2016 Supreme(Del) 1546

IN THE HIGH COURT OF DELHI AT NEW DELHI
GITA MITTAL, I.S.MEHTA, JJ.

RAVINDER KUMAR & ORS - Appellants
Versus
DELHI DEVELOPMENT AUTHORITY - Respondent
FAO(OS) 496/2015 and CM No.17860/2015
Decided on : 29-3-2016

Important Points

The court emphasized the importance of maintaining status quo to preserve the property for the real owner, while also considering the need to prevent encroachment by allowing the DDA to raise a boundary wall.

Subject

Civil Law - Property Disputes

Act Referred

CIVIL PROCEDURE CODE : O.39 R.4

Headnote

Demolition - Land Dispute - [IA No.2456/2014, Order XXXIX Rule 4 CPC] - The court discussed the challenge to an order regarding a demolition carried out by the Delhi Development Authority (DDA) on land claimed by the appellants. The court allowed the DDA to raise a boundary wall on the subject land to prevent encroachment, while maintaining status quo with regard to possession and construction on the land.

Fact of the Case:

The appellants filed a suit for injunction against the DDA, claiming that their construction on the land was illegally demolished by the DDA. The DDA sought to raise a boundary wall on the land to prevent further encroachment.

Finding of the Court:

The court allowed the DDA to raise a boundary wall on the subject land to prevent encroachment, while maintaining status quo with regard to possession and construction on the land.

Issues: Dispute over possession and construction on the land, challenge to the demolition by the DDA, and the DDA's request to raise a boundary wall on the land.

Ratio Decidendi: The court found it imperative to maintain status quo on the land to preserve it for the real owner, while allowing the DDA to raise a boundary wall to prevent encroachment.

Final Decision: The appeal and applications were dismissed, and the court directed the DDA to raise a boundary wall on the land while maintaining status quo with regard to possession and construction.

Advocates:
Advocate Appeared:
Mr. Sudhir Nandrajog, Sr. Adv. with Mr. Parvinder Chauhan and Mr. Abhilash Vashisht, Advs.
Mr. Pawan Mathur, Standing Counsel for DDA.

JUDGMENT

GITA MITTAL, J.


1. By this order, we propose to decide the challenge to an order dated 26th of August 2015 passed on I.A.No.2456/2014 in a suit bearing CS(OS)No.2187/2014 for injunction filed by the appellants against the Delhi Development Authority (‘DDA’ for brevity).

2. In its plaint the appellants are complaining in respect of a demolition carried out by the DDA on 15th July, 2014 with regard to the construction on land ad measuring 2 bighas out of Khasra No.1161/1 (min) situated in revenue estate of Village Mehrauli (Delhi). For brevity, we may note the appellants case in the plaint seeking decrees for permanent injunction and damages, inter alia averring as follows :

“10. That the again on 04.05.2007 the Deputy Director (Horticulture) of the defendant had written a letter dated 04.05.2007 to the Deputy Director (LN) SWJ DDA thereby informing that there are 10 numbers of Kachcha Juggies existing and it was also stated that some encroachment had been removed but not completed.

11. That thereafter a demolition programme for removing the remaining construction/encroachment was fixed on 13.06.2007 the demolition was carried out and the encroachment from the land of the defendant was removed. As per the knowledge of the plaintiff no. 1, before carrying out the aforesaid encroachment removal drive in the year 2007, the defendant had carried out a proper inspection and demarcation to determine/ascertain the extent and limits of its land. It is pertinent to mention here that, in the year 2007, no portion of the suit land was even touched in as much as even the officials of the defendant were certain about the fact that no portion of the suit land fell within the boundaries of the land under the ownership of the defendant.

12. That all of sudden and without any kind of notice or warning, on 15.07.2014, by taking advantage of prevalent situation, Sh. Suresh Kumar, Deputy Director (SWZ) and H.K. Tomar (Tehsildar) alongwith other official along with local police officials reached on the Suit Land of the plaintiff no.1.

13. That the aforesaid team came armed with a JCB Machine and started demolishing the rooms as constructed by the plaintiff no. 1 over the “Suit Land”.

xxx xxx xxx

17. That the plaintiff no.1 has spent around Rs.8 lakhs on the construction of the rooms which was illegally and arbitrarily demolished by the defendant.

As such, the defendant is liable to pay to the plaintiff no. 1 the aforesaid sum of Rs.8,00,000/- as damages.

xxx xxx xxx

19. That the cause of action has arisen in favour of the plaintiffs and against the defendant on 15.07.2014 when the defendant and its official illegally and arbitrarily carried out demolition over the suit land belonging to the plaintiffs. The cause of action further arose when the officials of the defendants threatened to construct the boundary wall thereby enclosing the suit land. The cause of action is still subsisting in as much as the threat of the defendant has not ceased.” (Emphasis supplied)

3. Amongst the prayers, the following prayer is made as prayer ‘B’ :

“B. Restrain, by way of decree of permanent injunction, thereby restraining the defendant, its officials, servants, representatives, agents servants, assigneeies and/or anybody, claiming through or under it, from raising/constructing boundary wall over the Suit land.”


4. Along with the plaint, the appellant had sought interim injunction by way of I.A.No.13495/2014 which was listed before the court on 25th July, 2014 where it was stated on the appellants behalf that the “plaintiffs’ possession has been disturbed and the construction made on the plaintiffs’ land is sought to be demolished”.

5. Mr. Pawan Mathur, learned standing counsel for DDA-respondent points out that this representation was contrary to the plaint which admits demolition and seeks damages. On this submission of the plaintiff, the learned Single Judge had directed that “till the next date of hearing, the defendant shall maintain status quo with rega