S.RAVINDRA BHAT, NAJMI WAZIRI
N. S. Atwal – Appellant
Versus
Jindal Steel & Power Ltd. – Respondent
S. Ravindra Bhat, J. (Open Court)
C.M. NO. 15154/2013 (for condonation of delay)
For the reasons mentioned in the application, C.M. No. 15154/2013 is allowed.
RFA (OS) 125/2013, C.M. NO. 15155/2013 & 15156/2013
1. This is an appeal from an order of the learned Single Judge declining the unsuccessful defendant’s (in the suit, and the appellant herein) leave to defend a suit brought under Order XXXVII of the Code of Civil Procedure (“CPC”) by Jindal Steel and Power Ltd. (hereinafter “JSPL”) for recovery of a principal sum of Rs. 2,98,39,060/-along with interest at the agreed rate of 10% per annum accrued thereon with effect from April, 2007 to March, 2008 and thereafter at 12% per annum from April, 2008 till the institution of the suit in February, 2010, thus amounting to a total amount of Rs. 4,00,44,341.20/-.
2. As the Single Judge records, the pleading on behalf of the plaintiff is as follows:
“1. XXXXXX XXXXXX XXXXXX
(i) that the defendant is the sole proprietor of M/s Guru Mehar Construction;
(ii) that in December, 2000, the defendant approached the plaintiff with offer to conduct the excavation activities required by the Plaintiff at its mining site near Dongamoh
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.