IN THE HIGH COURT OF DELHI AT NEW DELHI
VIBHU BAKHRU, J.
MRT SIGNALS LIMITED - Petitioner
Versus
JMC PROJECTS (INDIA) LIMITED & ANR. - Respondents
O.M.P. (COMM) 186 of 2018 & IA Nos. 5851 of 2018 & 5852 of 2018
Decided On : 01-05-2018
Arbitration - Joint Venture Dispute - Arbitration and Conciliation Act, 1996, Section 34 - 4.4(b), 4.4(g), 4.5 - The court discussed the disputes arising from the joint venture agreements for submitting bids in response to tenders invited by Rail Vikas Nigam Limited (RVNL) and the consequences of submitting a false affidavit as per the tender conditions. The court upheld the arbitral award of Rs. 4.05 crores in favor of the respondents, including the forfeiture of bid security and cost for preparing the bids.
Fact of the Case:
The dispute arose from the joint venture agreements for submitting bids in response to tenders invited by Rail Vikas Nigam Limited (RVNL). The petitioner contested the forfeiture of bid security and cost for preparing the bids by RVNL due to the submission of a false affidavit.
Finding of the Court:
The court upheld the arbitral award of Rs. 4.05 crores in favor of the respondents, including the forfeiture of bid security and cost for preparing the bids, stating that the consequences for furnishing an inaccurate affidavit must be borne by the petitioner.
Issues: Dispute over forfeiture of bid security and cost for preparing the bids due to the submission of a false affidavit.
Ratio Decidendi: The court found that the petitioner had furnished an incorrect affidavit, leading to the forfeiture of bid security, and upheld the arbitral award in favor of the respondents.
Final Decision: The petition was dismissed as unmerited, and the arbitral award in favor of the respondents was upheld.
VIBHU BAKHRU, J.
1. The petitioner has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereafter 'the Act'), inter alia, impugning the arbitral award dated 05.01.2018 (hereafter 'the impugned award') delivered by the Arbitral Tribunal constituted by the sole arbitrator, Justice V.K. Shali (Retired) (hereafter 'the Arbitral Tribunal').
2. The impugned award was rendered in the context of the disputes that had arisen between the parties in respect of the two separate agreements – captioned as "Memorandum of Understanding" (MOU) – entered into between the parties to form a joint venture in the name of "JMC–KPTL– MRTL (JV)" for submission of the bids in response to the tenders invited by Rail Vikas Nigam Limited (RVNL).
3. Briefly stated, the controversy arises in the following context :-
3.1 On 02.09.2014, RVNL had invited bids for construction of roadbed, bridges, supply of ballast, installation of track excluding supply of rails, electrical (General Electrification) signalling and telecommunication works in Ahmedabad Division of Western Railway, Gujarat. The said tenders were invited for two separate packages referred to as “Package No.1” and “Package No.2”. Package No.1 was related to doubling of the tracks between Samakhyati and Kidiyanagarh (34.66 Km) in the Ahmedabad Division of the Western Railways, Gujarat and Package No.2 related to doubling of track between Bhildi and Diyodar (29.48 Km) in the Ahmedabad Division of Western Railways.
3.2 The tender documents floated by RVNL permitted a consortium to bid for the contracts subject to certain conditions. As stated above, the parties entered into two separate MOUs for forming a consortium for submitting bids and performing the works in respect of the afore-mentioned two packages, for which tenders were invited by RVNL. Respondent No.1 was the lead member of the consortium in terms of the MOUs entered into between the parties.
3.3 The tender documents expressly provided that bidders would be disqualified if any previous contract of the bidder or any of its constituents had been terminated by RVNL within a period of two years prior to the deadline for submission of the bids. Clause 4.4(b) and Clause 4.4(g) of the tender documents floated by RVNL are relevant and are set out below :-
Clause 4.4(b)
“(b) Any previous contract of the bidder or any of its constituents had been terminated for contractor's failure by Rail Vikas Nigam Ltd (RVNL) any time starting from 2 years before the deadline for submission of bids and up to the day before opening of price bids.”
Clause 4.4(g)
“(g) The Bidder shall submit an affidavit stating that they are not liable to be disqualified as per this sub clause using the appropriate Performa given in Section 4. Non-submission of an affidavit by the bidder shall result in summary rejection of his bid.”
3.4 Further, in terms of Clause 4.5 of the tender documents, RVNL was entitled to forfeit the bid security in the event the bidder had submitted a false affidavit. Clause 4.5 of the tender documents is quoted below :-
“4.5 Bidder shall immediately inform the Employer in case they cease to fulfill eligibility in terms of ITB 4.3 & 4.4. In case the bidder fails to inform the Employer or submits a false affidavit his bid shall be summarily rejected and bid security shall be forfeited. The bidder shall also be liable for Banning of Business dealings for a period up to five years.”
3.5 Respondent No.1, being the lead member had submitted the bid security in the form of bank guarantees: a bank guarantee in the sum of Rs. 2 crores was provided as bid security for tender submitted in respect of Package No. 1 and a bank guarantee in the amount of Rs. 1.9 crores was provided as a bid security for Package No.2.
3.6 Respondent no.1 received a letter dated 18.12.2014 issued by RVNL, inter alia, stating that a contract awarded to IVRCL – MRT (JV) dated 13.08.2012 was terminated on 01.10.2013; therefore, the Consortium [JMC – KPTL –
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.