SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2015 Supreme(Del) 350

HIGH COURT OF DELHI
S. MURALIDHAR, J.
Ministry of Road Transport & Highways Government of India – Appellant
Versus
DSC Ventures Pvt. Ltd. – Respondent
ARB.A. No. 15 of 2015 & I.A. No. 4386 of 2015
Decided On : 03-03-2015

Advocate Appeared:
For the Appellant:Ravi Sikri, Senior Advocate with Tanu Priya, Meenakshi Sood, Mukesh Kumar, Advocates
For the Respondent:Kapil Sibal, Senior Advocate with Akhil Sibal, Deepak Khurana, Jatin Mongia, Advocates

Headnote:

Arbitration and Conciliation Act, 1996 - Section 37 (2) (b) - Contract - Termination - Violation of statutory provision - Contract was sought to be terminated by MoRTH by its notice - Notice was stayed by the AT by its order - Stay was operative only till the last date of the CA - Respondent filed another application under Section 17 of the Act conscious that the CA by efflux of time was to end - Directing in the impugned order that a revised fee notification should be issued by the MoRTH for a further period of six months - Directing the MoRTH not to take coercive steps "to prevent the operation of the project facility" the AT was in fact extending the concession period - CA was by its nature determinable and under Section 14 (1) (c) SRA, there could be no order, much less as an interim measure, preventing the CA from coming to an end and further extending it for six months thereafter - Impugned order of the AT overlooks the applicable law and legal principles - Order of the AT is set aside - Appeal is allowed.

JUDGMENT:-

1. This appeal under Section 37 (2) (b) of the Arbitration and Conciliation Act, 1996 (‘Act’) is directed against the impugned order dated 25th February 2015 passed by the Arbitral Tribunal (‘AT’) restraining the Appellant Ministry of Road Transport and Highways (‘MoRTH’) from “taking any coercive steps to prevent in any manner the operation of the project facility by the claimant after 1st March 2015” and further directing the MoRTH to issue “a revised fee notification in terms of the concession agreement before 2nd March 2015” and further directing that such revised fee notification “may be issued for a period of six months within which period the Tribunal reasonably expects that the matter will be finally adjudicated.”

2. In terms of the Concession Agreement ('CA') dated 8th May 2003 executed between the MoRTH and the Respondent DSC Ventures Pvt. Ltd., the Respondent was awarded the contract for implementation of a project involving construction, operation and maintenance of four laning of two lane road from Km. 282 to Km. 308/6 of NH 6 (Raipur-Durg section in the State of Chhattisgarh) on a build, operate and transfer (‘BOT’) basis.

3. In its bid, the Respondent quoted a concession period of 11 years and 9 months including the construction period of up to 3 years. Under Clause 2.2 of the CA, the concession period was defined to be that quoted by the Concessionaire commencing from the Commencement Date during which the Concessionaire is authorised to implement the project to operate the Project Facility in accordance with the provisions thereof.” In the CA, 'Commencement Date' has been defined to mean “the date on which the physical possession of the project site is delivered by the Government of India (GOI) to the Concessionaire, which shall not be later than 30 days from the date of this agreement.” The other relevant definition is ‘the commercial operation date' (‘COD’) which shall be the date on which the Independent Engineer (‘IE’) issues the completion certificate (‘CC’) or the provisional certificate (‘PC’) upon completion of the construction of the project and which shall subject to the provisions of the CA be not later than 180 days after the scheduled project completion date.

4. Under Clause 9.2(a) the project was to be deemed to be completed and open to traffic only when the CC or the PC was issued by the IE in accordance with the article 9.3. Under 9.2 (b), the Respondent guaranteed that the project completion shall be due in accordance with the CA on a date “not later than 36 months from the commencement date.” Under 9.2 (d) if the COD does not occur within 180 days from the scheduled project completion date, GOI shall subject to the provisions of the CA be entitled to terminate the agreement in accordance with the Article 16.2. The events of defaults were specified in Article 16.2. Under Clause 17.2 the concession period could be extended if upon being notified by the Respondent of the change in law and the proposed amendments to the CA, the Steering Group assists the change in the financial position as a result thereof and determine the extension to be given.

5. Schedule B to the CA defines the project site to mean the land width between Km. 282 to Km.308/6 of NH6 is 36.60M and extra land of 4.35M acquired where widening was proposed either to the left side or right of existing carriage-way. Land for the project shall be provided free from all encumbrances and free of costs.

6. According to the NHAI, it handed over the project site to the Respondent on 3rd June 2003 along with all concerned documents. It has enclosed as Annexure A-4 to the appeal, the certificate of hand over and takeover of the project site. However, there is a dispute between the parties as to whether the entire project site was handed over, free from all encumbrances, on the aforementioned date. It is the case of the Respondent that entire project site free from all encumbrances was not handed over to it till much later. In para 8.4













































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top