IN THE HIGH COURT OF DELHI AT NEW DELHI
Prathiba M. Singh, J.
Deepak Mehta – Appellant
Versus
Desh Bandhu Garg And Another – Respondents
Civil Miscellaneous (M) No. 296 of 2017, 755 of 2018; Civil Miscellaneous Application No. 26964 of 2018
Decided On : 29-08-2019
Collaboration Agreement - Property Dispute - Clause 20
Fact of the Case:
Dispute arose from a collaboration agreement between the Plaintiff and the builder regarding construction of property. The builder abandoned the work and executed a sale deed with a third party, leading to the Plaintiff seeking reliefs including cancellation of the sale deed and permission to complete the remaining construction.
Finding of the Court:
The Trial Court rejected the Plaintiff's application for permission to complete the construction, stating that the Plaintiff could only claim damages and compensation from the builder. The Court found a stalemate between the parties and granted permission to the Plaintiff to complete the construction of certain floors, while also allowing the third party to complete their floor, subject to the final decision in the suit.
Issues: The issues included the liability of the builder to pay monthly rent and other amounts, as well as the Plaintiff's entitlement to recover sums from the builder.
Ratio Decidendi: The Court interpreted the collaboration agreement and held that the Plaintiff had not given up or waived ownership rights in the property. It also granted permission to the Plaintiff to complete certain construction work, considering the stalemate between the parties.
Final Decision: The Court disposed of the petitions, allowing the Plaintiff to complete certain construction work and modifying the issues for adjudication by the Trial Court.
JUDGMENT :
Prathiba M. Singh, J.
Cm(M) 296/2017
1. The present petition arises out of order dated 23rd January, 2017. The genesis of the disputes between the parties is a collaboration agreement entered into by the Petitioner-Shri. Deepak Mehta who is also the Plaintiff in the suit (hereinafter "Plaintiff") on 15th March, 2013 with Shri Desh Bandhu Garg who is Defendant No.1 in the suit (hereinafter "builder"). As per the said collaboration agreement, the builder had agreed to construct the stilt parking on the ground floor, upper ground floor, first floor, second floor and third floor with automatic lift in property bearing no.1/11647, and New No. A-30, Built on Plot No.A-59, admeasuring 200 sq. yds. i.e. 167.22 sq. mtrs., out of Khasra no. 27, 28, 63, 92 to 97, 101, 481/102, 521/298-299, 448/26, 455/31, situated in the area of Village Uldhan Pur in the Abadi of Panchsheel Garden, Naveen Shahdara Delhi-110032 (hereinafter "suit property").
2. As per clause 1 of the agreement, the builder had to demolish the entire structure and construct the said floors at his own costs and expense after obtaining the sanctioned plans. The construction was to be completed within a period of 15 months. As a consideration for the construction, under the collaboration agreement, the rights in the third floor along with the roof rights were to vest with the builder and all the remaining floors were to be owned by the Plaintiff. The builder was to also pay a rent of Rs. 45,000/- per month to the Plaintiff during the period when the construction was ongoing. It was also agreed that the Plaintiff would execute a sale deed for the third floor in favour of any intending buyers, whom the builder may identify. It was, however, made clear that the possession of the third floor of the suit property was to be given only when the proposed building would be completed as agreed between the Plaintiff and the builder. The builder was permitted to dispose of his share in the suit property i.e. third floor with roof rights by way of a sale deed. Clause 20 of the agreement reads as under:
3. It is the case of the Plaintiff that the builder abandoned the work despite the fact that the third floor was permitted to be sold by the Plaintiff to a third party. The builder has executed a sale deed in favour of the third party who is Defendant No.2 Shri Hitendra Kumar Jain, vide sale deed dated 19th May, 2014. In order to enable the builder to execute the said sale deed, according to ld. counsel for the Plaintiff, the Plaintiff had executed a conditional sale deed on 4th April, 2014. It was, however, made clear that the possession would be handed over only after the entire building was completed. Since the builder had abandoned the premises and had also stopped paying the rent amount of Rs.45,000/- per month, the Plaintiff filed the suit seeking various reliefs including cancellation of the sale deed executed in favour of Defendant no.2, permanent injunction etc., The Plaintiff also moved an application seeking permission to complete the remaining construction in the suit property. The said application was disposed of vide the first impugned order dated 23rd January, 2017. The application was rejected by the ld. Trial Court on the ground that the only right of the Plaintiff is to seek compensation. The findings of the Trial Court read as under:
11. Perusal of the record further shows that plaintiff has stated in his plaint that defendant no. 1 fai
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.