HIGH COURT OF DELHI
Manju Goel, J.
G.D. Tiwari & Co. - Plaintiff
Versus
Delhi Development Authority & Anr. - Defendants
CS(OS) NO. 767-A/1996
Decided on : 19.05.2006
1. The petitioner Mis G.D. Tiwari and Company filed the petition under Section 14 of the Arbitration Act, 1940 with a prayer to call upon the Arbitrator Respondent No.2 Shri K.D. Bali to file his award in the dispute between the parties, viz., the petitioner and the respondent No.1-the DDA The petitioner obtained a contract for work of construction of 590 DUs under SFS at Vasant Kunj, Sector-C, Grade III SH: Construction of stone boundary wall and park wall vide agreement No. 3/HD-II/87-88. Some controversies between the parties arose and the respondent No.2 Shri K.D. Bali was appointed Arbitrator in the matter who published his award. On the petition being filed the CS(OS) No. 767-A/1996 was registered. Notice of filing of the award was issued to the parties and objections to the award was filed by the DDA under Section 30 and 33 of the Arbitration Act, 1940. Objections have been replied to and both parties have filed affidavits in support of their respective contentions. A rejoinder has also been filed.
2. Objections under Sections 30 & 33 of the Arbitration Act as delineated at the time of arguments are as under:
1. Reasons for the award have not been given by the Arbitrator.
2. Claim No.5 is nothing but duplication of Claim No.1 under which damages have been awarded to the tune of Rs. 1,33,000/-, and, therefore, the damages awarded under Claim No.5 could not have been awarded.
3. The Arbitrator has awarded interest @ 18% per annum from 16.5.1990 without indicating whether the interest was for pre-suit period or for the pendente lite period. The claimant had, also not indicated whether it claimed interest for the pre-suit period or for the pendente lite period.
4. That the Arbitrator did not consider the documents submitted by the defendant.
3. There is no dispute that Clause 25 of the agreement required that the Arbitrator would give reasons for the award. For examining whether the Arbitrator had given a reasoned award, it is necessary that the award is looked into. The Arbitrator's award says that parties were allowed to argue the matter fully before the Arbitrator. Claim No.1 deals with the claim for Rs. 2,35,305/- being the payment of final bill. The Arbitrator has awarded a sum of Rs. 1,64,506. The Award shows that the Arbitrator has examined various factors. The Arbitrator has gone through each and every aspect of the claim and has, arrived at a conclusion by due application of mind. The following portion of the award in respect of Claim No.1 will indicate that the Arbitrator has given reasons for his conclusions.
"From the perusal of C-22 being the copy of the hindrance register maintained by the respondent it is revealed that there was total delay in performance of the contract because of the respondent. The claimants have referred various documents C-10 to C-21 also in support of the said contention and on consideration of the evidence adduced by the parties I am of the view that there was delay in discharge of obligations at the hands of the respondents with the result the work could be actually completed on 27.12.1988 after about 15 months of the stipulated completion. I hold that the respondents committed breach of contract and are liable to damages.
As regards quantum, from the cost index as issued by Government from time to time the increase during this period of delay comes to 20%. The claimants in support of this has filed C-27 indicating the cost index of the relevant period. I assess and award 15% on the work executed after stipulated date of completion which comes to Rs. 66,460/-
In consideration of the above facts I award a sum of Rs. 1,64,506/(Rupees one lakh sixty four thousand five hundred six only) in favour of the claimants under this claim."
4. Clearly the Arbitrator had taken into account the facts of the case, register maintained by the DDA and the cost index issued by the Government from time to time. The Arbitrator could have awarded the damages @ 20%. Yet the Arbitrator actually awarded
SupremeToday
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.