SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2018 Supreme(Del) 755

IN THE HIGH COURT OF DELHI AT NEW DELHI
YOGESH KHANNA, J.
M/s Prestress Wire Industries – Petitioner
Versus
M/s Uppal Builders Pvt. Ltd. – Respondent
O.M.P. No. 1588 of 2014 and I.A. No. 13751 of 2017
Decided On : 09-02-2018

Advocates Appeared:
For the Petitioners: Mr. Ankit Anandraj Shah, Mr. Vivek R. Mohanty, Ms. Priyadarshini Patnaik.
For the Respondent: Mr. L.B. Rai, Mr. Syed Kamran Ali.

The court emphasized that it would not re-examine the facts of an arbitral award unless specific grounds for challenge are present under section 34(2) of the Act.

Headnote:

Arbitration and Conciliation Act 1996 - Construction Dispute - Section 34

Fact of the Case:

The petitioner challenged an arbitration award related to a construction project. Disputes arose regarding the construction work, payments, and additional items of work. The arbitrator made decisions on various claims including compensation for increase in construction costs and interest rates.

Finding of the Court:

The court found that the arbitrator's award was reasoned and based on the agreements. The court dismissed the petition and ordered the petitioner to pay the entire costs.

Issues: Disputes over payments, additional work, compensation for increased construction costs, and interest rates.

Ratio Decidendi: The court upheld the arbitrator's award and stated that it would not sit in appeal over the award of an arbitral tribunal unless there are specific grounds mentioned in section 34(2) of the Act to challenge the award.

Final Decision: The petition was dismissed, and the petitioner was ordered to pay the entire costs within four weeks.

JUDGMENT :

YOGESH KHANNA, J.

1. This petition is under section 34 of the Arbitration and Conciliation Act 1996 (hereinafter referred as ‘the Act’) challenging the award dated 17.04.2017 passed by the sole arbitrator.

2. Vide an agreement dated 24.01.2009 M/s Prestress Wire Industries (the petitioner herein) had awarded the work of construction of factory building at Bajpur vide agreement dated 24.01.2009 amounting to Rs. 2,28,00,000/- to the contractor/the respondent herein who reduced its bid by 6.7% discount. Certain disputes arose between the parties and an arbitrator was appointed. The statement of claim was filed on 09.08.2012 and the statement of defense was filed on 04.12.2012. The claimant submitted its rejoinder on 26.02.2013 and evidence was recorded and thereafter an impugned award was given.

3. The stipulated date of commencement of work was 21.01.2009 and the stipulated time for completion was 180 days plus 15 days for additional mobilization.

4. The layout drawings of the work were issued on 14.03.2009, the foundation details on 19.03.2009 and hence the date of start of the work was 03.02.2009. Further tiles were asked to be provided in foundation as an additional item of work. There was a shortage of cement and steel which was later arranged and the shortage of labour and other resources on the part of the claimant.

5. Qua allowing of claim No. 1 of the respondent the petitioner has urged the details of the final bill given in annexure C-6 are not admitted as were never received by them and was not signed by the Architect of the respondent. Rather relying upon the details of the final bills given in the letter of the Architect dated 12.10.2012 anneuxre R-23 it is stated no other payment was due to the claimant and that over payments have been made. It is urged by the learned counsel for the petitioner the tender of the claimant was not the lowest, but was accepted after the claimant had agreed to reduce the tender amount by allowing rebate of 6.7%. The respondent urges the rebate was conditional to execution of both the works by the claimant viz. this work and a similar work for the sister concern of the respondent- M/s. Sidhi Ferrous, but such rebate was never agreed to and accordingly no such condition is stipulated in the agreement. However, the learned arbitrator has decided this claim as under:-

“..........Admittedly all the running bills were paid after deducting the rebate, which were all along accepted by the claimant. It is added that as late as on 05.05.2010 (Exh.R/21), the claimant confirmed/admitted the account statement of the 5th Running bill accounting for the rebate. Further, since there is no stipulation in the contact agreement as to the rebate being conditional to the execution of both the works by the claimant, the rebate can't be denied in this work to which this arbitration relates.

As per the admission/denial of the documents, the respondent has denied receipt of the final bill submitted by the claimant at Annex. C-6, and the claimant has denied the cover page of the final bill at Annex. R/23 while the rest of the details as on pg 60 to 69 of Annex. R-23 are accepted, which incidentally are practically the same as at Exh.C/6. It is seen that the cover page of Annex. R-23 is the letter from the Architect addressed to the respondent, giving summary of the final bill. The letter is signed by the Architect.

Admittedly, amount of .the total work done comes to Rs. 3,42,59,951/- (Rs. 3,02,67,908/- on account of work as per tender items plus Rs. 39,92,043/- for extra items) and after adding 33% of 10.3% service tax (payable to the claimant as per terms of the contract) on the total amount of Rs. 3,42,59,951/- gross amount of the work comes to Rs. 3,54,24,447/-.

Recovery on account of steel and cement stands at Rs. 1,12,35,051/- and a total payment of Rs. 2,15,80,666/- has earlier been received by the


































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top