2016 Supreme(Del) 3354
IN THE HIGH COURT OF DELHI AT NEW DELHI
JAYANT NATH, J.
M/S. CARDIFF ASSOCIATES PVT. LTD. – Petitioner
Versus
M/S. INDRAPRASTHA ICE AND COLD STORAGE PVT. LTD. – Respondent
CM (M) No. 875 of 2016
Decided On : 07-09-2016
Important Points
Subject
Civil Law - Property Law
Act Referred
CONSTITUTION OF INDIA : Art.227, Art.226
SPECIFIC RELIEF ACT : S.6
Headnote
Specific Relief Act - Challenge to interim order directing maintenance of status quo - Section 6 of the Specific Relief Act - [Section 6 of the Specific Relief Act] - The court discussed the rights of a landlord under Section 6 and concluded that dispossession of the sub-tenants was dispossession of the tenant, allowing the tenant to file the suit. The court also addressed the issue of limitation and the petitioner's request to raise construction on the property, citing relevant case law and denying the relief.
Fact of the Case:
The respondent filed a suit for possession under Section 6 of the Specific Relief Act after being dispossessed of the property by the petitioner. The trial court passed an interim order directing the petitioner to maintain status quo regarding the nature and construction of the property.
Finding of the Court:
The court found that the respondent was entitled to file the suit as the dispossession of the sub-tenants was considered dispossession of the tenant. The court also rejected the petitioner's contention regarding limitation and denied the relief sought to raise construction on the property.
Issues: The issues included the entitlement of the respondent to file the suit, the applicability of limitation, and the petitioner's request to raise construction on the property.
Ratio Decidendi: The court held that the dispossession of the sub-tenants constituted dispossession of the tenant, allowing the suit to be filed. The court also concluded that the petitioner's request for construction on the property was not justified based on relevant case law.
Final Decision: The petition was dismissed as the court found no patent error in the impugned order.
For the Petitioners: Mr. Sudhir Nandrajog with Mr. Jasmeet Singh, Ms. Astha Sharma & Mr. Surya Rajappan.
For the Respondents: Mr. Sandeep Sethi with Mr. Jayant Mehta & Ms. Gurmeet Bindra.
JAYANT NATH J.
C.M. No. 31799/2016 (for exemption)
Allowed, subject to all just exceptions.
CM (M) No. 875/2016 & C.M. No. 31800/2016 (for stay)
1. By the present petition, the petitioner seeks to challenge the order dated 9.8.2016 by the trial court whereby the trial court in a suit filed by the respondent under Section 6 of the Specific Relief Act passed an interim order directing the petitioner to maintain status quo as regards nature and construction of the suit property.
2. The background facts are that Late Sh. Jai Dev Sharma was the owner of property being ‘Ahata’ bearing Municipal No. 10130 at Katra Chhajju Pandit, Sidi Pura, opposite Model Basti, East Park Road, New Delhi-110005 measuring 1517.25 square yards. The property was leased on 8.9.1953 to the respondent. The respondent inducted two sub-tenants, namely, Om Prakash Gupta and Subhash Aggarwal on 1.11.1989. In the meantime, the original owner Jai Dev Sharma expired. His successor/son Surendra Deo Gaur vide registered sale deed dated 29.5.2013, sold the property to the petitioner/ defendant. The said petitioner also took vacant physical possession from the sub-tenants, namely, Om Prakash Gupta and Subhash Aggarwal and commenced construction after demolition of the existing structure.
3. The respondent in 2016 filed the present suit for possession under Section 6 of the Specific Relief Act. Along with the suit, an application under Order 39 Rule 1 & 2 CPC was filed seeking directions to the petitioner/defendant to maintain status quo regarding the nature and construction of the suit property. The trial court relying upon the judgment of the Supreme Court in Sadashiv Shyama Sawant (Dead) & Ors. vs. Anita Anant Sawant, (2010) 3 SCC 385 noted that Section 6 of the Specific Relief Act was applicable to a landlord against a trespasser as in matter of law, the dispossession of a tenant by a third party is dispossession of the landlord. The contention of the petitioner that the suit has been filed beyond the period of six months was not accepted holding that prima facie it appears that the respondent became aware of dispossession in February, 2016 when a representative of the respondent visited the suit property. Noting that the petitioner has started raising construction on the suit property after filing of the suit, the trial court passed the interim order as noted above.
4. I have heard the learned senior counsel for the parties. The learned counsel for the petitioner has vehemently argued that the suit filed by the respondent is, on the face of it, barred by limitation. He submits that the sale took place on 29.5.2013. It is the respondent‘s own case that since December, 2012, the sub-tenants stopped paying rent and admittedly the respondent took no steps. Subsequently on 9.6.2015, the petitioner applied for sanction of the building plan. On 10.8.2015, he was also permitted to fell trees on the land. It is only now much thereafter in May, 2016 that the present suit has been filed. It is submitted that the conclusions of the trial court that the suit has been filed within six months is erroneous on the face of it. Further, reliance is also placed on various terms of the lease deed to contend that the sub-tenants had a right to demolish the existing structure and construct a new building and had a right to sub-let the property. Given the nature of the lease, no prejudice is caused to the respondent. It is further submitted that irreparable loss and injury is likely to be caused to the petitioner if the order is not at least modified. He submits that if for some reason the order is not vacated, the same may be modified and the petitioner may be permitted to carry on the construction subject to the limitation that the petitioner shall not alienate or part with any part of the property and will abide by the final decision of the case.
5. The learned senior counsel appearing for the respondent has however contended that the action of the petitioners lack equity. The sale