2018 Supreme(Del) 2424

IN THE HIGH COURT OF DELHI AT NEW DELHI
RAJIV SHAKDHER, J.
RATTAN POLYCHEM PVT. LTD. & ANR. - Petitioners
Versus
RELIABLE INSUPACKS PRIVATE LIMITED & ORS. - Respondents
ARB.P. 489 of 2018
Decided on : 28-08-2018

Important Points

The main legal point established in the judgment is that the existence of an arbitration agreement between the parties warrants the appointment of an Arbitrator, and that contentions regarding fraud and pending NCLT action do not preclude the appointment of an Arbitrator.

Subject

Arbitration Law - Appointment of Arbitrator

Act Referred

ARBITRATION AND CONCILIATION ACT : S.11, S.9

Headnote

Arbitration - Appointment of Arbitrator - Arbitration and Conciliation Act, 1996 - Section 11

Fact of the Case:

The petitioners sought appointment of an Arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996, praying for the appointment of an Arbitrator due to a dispute arising from money advanced to respondent no.1 company and subsequent disagreements regarding share transfer and control of the company.

Finding of the Court:

The court found that a dispute existed between the parties and that the appointment of an Arbitrator was warranted. The court also noted that the respondents' contentions were unsustainable and that the appointment of an Arbitrator could not be denied solely on the ground of a pending oppression and mismanagement action in the NCLT.

Issues: The main issues revolved around the dispute regarding money advanced, share transfer, and control of the respondent no.1 company, as well as the respondents' resistance to the appointment of an Arbitrator.

Ratio Decidendi: The court held that the existence of an arbitration agreement between the parties warranted the appointment of an Arbitrator, and that the respondents' contentions regarding fraud and pending NCLT action were unsustainable.

Final Decision: The court appointed Mr. Manmohan Sarin as an Arbitrator and allowed the petition, with the order binding only the petitioners and respondent no.1 to 4.

Advocates:
Advocate Appeared:
For the Appellant : Mr. Rakesh Kumar and Mr. Hetish Raj Singh, Advs.
For the Respondent: Mr. Vinay Shukla, Adv.

JUDGMENT :

RAJIV SHAKDHER, J.

1. This is a petition filed under Section 11 of the Arbitration and Conciliation Act, 1996.

2. The petitioners pray for appointment of an Arbitrator.

3. Notice in this petition was issued on 13.7.2018, when on behalf of respondent no.2, Ms. Parul Agrawal accepted notice. While on behalf of respondent nos. 3 to 6, Mr. Shukla accepted notice.

4. An opportunity was given to the aforementioned counsel to file their replies in the matter.

5. Unfortunately, respondent no.2 is not represented today.

6. Insofar as respondents no.2 to 6 are concerned, no reply has been filed, though Mr. Shukla is present in Court.

7. Given this situation, there is, in fact, on record, no rebuttal to the assertions made in the petition.

8. Broadly, the case of the petitioners appears to be that in and about 16.11.2016 money was advanced to respondent no.1 company. Against the money advanced, a pledge was created qua plant and machinery, and receivables as also stocks were hypothecated.

9. It is the petitioners’ stand that respondent no.1 company owed a sum of Rs.2,13,12,822/- to the petitioners; a claim which was made subject matter of a Memorandum of Understanding dated 3.2.2018 (hereafter referred to as the 1st MOU).

10. Concededly, the 1st MOU did not fructify and that, according to the petitioners, was overridden by the MOU dated 15.2.2018 (hereafter referred to as the 2nd MOU).

11. Broadly, under the 2nd MOU, respondents no.2 to 6, according to the petitioners, had agreed to transfer 100% equity stake held by them in the 1st respondent company in favour of the petitioners.

12. Resultantly, according to the petitioners transfer forms were executed and valuation of the shares was got done in pursuance of the 2nd MOU.

13. The valuer, so appointed, rendered his report, which is dated 30.3.2018. As per the valuer, the subject shares were worth Rs.15,25,000/-.

14. Respondent no.2 to 6 appear to dispute the valuation. Respondent no.2 to 6 are also aggrieved by the fact that the petitioners have not defrayed unsecured loans. These grievances have been communicated to the petitioners via an email dated 4.4.2018.

15. Besides the aforesaid, it appears that respondent No. 2 to 6 have also filed a criminal complaint against the petitioners. The complaint was evidently filed in and about 11.4.2018. The burden of the criminal complaint is that the petitioners have illegally acquired control of the 1st respondent company.

16. A cross-criminal complaint has been filed by the petitioners, perhaps, as a reaction to the complaint lodged by respondent No. 2 to 6.

17. This apart, respondent no.3 to 6, I am told by Mr. Shukla, have approached the NCLT. The petition preferred by respondent no.3 to 6 is an oppression and mismanagement action.

18. I may also indicate that this Court, in a petition preferred under Section 9 of the 1996 Act, has passed an order dated 22.5.2018. The relevant part of that order is extracted hereafter:

“.......It is the case of the petitioners that the respondent no. L owed a sum of approximately Rs.2.35 crores on account of supply of raw material made by the petitioner to the respondent no. L. As the respondent no. L was not in a position to pay the said amount, a Memorandum of Understanding (MOU) dated 3rd February, 2018 was executed between the petitioner and respondent no. 1. Respondent no. L was being represented by the respondent no.2 who was its Director. In terms of the said MOU, 55% of the shareholding of the respondent no. L was to be bought by the petitioner at a value or Rs.35 per share. The money received from the petitioners was to be ploughed back in the company to re-pay the dues of the petitioners. It was a term of the Agreement that the respondent no. L shall pay interest @ 1% in monthly instalments of Rs.11 lacs each till the entire outstanding of the petitioner is settled.

Another MOU was executed between the petitioner and the respondent no.1 on 15th February, 2018 in terms whereof the petitioners agreed to acquire