2017 Supreme(Del) 1437
IN THE HIGH COURT OF DELHI AT NEW DELHI
S. RAVINDRA BHAT, YOGESH KHANNA, JJ.
COMMISSIONER TRANSPORT - Appellant
Versus
BSC-C&C JV - Respondent
FAO(OS)(COMM) 63 of 2017, C.M. APPL.10138-10139 of 2017
Decided on : 12-05-2017
Subject
Arbitration Law - Award
Act Referred
Headnote
Arbitration and Conciliation Act, 1996 - Section 34, 37 - Arbitration - Bid - Delay in work - Contractor was the highest and the successful bidder for the work - Its bid was accepted - Contractor claimed certain amounts - Claims were rejected - Disputes were referred to Arbitration - Commissioner was held primarily responsible for the delay in completion of the work - Arbitral tribunals ascribe delays to the Commissioner - These are pure findings of fact - Commissioner's argument in appeal is that price variation benefit or advantage was given to the contractor - Engineer failing to issue specifications, drawings, instructions required for execution of works on time - Contractor proved these omissions - Opinion of single judge is justified - Held, arbitral tribunal's findings are manifestly unreasonable - Impugned judgment does not call for interference - Appeal is dismissed.
For the Appellant :Sh. Sanjay Jain, ASG with Sh. Gautam Narayan, ASC (Civil), Sh. R.A. Iyer, Ms. Rhea Verma and Ms. Natasha Thakur, Advocates, Sh. Vijender Kumar, Deputy Commissioner (Transport)
For the Respondent:Sh. Navin Kumar, Ms. Rashmeet Kaur and Ms. Arpana Majumdar, Advocates.
S. RAVINDRA BHAT, J.
1. Complaining that a learned single judge erred in refusing to interfere with the award of an arbitral tribunal, the Commissioner, Transport of the Government of NCT of Delhi (hereafter “Commissioner”) preferred this appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (“the Act”). The impugned judgment rejected the Commissioner’s objections under Section 34 of the Act to an Award dated 14th December 2015 issued by a sole Arbitrator in its disputes with the respondent (hereafter “BSC-C&C JV”or “the contractor”), a joint venture between BSCPL Infrastructure Limited and C&C Construction Ltd. The dispute arose from a contract awarded to the claimant concerning "construction of works related to widening/modification of roads to create multiple lanes of existing carriageway for High Capacity Bus System (HCBS) between Ambedkar Nagar to Delhi Gate covering a distance of 14 kilometres" (hereafter “the work” or "the contract").
2. The contractor was the highest and, therefore, was the successful bidder for the work; its bid was accepted on 1st August, 2006. The date of commencement of work under the contract was 5th September, 2006. It was to be completed in fifteen months, i.e. by 7th December, 2007. The actual date of completion was 26th November 2009. The contractor claimed certain amounts; these claims were rejected by the Commissioner’s engineer. It then approached the Dispute Resolution Expert (DRE) whose recommendations were not accepted by the Commissioner. The disputes were, therefore, referred to Arbitration.
3. The contractor claimed, before the arbitrator that the delay in completion of the project was solely attributable to the Commissioner resulting in time overrun and that it incurred consequent additional costs and losses. It claimed breaches of contract by the Commissioner, such as delay in handing over of the complete site on the start date, delay in issuance/approval of drawings and designs; non-clearance of hindrances throughout the worksite; large scale frequent changes in designs, specifications and scope of the work by the Engineer; failure to supply control points; stoppages of work by the Engineer, his instructions to delay the work and wrongful withholding of rightful dues leading to cash flow problems.
4. The Commissioner’s defence in the arbitral proceedings was that despite extension of time (EOT) without levy of liquidated damages (LD), clause 27 of the conditions of contract required the contractor to execute the work in terms of the agreed programme. The Commissioner complained that the contractor deliberately avoided upgrading the programme and resource planning, in spite of the Engineer’s reminders. The Commissioner alleged that the campsite was handed over to the contractor on 08.09.2006, not on 08.09.2007 as claimed by the contractor.
5. In the award, the Arbitrator, on the pleadings and materials on record, concluded that (a) the pre-bid documents and minutes of meeting showed that the full site was not with the Commissioner at the start of work; (b) that the Commissioner did not mention the date on which the entire site was handed over to the contractor. (c) The Commissioner’s argument that the contractor was responsible for clearing encroachments and hindrances and for shifting of the public utilities by coordination with other government departments was misplaced; (d) the Commissioner’s submission with regard to discharge of its obligation on payment of the item of work pertaining to site clearance was incorrect; (e) there was an implied term that work drawings would be submitted in a timely manner and changes would be indicated within reasonable time, because time was the governing factor and there was a stipulated period on which the contractor’s rates were based. The Commissioner did not make the full site available to the contractor at the start of the work; also it made frequent change in drawings leading to time wastage; (f) the contractor tried