2018 Supreme(Del) 2566
IN THE HIGH COURT OF DELHI AT NEW DELHI
VALMIKI J.MEHTA, J.
JALANDHAR PANDIT - Appellant
Versus
DSC LIMITED - Respondent
RFA No.826 of 2018
Decided on : 01-10-2018
Important Points
Subject
Civil Law - Recovery of Moneys
Act Referred
Headnote
CIVIL PROCEDURE - Recovery of Moneys - Section 96 of CPC - [Section 96 of CPC] - The court dismissed the suit for recovery of moneys filed by the appellant/plaintiff, as the appellant/plaintiff failed to prove the value of work done and the measurements of the work done, and did not provide details of the work performed and the payment outstanding against the defendant.
Fact of the Case:
The appellant/plaintiff filed a suit for recovery of moneys claimed to be due for civil works done for the respondent/defendant. The trial court dismissed the suit as the appellant/plaintiff failed to prove the value of work done and the measurements of the work done.
Finding of the Court:
The trial court dismissed the suit, stating that the appellant/plaintiff failed to prove the value of work done and the measurements of the work done, and did not provide details of the work performed and the payment outstanding against the defendant.
Issues: The main issue was whether the appellant/plaintiff was entitled to recover the claimed amount for civil works done for the respondent/defendant.
Ratio Decidendi: The appellant/plaintiff failed to provide sufficient evidence to prove the value of work done and the measurements of the work done, and did not provide details of the work performed and the payment outstanding against the defendant.
Final Decision: The suit for recovery of moneys filed by the appellant/plaintiff was dismissed by the trial court.
Advocate Appeared:
For the Appellant :Mr. Triloki Pandit, Advocate
VALMIKI J. MEHTA, J.
C.M. No.40430/2018(exemption)
1. Exemption allowed subject to just exceptions.
C.M. stands disposed of.
C.M. No.40431/2018(for condonation of delay)
2. For the reasons stated in the application, delay of 110 days in re-filing the appeal is condoned subject to just exceptions.
C.M. stands disposed of.
RFA No.826/2018
3. This Regular First Appeal under Section 96 of the Code of Civil Procedure, 1908 (CPC) is filed by the plaintiff in the suit impugning the Judgment of the Trial Court dated 17.07.2017 whereby trial court has dismissed the suit for recovery of moneys filed by the appellant/plaintiff. By the suit the appellant/plaintiff claimed an amount of Rs. 7,38,060/- alongwith interest for civil works done said to be done by the appellant/plaintiff for the respondent/defendant.
4. The facts of the case are, that the three work orders are pleaded to have been awarded to the appellant/plaintiff by the respondent/defendant for doing the work of concreting, shuttering and scaffolding, water bar fixing, PCC, RCC and other miscellaneous works. The three work orders issued by the respondent/defendant to the appellant/plaintiff are dated 11.01.2010, 16.03.2010 and 08.06.2010. The works which were to be done were for the project awarded to the respondent/defendant, being the Main Drain at Pochanpur/Sector 23, Dwarka, New Delhi. The appellant/plaintiff claimed that it has done work of Rs. 12,39,530.33/- for the work order dated 11.01.2010, Rs.75,852.80/- for the work order dated 16.03.2010 and Rs. 1,20,960/- for the work order dated 08.06.2010. The total amount of work done was therefore for Rs. 14,36,343.13/-. After the respondent/defendant made certain deductions, which were admitted by the appellant/plaintiff, the appellant/plaintiff claimed that a sum of Rs. 4,42,012.93/- remained due from the respondent/defendant to the appellant/plaintiff, and this amount alongwith interest was claimed in the suit after serving the Legal Notice dated 23.06.2014.
5. The respondent/defendant contested the suit and pleaded that the appellant/plaintiff did not complete the work assigned under the work orders and in fact had abandoned the work. It was pleaded that at the time of abandoning the work, the appellant/plaintiff had with him various materials issued from the store of the respondent/defendant on use and return basis. The said material was appropriated by the appellant/plaintiff without giving the details of the use of the same. It was also pleaded by the respondent/defendant that the value of work pleaded to have been done by the appellant/plaintiff has actually not been done. The suit was therefore prayed to be dismissed.
6. After the pleadings were complete, the trial court framed the issues and parties led evidence. These aspects are recorded in paras 7 to 9 which read as under:-
“7. Thereafter the case proceeded for framing of issues. On the pleadings of the parties, following issues were framed:-
ISSUES
1. Whether the suit is bad for mis-joinder of cause of action? OPD
2. Whether the plaintiff is entitled to decree in the sum of Rs. 7,38,060, along with interest? OPP
3. Relief.
8. Plaintiff has examined himself as PW-1 as sole witness and has proved on record following documents:-
1. Work order dated 11.01.2010 as Ex.PW1/1;
2. Certified copy of his bank statement as Ex.PW1/2;
3. Certificate given by SBI Ex.PW1/3;
4. Legal notice dated 23.06.2014 is Ex.PW1/4;
5. Speed postal receipts are Ex.PW1/5 (colly);
6. Internet tracking report Ex.PW1/6;
7. Envelope containing legal notice Ex.PW1/7.
9. On behalf of the defendant, one Sh. S.K. Gupta was examined and he was duly cross examined by defendant and thereafter defendant closed its evidence vide separate statement recorded on 09.05.2017. After that, case was proceeded for final arguments.”
7. The trial court has dismissed the suit by holding that the plaintiff had to prove the value of work done by him, as also the measurements of the work done by him, but the plaint is totally vague as