2017 Supreme(Del) 3028

IN THE HIGH COURT OF DELHI AT NEW DELHI
JAYANT NATH, J.
Aez Infratech Pvt. Ltd. - Petitioner
Versus
Vibha Goel & Anr. - Respondents
O.M.P. (COMM) 322 Of 2016
Decided On : 23-08-2017

Important Points

Important Point – Arbitral award which is a plausible award, cannot be interfered with.

Subject

Specific Performance - Agreement to Sell

Act Referred

ARBITRATION AND CONCILIATION ACT : S.34, S.9, S.11, S.21
LIMITATION ACT : Art.54
SPECIFIC RELIEF ACT : S.16(c)

Headnote

Arbitration and Conciliation Act, 1996 – Section 34 – Specific Relief Act, 1963 – Section 16(c) – Interpretation of an agreement is within domain of Arbitrator – Arbitrator has given a bonanza to respondent by granting specific performance of Agreement to Sell and also granted 18% interest on loan amount – There is no period prescribed for performance in agreement – As such, period for limitation would start running when plaintiff had notice that performance is refused – Merely because respondent in claim petition has averred that it was expected that petitioner would complete construction by May 2010 does not ipso facto mean that any period was specified in agreement for performance of agreement – Award is within limitation period – Award is a plausible award based on facts placed on record – Petition dismissed. (Paras 12, 13, 15, 16, 19, 25 and 26)

Advocate Appeared:
For the Petitioner:Mr. Alok Kumar, Mr. Neeraj Kumar Gupta, Mr. Harish Kr. Garg, Mr. Amit Kr. Singh and Mr. Abhishek Paruthi, Advocates
For the Respondent:Mr. Samar Singh Kachwaha and Mr. Raghavendra Mohan Bajaj, Advocates

JUDGMENT :

JAYANT NATH, J.

1. The present petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act’) seeking to impugn the award dated 19.03.2016 passed by the learned arbitrator.

2. Some of the relevant facts as stated by the respondents are that the respondents are the wife and son of Col.Devesh Goel.(Retd.) who was employed with M/s Aerens Builders Pvt. Ltd.(hereinafter referred to as ‘the Aerens Builders’), a sister concern of the petitioner company. It is stated that the respondents were induced into loaning a sum of Rs.70,00,000/- to the Aerens Builders by Mr. Kailash Gupta, the Promoter-Director of the said Aerens Builders at agreed rate of interest. Monthly interest was paid by the said Aerens Builders on regular basis for about two years. In 2008-2009, there was a default on the part of the Aerens Builders in payment of interest. In fact, Col.Devesh Goel (Retd.) did not also receive his salary. It is at that stage, that the said promoter Sh.Kailash Gupta moved his operations into the premises of the petitioner company which was promoted by his brother. On negotiations between the parties, an agreement dated 09.09.2009 was entered into between the parties whereby the petitioner company agreed to sell to the respondents a flat being No.D5/702 (having super area measuring about 2244 sq.fts.) at AEZ Aloha Project of the petitioner company in Village Tigra, District Gurgaon. The total sale consideration agreed was Rs.78,00,000/-. The loan amount paid by the respondents to Aerens Builders was adjusted towards the sale consideration payable for the flat. Unpaid interest on the said loan upto 30.06.2009 amounting to Rs.7,84,875/- was also adjusted to the sale consideration. A balance consideration of Rs.15, 125/- remained payable by the respondents. It was also agreed between the parties that the petitioner company shall pay interest @ 18% per annum monthly @ Rs.1,41,148/- per month till the date of possession of the said flat. It is stated that in terms of the agreement, the agreed interest was paid upto the month of July, 2011 and thereafter the petitioner has defaulted. The possession of the flat has not been handed over to the petitioner.

3. It is the case of the respondents that in November, 2012 they reliably learnt that the petitioner company is trying to sell the flat in question. A petition under Section 9 of the Act being OMP No.1112/2012 was filed. This court on 03.12.2012 passed an interim order restraining the respondents from transferring, alienating, creating any third party interest or parting with possession of the said flat. On 18.07.2013, this court passed an order directing the petitioner company to deposit the keys of the flat in issue with the Registry of this court.

4. It is in this background, that the arbitration clause was invoked. The learned arbitrator was appointed on a petition filed under Section 11 of the Act being ARB. P. No.120/2014 by this court on 23.09.2014.

5. The petitioner company has raised various defences in the pleadings before the learned arbitrator. It has been pleaded that the agreement to sell dated 09.09.2009 has been cancelled/novated by a fresh agreement dated 22.11.2011 whereby the respondent agreed to cancel the agreement to sell and a new agreement dated 22.11.2011 was entered into whereby the respondent agreed to buy two shops and received Rs.1,41,148/-. It was further stated that the agreement to sell is only a security agreement and conferred no rights on the respondent. It was also pleaded that the claim of the respondent is barred by limitation.

6. The learned arbitrator framed the following issues on 10.04.2015:

(1) Whether the Agreement to sell dated 09.09.2009 entered into between the Claimants and the Respondent Company in respect of flat No. D-5/702, alongwith four covered car parkings in the Aloha Projec