2016 Supreme(Del) 4484

IN THE HIGH COURT OF DELHI AT NEW DELHI
R.K.GAUBA, J.
KRISHAN RADHU – Plaintiff
Versus
THE EMMAR MGF CONSTRUCTION PVT. LTD. – Defendant
CS(OS) 3281 OF 2014 and IA No.7709 OF 2015 (under Section 8 of the Arbitration and Conciliation Act) and OA No.210 OF 2015
Decided On : 21-12-2016

Important Points

The main legal principle established is the peremptory nature of Section 8 of the Arbitration and Conciliation Act, 1996, and the obligation of the civil court to refer parties to arbitration when an arbitration agreement exists.

Subject

Arbitration Law - Enforcement of Arbitration Agreement

Act Referred

ARBITRATION AND CONCILIATION ACT : S.8, S.5, S.8(1), S.8(3)
CIVIL PROCEDURE CODE : O.8 R.1, O.8 R.10
CONSUMER PROTECTION ACT : S.3

Headnote

Arbitration - Delayed Possession - Arbitration and Conciliation Act, 1996 - Section 8

Fact of the Case:

The plaintiff sought damages for delayed possession of apartments from the defendant company. The defendant invoked Section 8 of the Arbitration and Conciliation Act, 1996, claiming that the dispute should be referred to arbitration based on arbitration clauses in the apartment buyers' agreements.

Finding of the Court:

The court found that the defendant's invocation of Section 8 was valid and ordered the parties to arbitration, as the dispute fell within the scope of the arbitration agreements. The court set aside the previous order closing the defendant's right to file a written statement and referred the parties to arbitration.

Issues: The main issue was whether the dispute should be referred to arbitration under Section 8 of the Arbitration and Conciliation Act, 1996, based on the arbitration clauses in the apartment buyers' agreements.

Ratio Decidendi: The court held that the defendant's invocation of Section 8 was valid, as the dispute fell within the scope of the arbitration agreements. The court emphasized the peremptory nature of Section 8 and the obligation of the civil court to refer parties to arbitration when an arbitration agreement exists.

Final Decision: The court allowed the defendant's appeal and application under Section 8 of the Arbitration and Conciliation Act, 1996, set aside the previous order, and referred the parties to arbitration in accordance with the arbitration agreements.

Advocates Appeared:
For the Plaintiff : Mr. Alok Kumar, Mr. Neeraj Kumar Gupta, Mr. Abhishek Paruthi and Mr. Amit Kumar Singh
For the Defendant : Ms. Manmeet Arora and Ms. Chand Chopra

JUDGMENT :

1. This suit was instituted by the plaintiff against the defendant company seeking a decree in the sum of Rs.1,07,65,250/- (Rupees One Crore Seven Lakhs Sixty Five Thousand two hundred and fifty only) as damages along with pendent lite and future interest at the rate of 10% from the date of filing of the suit till realization along with costs, pleading cause of action to have arisen mainly on the averment that the defendant had caused losses to the plaintiff by having failed to deliver timely possession of the two apartments (T-2-02-02 and T-2-03-02) at Common Wealth Games Village constructed/developed by the said company on lands admeasuring 11 hectares at junction of roads adjacent to National Highway 24 and Akshardham Temple in terms of apartment buyers agreements executed by the parties on 16.03.2009.

2. According to the plaintiff’s case, the possession of the said two apartments were to be handed over, as per the said two identically worded agreements, before the end of June 2011 and since there was a default in this regard till September 2012, the plaintiff had earlier instituted consumer complaint before the National Consumer Disputes Redressal Commission (NCDRC) under the provisions of Consumer Protection Act, 1986, after the filing of which the possession was delivered thereby satisfying the claim for relief of possession on 27.09.2012. The plaintiff pleads that upon it being pointed out that he was not “consumer” within the meaning of the expression used in the Consumer Protection Act, 1986 and resultantly NCDRC had no jurisdiction to adjudicate upon the consumer complaint preferred before it, the said matter having been withdrawn, the present suit was instituted seeking damages for the loss suffered consequent to the delay, the defendants having failed to give the necessary relief in spite of the demand by legal notice dated 24.10.2011.

3. Upon the summons of the suit and notice on the application filed therewith being served on 28.11.2014, in terms of the order dated 03.11.2014 of the Joint Registrar (Judicial), the defendant, instead of filing written statement, moved the application (IA 7709/2015) under Section 8 of the Arbitration and Conciliation Act, 1996, inter alia, stating that the two apartment buyers’ agreements on the basis of which the case had been brought contained arbitration clauses, in which view the suit deserved to be dismissed and the parties referred to arbitration. This application came up before the Joint Registrar (Judicial) on 21.04.2015 when it was submitted by the counsel for the defendant that the written statement had not been filed for the reason it would prejudice the application under Section 8 of the Arbitration and Conciliation Act, 1996. This plea was rejected by the Joint Registrar (Judicial) by order dated 21.04.2015 whereby the right of the defendant to file the written statement was closed for the reason the period of 90 days permitted for the purpose under the Code of Civil Procedure, 1908 (CPC) had lapsed. This decision of the Joint Registrar is under challenge by the defendant by chamber appeal (OA 210/2015).

4. Both the application under Section 8 of the Arbitration and Conciliation Act, 1996 (IA 7709/2015) and original appeal (OA 210/2015) have been resisted by the plaintiff. It may be noted that, in spite of opportunity, no reply has been filed by the plaintiff.

5. The two apartment buyers’ agreements dated 16.03.2009 on the basis of which cause of action is pleaded in this suit have been filed, in original, by the plaintiff along with the plaint, in terms of the list of documents dated 06.10.2014. Both the agreements are in standard formats, describe the defendant as “the Developer” and the plaintiff as “the allottee” and concededly contain identically worded arbitration clauses in para 43.0 which read as under :-

“43.0 Arbitration

All or any dispute arising out of or touching upon or in relation to the terms of this Agreement or its termination, including the inter