Documents - Recovery Suit - Order 7 Rule 14 CPC - Attested copies of noting sheet of tender 1 to 5, justification statement, letter from DDA, completion certificate, and letters related to work estimates and payments - The court allowed the plaintiff to file additional documents except for two, as they were deemed relevant for the fair adjudication of the case.

Fact of the Case:

The plaintiff filed an application seeking permission to file additional documents in a suit for recovery of Rs.98,65,000 against the defendants. The plaintiff claimed that the additional documents were relevant for fair adjudication of the suit and were obtained through the Right to Information Act.

Finding of the Court:

The court found that some of the documents sought to be placed on record were relevant for the proper and final adjudication of the case on merits. The court allowed the application, except for two documents, and imposed a cost of Rs.10,000 on the plaintiff to be deposited with the Delhi High Court Mediation and Conciliation Centre.

Issues: The issues revolved around the relevance and timing of the additional documents sought to be filed by the plaintiff, the defendants' opposition to the application, and the plaintiff's compliance with procedural requirements.

Ratio Decidendi: The court allowed the filing of additional documents that were deemed relevant for the fair adjudication of the case, considering that the plaintiff had not yet concluded his evidence and no prejudice was likely to be caused to the defendants.

Final Decision: The application was partly allowed, permitting the plaintiff to place on record the additional documents except for two, and imposing a cost of Rs.10,000 on the plaintiff. Additionally, the plaintiff was permitted to file an additional affidavit of the witness within four weeks.

Advocates appeared:
Mr. Rajinder Aggarwal, Advocate
Mr. Gaurav Sarin, Advocate

ORDER

ARUNA SURESH, J.

IA No.6254/2007 (Order 7 Rule 14 CPC) in CS (OS) No.2537/2000

1. Plaintiff has filed this application under Order 7 Rule 14 CPC seeking permission to file additional documents as detailed in para 4 of the application.

Plaintiff has filed the present suit for recovery of Rs.98,65,000/- against the defendants which is pending adjudication and is at the stage of recording of plaintiff’s evidence.

2. It is contended by the plaintiff that he filed the documents which were in his power and possession and relevant for deciding the matter in issue. However, some of the documents which were in power and possession of the defendants were not filed by the defendants despite receipt of notice under Order 12 Rule 8 CPC dated 6.5.2006 served upon the defendants. Plaintiff filed an application under the Right to Information Act and was successful in obtaining various documents and letters exchanged between the parties. According to the plaintiff these documents are relevant for the purpose of fair and just disposal of the suit and they could not be filed earlier because they were not in his power and possession.

3. Defendants have opposed this application on the grounds that these documents are not relevant and they have been filed belatedly despite the fact that plaintiff was given sufficient opportunity to file his documents. Even cost was imposed upon the plaintiff when he failed to file the documents within the time frame fixed by the Court. According to the defendants, the application is without merits and should be dismissed.

4. Plaintiff’s claim is based on execution of work carried out by him for the development of land in Sector 23, 24 and 25 of Rohini, Phase-III, S.H.: construction of outfall drain from Sector 20 to 24 at Rohini Line No.E to 71 by the defendants vide agreement No.5/RPD-11/96-97. Plaintiff has sought permission to file the following documents on the record:

“1. Attested copies of noting sheet of tender 1 to 5 in the Office of Executive Engineer (P) 1 SE (P) R DDA.

2. Attested copy of justification statement along with analysis sheets 6 to 25.

3. Original copy of letter No. 92/PIO/RZ/RTI Act-05/525 dated 01.03.2007 sent by DDA to plaintiff.

4. Attested copy of letter No. CE(R) 4(2)98/AE(QC)DDA/1823 dated

04.08.1997 sent to various officers of DDA.

5. Attested copy of A.E. III/RPD-11 letter no. F6(22) 96-97/AE III/RPDXI/13 dated 01.05.1997 sent to Ex. Engineer RPD-11 along with annexure page No.2 to 13.

6. Attested copy of A.E. III/RPD-11 letter no. F6(22) 96-97/AE III/RPDXI/11 dated 27.03.1997 sent to the Ex. Engineer RPD-11 along with annexure Page No. 15 to 17.

7. Attested copy of completion certificate.

8. Attested copy of Ex. Engineer RPD-11 letter No.F50(439)A/RPD-8/DDA/440 dated 30.04.1998 sent to Superintending Engineer, Civil Circle – 14, DDA along with page Nos. 20 to 25.”

5. Documents at serial No.1 are not relevant as it is not disputed that plaintiff was awarded work and also that final payment was released to the plaintiff. These noting sheets relate to the period before the tender of the plaintiff was finalised and contract was executed between him and the defendants for development of land in Sector 23, 24 and 25 at Rohini, Phase-III. These noting sheets have no bearing on the claim of the plaintiff.

6. Document No. 2 is a justification statement which is relevant for adjudication of the claim of the plaintiff.

7. Document No.3 is the reply of the DDA to the application of the plaintiff filed under the Right to Information of Act, 2005. This document is formal in nature and enclosed with this are the other documents which the plaintiff has sought to be placed on record.

8. Document No.4 is not relevant as it contains guidelines to be observed by various officers of the department for testing of the joint of RCC pipes. It has no bearing on the facts and circumstances of this case.

9. Document No.5 is a letter in respect of revised estimate of the work e













1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top