RAJIV SHAKDHER, SANJAY KISHAN KAUL
INDIAN FARMERS FERTILISER COOPERATIVE LTD. – Appellant
Versus
DUGGAL CONSTRUCTIONS (INDIA) LTD. – Respondent
SANJAY KISHAN KAUL, J.
1. M/s. Indian Farmers Fertilizers Cooperative Limited (for short „M/s. IFFCO?) floated a tender for construction of “B” Type residential quarters for its township at its Fertilizer Plant in Aonla (District Bareilly, Uttar Pradesh). M/s. Duggal Construction (India) Ltd. (for short “M/s. Duggal”) submitted its bid for the same and vide letter dated 8.4.1985, contract No.117 was allotted to M/s. Duggal for construction of 257 quarters for contract value of `4,26,80,000.00. In response to the very same tender another contract No.117-A for construction of 128 quarters was awarded to M/s. Duggal vide letter dated 25.5.1985 of about the same value.
2. The contract was to be completed within a period of 18 months as per clause 2 of Letter of Intent (for short LoI) dated 8.4.1985. Any delay was to attract liquidated damages. The relevant clause 2 reads as under:
“The entire job has to be completed within a period of 18 (eighteen) months from the date of acceptance of this Letter of Intent. Any delay in completion of job will attract liquidated damages at the rate of ½ per cent (half per cent) of the contract price (as defined under clause 1 of the letter
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.