2019 Supreme(Del) 2456
IN THE HIGH COURT OF DELHI AT NEW DELHI
JYOTI SINGH, J.
Bhubaneshwar Expressways Pvt. Ltd. - Petitioner
Versus
National Highways Authority of India - Respondent
O.M.P.(I) (COMM.) 218 of 2019
Decided On : 25-11-2019
Act Referred
CIVIL PROCEDURE CODE : O.2 R.2, O.39 R.1, O.39 R.2, O.38 R.5, O.18 R.5
SPECIFIC RELIEF ACT : S.38(3)(b)
Headnote
ARBITRATION - TERMINATION PAYMENT - CONCESSION AGREEMENT - SECTION 9 OF ARBITRATION AND CONCILIATION ACT, 1996 - APPLICATION FOR DIRECTION TO PAY 90% OF DEBT DUE AS TERMINATION PAYMENT - ARBITRAL AWARD - SPECIFIC RELIEF ACT, 1963 - SECTION 38(3)(B) - MANDATORY INJUNCTION - ESCROW ACCOUNT - INTEREST - BALANCE OF CONVENIENCE - INTERIM RELIEF - BANK GUARANTEE.
Fact of the Case:
Petitioner, a concessionaire, entered into a Concession Agreement with the respondent, NHAI, for four laning of a National Highway. The agreement contained an arbitration clause and a clause for Termination Payment in case of termination of the agreement. Disputes arose between the parties, and the petitioner invoked the arbitration clause. An arbitral tribunal was constituted, and the petitioner filed its statement of claim. The petitioner also filed an application under Section 17 of the Arbitration and Conciliation Act, 1996 (the Act) for an interim relief of Termination Payment. However, the application could not be heard due to the recusal of one of the arbitrators. The petitioner then filed the present petition under Section 9 of the Act seeking a direction to the respondent to pay 90% of the debt due as Termination Payment.
Finding of the Court:
The court held that the petitioner was entitled to 90% of the debt due as Termination Payment, even if the termination was due to the petitioner's default. The court also held that the respondent was liable to pay interest on the Termination Payment from the date of termination till the date of payment. The court further held that the petitioner was entitled to an interim relief of Termination Payment, as it had made out a prima facie case and the balance of convenience was in its favor. The court directed the petitioner to furnish an unconditional and irrevocable bank guarantee in favor of the respondent, and the respondent to deposit the Termination Payment in an escrow account.
Issues: 1. Whether the petitioner was entitled to 90% of the debt due as Termination Payment, even if the termination was due to the petitioner's default? 2. Whether the respondent was liable to pay interest on the Termination Payment from the date of termination till the date of payment? 3. Whether the petitioner was entitled to an interim relief of Termination Payment?
Ratio Decidendi: 1. The court held that the petitioner was entitled to 90% of the debt due as Termination Payment, even if the termination was due to the petitioner's default, based on the interpretation of the Termination Payment clause in the Concession Agreement. The court also relied on a previous judgment of a coordinate bench of the Delhi High Court in the case of Jetpur Somnath Tollways Limited vs. National Highways Authority of India, which had held that NHAI was liable to pay 90% of the debt due as Termination Payment, even if the termination was due to the concessionaire's default. 2. The court held that the respondent was liable to pay interest on the Termination Payment from the date of termination till the date of payment, based on the provisions of the Concession Agreement and the principles of equity. 3. The court held that the petitioner was entitled to an interim relief of Termination Payment, as it had made out a prima facie case and the balance of convenience was in its favor. The court considered the petitioner's financial hardship and the fact that the respondent had not disputed its liability to pay the Termination Payment.
Final Decision: The court allowed the petition and directed the respondent to pay 90% of the debt due as Termination Payment to the petitioner, along with interest from the date of termination till the date of payment. The court also directed the petitioner to furnish an unconditional and irrevocable bank guarantee in favor of the respondent, and the respondent to deposit the Termination Payment in an escrow account.
For the Petitioner:Mr. Sandeep Sethi, Senior Advocate with Mr. Abhyudai Singh, Mr. Sidhant Kumar and Mr. Sahil Tandon, Advs.
For the Respondent:Mr. Sudhir Nandrajog, Senior Advocate with Mr. C.S. Chauhan, Mr. Satish Kumar Mishra, Advocates
JUDGMENT :
Jyoti Singh, J.
1. The present petition has been filed under Section 9 of the Arbitration & Conciliation Act, 1996 (“Act”) seeking a direction to the respondent to pay/deposit an amount of Rs. 3,37,73,19,434.10/- which constitutes 90% of the debt due amount as per the provisions of Concession Agreement, along with interest on the aforesaid amount from the date of termination i.e. from 20.03.2017 till 90 days there from, at a rate 3% above the Bank rate and further interest till the date of actual payment at a rate of 5% above the Bank rate in terms of the provisions of the Concession Agreement.
2. Necessary facts for adjudicating the present petition are that the parties had entered into a Concession Agreement dated 13.07.2010 (hereinafter referred to as the “Agreement”) for four laning of Bhubaneshwar – Puri Section of National Highway 203 from KM 0.00 to KM 59.00 in the State of Odisha on a DBFOT basis. The said Agreement was amended by a supplementary agreement dated 17.08.2016. The parties entered into an Arbitration Agreement reflected in Article 44.3 of the Agreement and agreed to resolve their disputes by way of arbitration through Society for Affordable Redressal of Disputes (“SAROD”).
3. For the purpose of executing the project, the petitioner availed finance from various Banks and financial Institutions pursuant to a Loan Agreement dated 13.03.2011. The petitioner achieved Financial Closure on 13.01.2011 and the petitioner, respondent and PNB also executed a substitution agreement on 12.01.2011.
4. The estimated cost of construction and development of the project was initially Rs. 5,41,15,00,000/- and it was agreed to be financed through a loan of Rs. 244 Crores and Grant of by NHAI of Rs. 193.78 Crores.
5. It is the case of the petitioner that the respondent failed to provide encumbrance free site to the petitioner for development of the project and caused several delays in handing over the site. 80% of the site had to be made available as on the appointed date, whereas barely 25% was made available and complete site was handed over as late as in July 2015. The delays on the part of the respondent were observed by the Independent Engineer as well as the Project Director in the Regional office of the respondent and which is why they had approved the extension of time for completion of the project on two occasions viz. first by their letter dated 26.03.2014 upto 31.03.2015 and then upto 31.03.2016. The respondent had also delayed the appointment of the Independent Engineer beyond the period of 90 days from the execution of the Agreement.
6. It is the further case of the petitioner that the delay in completion of the project had severe cost implications for the petitioner including increase in costs of borrowing, mobilisation of manpower, machinery and resources, amount of interest payable etc. In fact, the petitioner and its lenders were compelled to infuse further funds of over Rs. 100 Crores to salvage the project and achieve completion, which was brought to the notice of the respondent. It is pleaded that despite all odds, the petitioner remained committed to the project and was able to achieve substantial completion to the extent of 80%. A provisional completion certificate was issued by the Independent Engineer on 20.08.2015. The Tolling operations began on 25.08.2015 but were stopped due to public agitation and even thereafter could be only partially resumed. The respondent even failed to procure support from the State Government to assist the petitioner in Toll collection.
7. The petitioner thereafter served a notice of default dated 06.01.2017 upon the respondent and made a claim of Rs. 4,45,00,00,000/- for the losses suffered on account of various breaches by the respondent. Eliciting no response from the respondent, the petitioner invoked the Arbitration Agreement. On receipt of the said notice, the r