2015 Supreme(Del) 4068
Delhi High Court
Badar Durrez Ahmed, Sanjeev Sachdeva, JJ.
Sun Broadcast Equipment Pvt. Ltd. - Appellant
Versus
Prasar Bharati & Anr. - Resopndent
W.P.(C) 7896/2014
Decided On : 01-09-2015
Important Points
Subject
Administrative Law - Tender Cancellation
Headnote
TENDER - Cancellation of Tender - 8(5) 2013-14 E1(P) TV - The court discussed the cancellation of the subject tender for administrative reasons and the compliance of the petitioner's bid with the tender items. The key legal provision discussed was the right of the tender inviting authority to cancel the tender for valid reasons and the requirement for bids to be fully compliant with the tender items. The court found that the petitioner's bid was not compliant and upheld the cancellation of the tender.
Fact of the Case:
The petitioner challenged the cancellation of a tender for supply of digital camera chain, alleging wrongful cancellation to deprive the petitioner of the contract. The respondent contended that the cancellation was for administrative reasons and due to non-compliance of the petitioner's bid with the tender items.
Finding of the Court:
The court found that the petitioner's bid was not fully compliant with the tender items and upheld the cancellation of the tender by the respondent. The court also noted the lack of diligence in filling the tender document by the petitioner.
Issues: The issues involved the wrongful cancellation of the tender, compliance of the petitioner's bid with the tender items, and the authority of the tender inviting authority to cancel the tender for valid reasons.
Ratio Decidendi: The court held that the tender inviting authority has the right to cancel the tender for valid reasons and that bids must be fully compliant with the tender items. The lack of diligence in filling the tender document by the petitioner was also considered.
Final Decision: The petition and pending applications were dismissed, upholding the cancellation of the tender. No costs were awarded.
For the Respondents No. 1:Mr. Rajeev Sharma, Adv. with Ms. Priyanka Raj, Ms Radhalakshmi R. Advocates.
For the Respondent No. 2:Mr. Ajit Warrier, Adv. with Ms Tarunima Vijra, Advocates.
For the Respondent No. 3:Mr. Sheetesh, Advocate.
Sanjeev Sachdeva, J.
1. This petition has been filed by the petitioner impugning order dated 08.08.2014 passed by the respondent No. 1 informing the bidders including the petitioner that the subject tender has been cancelled for administrative reasons.
2. The respondent No. 1 had issued Notice Inviting Tender for supply of 3 Chip CCD Multi Format EPF Digital Chain for Studio/OB/EFF Applications vide tender No. 8(5) 2013-14 E1(P) TV dated 26.08.2013. The Petitioner including certain other bidders submitted their bids. The subject tender has been cancelled by the Respondents No. 1 by communication dated 08.08.2014 on administrative grounds.
3. The contention of the counsel for the petitioner is that the subject tender has been wrongfully cancelled and the impugned decision is part of a series/sequence of tenders cancelled by the respondent No. 1 and the said cancellation happens when the petitioner is found to be L-1. It is submitted that the said subject tender has been cancelled to deprive the petitioner of the contract. It is contended that on at least two previous occasions, the respondent No. 1 floated Tenders for sale/similar products and the said tenders were cancelled once the petitioner was found to be L-1.
4. On the contrary, the learned counsel for the respondent No. 1 has contended that the subject tender was cancelled for administrative reasons and there were no mala fides in cancellation of the subject tender. It is further contended that all the bidders including the petitioner had not been found to be technically qualified and in the case of the petitioner, the petitioner quoted for an incorrect tender item, which was not compliant with the tender items. Reference was also made to the letter annexed with petition as Annexure ‘L’ issued by DDG (Engg.) on behalf of the Director General (Doordarshan) to the CEO of the respondent No. 1. The letter reads as under:-
“Sir,
With reference to above referred letter regarding cancellation of 3 Chip CCD Multi-Format EFP Digital Camera Chain for Studio/OB/EFP.
Point wise reply is given below:-
1. Subject tender was published in July 2013 and commercial bid was opened on 06.11.2013. Sony Camera offered by M/s Sun Broadcast Equipment Pvt. Ltd. (Authorized Distributor of M/s Sony) and was the lowest bidder.
2. A letter had received from M/s Hitachi that M/s Sony had offered ‘HDVF-C550W’ LCD color view finder. M/s Hitachi wished to know that 5 inch LCD color view finder is acceptable to Doordarshan against their requirement of 9 inch LCD view finder.
TEC had corrected 5 inch CRT view finder as ‘HDVF-550’ in place of ‘HDVF-C550W’ considering typographical error from side of firm M/s Sun Broadcast.
It was observed that in the commercial bid of M/s Sun Broadcast, Model No. of view finder was ‘HDVF-C550W’ while in approved TEC; Model No. was ‘HDVF-550. TEC has stated that Model No. opted by TEC is based on Technical literature & compliance given by the firm.
3. File was sent to LE on 14.03.2014 for above clarification in model No. of view finder. As per LE, it is stated that it is a post tender negotiation & cannot be accepted by TEC. It is prohibited under CVC guidelines, Model No. HDVF-550 has been offered by the bidder after opening of technical bid and as such is another and subsequent offer and not acceptable.
4. File was sent for seeking opinion of legal counsel Sh. Rajeev Sharma on 03.04.2014. File was received from standing counsel on 27.05.2014.
5. File was again sent to vigilance section as desired by vigilance section for scrutiny. Sh. Rajeev Sharma submitted the case to solicitor General for advice. File was received on 26.06.2014.
6. As per vigilance section, it is stated that “the doubt regarding a possible typographical error notwithstanding (as opined by the SG), the vigilance wing’s view is that DD should have perhaps gone for cancellation and retendering considering the controversy of post tender modification, non diligent manner of filing of bid by the firm and this be