IN THE HIGH COURT OF DELHI AT NEW DELHI
VIBHU BAKHRU, J.
ARVIND TECHNO ENGINEERS PVT LTD - Petitioner
Versus
DELHI METRO RAIL CORPORATION - Respondent
O.M.P. (COMM) 247 of 2017
Decided On : 22-05-2018
Arbitration and Conciliation Act - Design and Construction Contract - 34 - 2.1.5(n), 2.3, 2.5.2
Fact of the Case:
The petitioner challenged an arbitral award rejecting their claims for additional costs incurred due to variation in soil strata encountered during the execution of a construction contract.
Finding of the Court:
The court found that the claims for additional expenditure were contrary to the express terms of the Agreement, which specified that no claim for additional payment would be permissible on account of differences in the sub soil strata actually encountered and those indicated in the tender documents.
Issues: Dispute over additional costs incurred due to variation in soil conditions, interpretation of contract terms, and applicability of the Arbitration and Conciliation Act.
Ratio Decidendi: The court upheld the impugned award, emphasizing the express terms of the Agreement that precluded claims for additional payment due to discrepancies in soil conditions and ground levels as indicated in the tender documents.
Final Decision: The petition was dismissed, and the parties were left to bear their own costs.
VIBHU BAKHRU, J.
1. The petitioner has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereafter 'the Act'), inter alia, impugning the arbitral award dated 18.01.2017 (hereafter 'the impugned award') delivered by the Arbitral Tribunal comprising of three arbitrators, namely, Sh. Jagdish Kumar (Presiding), Sh. R.K. Yadav and Sh. Ajay Sharma (hereafter 'the Arbitral Tribunal').
2. The impugned award was rendered in the context of disputes that had arisen between the parties in relation to the contract for execution of the work of Design and Construction of main viaduct, Ramp on both sides, Mukundpur Elevated station including Architectural Finishing Works, Auto Coach Washing Plant Platform and Entry/Exist line to Mukundpur Depot (Scope of work starts from Ch.334.65 M) on Mukundpur-Yamuna Vihar Corridor (Line-7) of Phase-III, Delhi. By the impugned award, the Arbitral Tribunal has rejected all claims made by the petitioner for additional costs incurred on account of variation in soil strata as indicated in tender documents as encountered by the petitioner. The petitioner had claimed that it had incurred additional costs, inter alia, on the ground that subsequent soil investigation indicated that the first ten meter of the soil was much weaker than as indicated in the report forming part of the tender documents and, therefore, the petitioner had to incur additional expenditure for reinforcement of concrete and for taking other measures. The Arbitral Tribunal rejected the same on the ground that the contract between the parties expressly provided that the contractor would carry out an independent investigation of the soil and no claim whatsoever on account of discrepancy between the sub surface condition, as actually encountered and as provided in the tender documents, would be entertained.
Factual Background
3. On 02.01.2013, the respondent (hereafter 'DMRC') awarded the work of “Design and Construction of main viaduct, Ramp on both sides, Mukundpur Elevated station including Architectural Finishing Works, Auto Coach Washing Plant Platform and Entry/Exit line to Mukundpur Depot (Scope of work starts from Ch.334.65M) on Mukundpur-Yamuna Vihar Corridor (Line-7) of Phase-III Delhi” (hereafter 'the works'). The value of the works was estimated at Rs. 125 crores and it was awarded to the petitioner at a contract value of Rs.123,40,44,611/-. The works were commenced on 07.01.2013 and the stipulated date of completion was fixed to be 31.05.2016.
4. The parties entered into an agreement for the aforesaid contract on 12.02.2013 (Contract no.CC-14) (hereafter 'the Agreement').
5. Tender documents were available till 16.08.2012 and the tender for the work was to be submitted by 15.09.2012 (subsequently revised to 17.09.2013). The tender documents also included a geo technical report as to the soil conditions.
6. On 11.12.2013, the petitioner sent a letter to DMRC stating that the soil data provided in the tender documents did not match the soil investigation report received by the petitioner, which showed that the first ten meters of the soil was much weaker than what was indicated in the soil report forming a part of the tender documents.
7. DMRC responded on 23.12.2013 refuting the claims made by the petitioner in its letter dated 11.12.2013 and further referring to Clause no. 2.1.5(n) and 2.3 of the Agreement. Thereafter, the petitioner invoked the arbitration clause and the Arbitral Tribunal was constituted. The Arbitral Tribunal held a preliminary hearing on 03.09.2015. At the hearing, the parties agreed that the oral evidence was not required and the arbitration be conducted on the basis of documentary evidence provided by the parties.
8. The arbitral proceedings culminated in the impugned award.
9. The petitioner had set up a case that the time period provided for carrying out soil investigation was a month and this did not afford any of the bidders an opportunity to carry out the soil invest
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.