SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2018 Supreme(Del) 2150

IN THE HIGH COURT OF DELHI AT NEW DELHI
NAVIN CHAWLA, J.
Union of India Through: Its Secretary - Petitioner
Versus
Intercity Cables Pvt. Limited - Respondent
OMP (COMM.) 429 of 2018
Decided On : 09-10-2018

Advocates Appeared:
For the Petitioners: Mr. Dinesh Agnani, Sr. Adv. with Mr. L.B. Rai, Mr. Mohit Kumar Sharma, Ms. Disha Singh, Advs.
For the Respondents: Mr.Sachin Datta, Sr. Adv. with Ms.Kanika Sinha, Mr.Tanmaya Sinha, Advs.

The interpretation of the contract by the Arbitrator and findings based on evidence cannot be interfered with unless found to be perverse or unreasonable.

Headnote:

Arbitration - Challenge to Arbitral Award - Arbitration and Conciliation Act, 1996 - Section 34 - Clause 4 of the General (Commercial) Conditions of Contract - Kailash Nath Associates vs. Delhi Development Authority & Anr. (2015) 4 SCC 136

Fact of the Case:

The petitioner filed a petition challenging the Arbitral Award, which found the respondent in breach of the Agreement but held that the petitioner was not entitled to retain the proceeds of the Performance Bank Guarantee en-cashed by it due to lack of proof of loss suffered.

Finding of the Court:

The court found that the Arbitrator's interpretation of the contract and the finding based on evidence cannot be interfered with unless found to be perverse or unreasonable, and thus dismissed the petition.

Issues: Challenge to Arbitral Award under Section 34 of the Arbitration and Conciliation Act, 1996

Ratio Decidendi: The court upheld the Arbitrator's interpretation of the contract and the finding based on evidence, citing Kailash Nath Associates vs. Delhi Development Authority & Anr. (2015) 4 SCC 136.

Final Decision: The petition was dismissed with no order as to costs.

JUDGMENT :

NAVIN CHAWLA, J.

IA 13972/2018

Exemption allowed subject to all just exceptions.

OMP (COMM) 429/2018 & IA 13971/2018

1. This petition under Section 34 of the Arbitration and Conciliation Act, 1996(hereinafter referred to as the ‘Act’) has been filed by the petitioner challenging the Arbitral Award dated 25.07.2018 passed by the Sole Arbitrator adjudicating the disputes that have arisen between the parties in relation to the Advance Purchase Order dated 25.09.1995 and the subsequent Purchase Order dated 23.02.1996 for supply of Optical Fibre Line Terminating Equipment (PDH) placed by the petitioner on the respondent.

2. The Arbitrator by the Impugned Award has found that the respondent had failed to make the supplies in terms of the Purchase Order. The Arbitrator further held that the excuse of the respondent that it was not able to make the supplies for lack of response from the petitioner to its proposal for entering into a collaboration with another company was unjustified. Therefore, the respondent was found to be in breach of the Agreement, that is, the Advance Purchase Order and the consequent Purchase Order placed by the petitioner on the respondent.

3. At the same time and in spite of this finding, the Sole Arbitrator had held that as the petitioner was unable to prove any loss suffered by it due to this breach of the Agreement, it was not entitled to retain the proceeds of the Performance Bank Guarantee en-cashed by it and has ordered a refund of the said proceeds along with interest @9% per annum with effect from the date of encashment of the Bank Guarantee till realization. The Arbitrator has also awarded costs assessed at Rs.3 lacs in favour of the respondent.

4. The learned senior counsel for the petitioner relying upon clause 15.2 of the General (Commercial) Conditions of Contract submits that incase of a delay by the supplier in the performance of its delivery obligations, the petitioner was entitled to inter alia forfeit the performance security. As the Arbitrator has found the respondent to be in breach of its performance obligations, the Performance Bank Guarantee was rightly en-cashed and forfeited by the petitioner. In such circumstances, the petitioner was not required to prove any loss being suffered by it due to such breach of the contract by the respondent.

5. I am unable to agree with the said submission of the learned senior counsel for the petitioner. In the present case, a few terms of the contract would be relevant to answer the said submission. Clause 4 of the General (Commercial) Conditions of Contract reads as under:-

4. PERFORMANCE SECURITY:

4.1 The supplier shall furnish performance security to the purchaser for an amount equal to 5% of the value of each purchase order upto Rs.4 Crores and 2% for every additional one crore of purchase order limited to maximum to one crore based on the quantity proposed to be procured against the purchase order.

4.2 The proceeds of the performance security shall be payable to the Purchaser as compensation for any loss resulting from the Supplier’s failure to complete its obligations under the Contract.

4.3 The Performance Security Bond shall be in the form of a bank guarantee issued by a Scheduled Bank and in the form provided in the Bid Document, Section IX.

4.4 The performance security Bond will be discharged by the Purchaser after completion of the Supplier’s performance obligations, including any Warranty obligations, under the Contract.”

(Emphasis Supplied)

6. A reading of clause 4.2 would clearly show that the proceeds of the performance security are to be adjusted against any loss resulting from the supplier’s failure to complete its obligations under the contract. The same is also evident from the terms of the Performance Bank Guarantee itself, which is quoted herein under:

“We State Bank of India do hereby undertake to pay the amounts due and payable under this guarantee without any demur, merely on a demand from the Government stating that the amount claimed

























Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top